ORDER

                                                                              Date of filing      : 12.03.2019                                                                     Date of disposal  : 09.12.2019

DISTRICT CONSUMER DISPUTES REDRESSAL FORUM, CHENNAI (SOUTH)

@ 2ND Floor, T.N.P.S.C. Road, V.O.C. Nagar, Park Town, Chennai-3.

 

PRESENT: THIRU. M. MONY, B.Sc., L.L.B, M.L.                     : PRESIDENT

TR. R. BASKARKUMARAVEL, B.Sc., L.L.M., BPT., PGDCLP.  :  MEMBER

 

C.C. No.63/2019

DATED THIS MONDAY THE 09TH DAY OF DECEMBER 2019

1. Mr. B.C. Vinayagam,

S/o. Mr. B. Chinnnakuppa Reddy,

No.13/6/2, Kulanthaivelu Street,

Purasaiwakkam,

Chennai – 600 007.    

 

2. Mrs. J. Kamatchi,

W/o. Mr. B.C. Vinayagam,

No.13/6/2, Kulanthaivelu Street,

Purasaiwakkam,

Chennai – 600 007.                                                     .. Complainants.

..Versus.. 

M/s. Dugar Housing Limited,

Rep. by its Managing Director,

Dugar Towers,

Old No.123, New No.34,

Marshalls Road,

Egmore,

Chennai – 600 008.                                                    .. Opposite party.

 

 Counsel for the complainants  : M/s. J. Dharmarajan & another

Counsel for the opposite party : M/s. K.V. Bhashyam Chari &

                                                     another

 

ORDER

THIRU. M. MONY, PRESIDENT

 

This complaint has been filed by the complainants against the opposite party under section 12 of the Consumer Protection Act, 1986 to handover the possession of the apartment which has been allegedly completed and ready for occupation by the complainant, to carry out the other works including the infrastructure and other amenities within a stipulated time, to comply with the statutory requirements including Registration of the Project and other compliances as per the Real Estate (Regulation and Development) Act, 2016, to pay the statutory interest of 10% on the amount already paid (i.e. Rs.70,62,732/-) for the delay in delivery of the apartment from 01.04.2016 till the date of delivery of the apartment, to reimburse the payments amounting to Rs.7,54,608/- (Rs.2,07,250/- + Rs.4,55,000/- + Rs.92,358/-) which were received by the opposite party towards the services / facilities which were promised but not provided by the opposite party and to pay a sum of Rs.5,00,000/- towards compensation for damages, pain, tension, inconvenience, frustration and mental agony and cost of proceedings to the complainant.

The complainant and Counsel made an endorsement.    In view of the endorsement, this complaint is dismissed as withdrawn with liberty to file a fresh case before the appropriate Forum.    No costs.

Dated this Monday the 09th day of December 2019.

 

 

MEMBER                                                                                                                                                                                                    PRESIDENT

 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.