View 8274 Cases Against Construction
Mr. Thyagarajan Arunachalam filed a consumer case on 12 Oct 2022 against M/s Bharath Building Construction in the South Chennai Consumer Court. The case no is CC/301/2018 and the judgment uploaded on 07 Feb 2023.
Date of Complaint Filed : 02.07.2018
Date of Reservation : 23.09.2022
Date of Order : 12.10.2022
DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION,
CHENNAI (SOUTH), CHENNAI-3.
PRESENT: TMT. B. JIJAA, M.L., : PRESIDENT
THIRU. T.R. SIVAKUMHAR, B.A., B.L., : MEMBER I
THIRU. S. NANDAGOPALAN., B.Sc., MBA., : MEMBER II
CONSUMER COMPLAINT No. 301/2018
WEDNESDAY, THE 12th DAY OF OCTOBER 2022
Mr. Thyagarajan Arunachalam Thevar,
No.17/1, 4th Main Road,
V.G.P Layout Part 1,
Palavakkam,
Chennai – 600 041. ... Complainant
..Vs..
M/s. Barath Building Construction (India) Pvt Ltd,
Rep. by its Chief Finance,
No.20, Mylai Ranganathan Street, T.Nagar,
Chennai – 600 017. ... Opposite Party
******
Counsel for the Complainant : M/s. R.N. Amarnath
Counsel for the Opposite Party : Exparte
On perusal of records and after having heard the oral arguments of the Complainants, we delivered the following:
ORDER
Pronounced by the President Tmt. B. Jijaa, M.L.,
1. The Complainant has filed this complaint as against the Opposite Party under section 12 of the Consumer Protection Act, 1986 and prays to direct the Opposite Party to pay a sum of Rs.4,80,000/- towards loss of rent and to pay a sum of Rs.2,00,000/- towards mental agony and delay in completion of Construction and to pay a sum of Rs.3,00,000/- towards hardship caused to the Complainant.
2. The averments of Complaint in brief are as follows:-
The Complainant’s parents are native of Tamil Nadu, doing business at Nasik, Maharashtra. The Complainant’s father is a Renal Transplant patient and requires regular medical check-up and consultation. The lack of medical facilities in Nashik and on their wish to settle down in their native the Complainant had taken house for rent at Palavakkam, Chennai. He came to know that the Opposite Party was promoting apartment at Thoraipakkam. When the Complainant approached the Opposite Party the Complainant was made to believe that the apartment will be completed and handed over around April 2016. Believing the promises made by the Opposite Party the Complainant made an advance payment for a sum of Rs.49,500/- on 25.02.2015. On payment of advance the Complainant was issued with an allotment letter for an apartment in E Block, 3rd Floor bearing Apartment No.3E with built up area of 1121 sq.ft along with undivided share of 531.79 sq.ft and one for car parking for a total sale consideration of Rs.63,25,859/-. The Complainant made further payment of Rs.49,500/-. Based on the advance paid and issuance of allotment letter, a memorandum of understanding was entered between the Opposite Party and the Complainant on 03.03.2015. As per clause 12 of the MoU the Construction of Apartment should be completed within a period of 24 months from the date of grant of approval of the building plan or by April 2016 whichever is later, with a grace period of 3 months. The Complainant had paid a sum of Rs.4,98,182/- and Rs.22,90,135/-. As per Annuxure-D of MoU the payments to be made at regular intervals. The Complainant was intimated with a status report on 05.01.2016, which had no information regarding Block E. The Complainant was also intimated with another status report on 22.04.2016 which had photographs of Block- E from which it is clear that the foundation work was started only on April 2016. On 30.11.2016 the Opposite Party demanded payment for stage 4 through email which is to be made on completion of the first floor slab. With regard to the said email the Complainant had sent an email on 01.12.2016 enquiring the date of completion of the construction and handing over possession, since they have already crossed the due date. Thereafter there was several communications between the Complainant and the Opposite Party regarding the completion of the Apartment and finally on 24.04.2017 the Opposite Party had demanded for a payment for 95% of the total sale consideration which arises only after completion of the construction of Apartment. Further as per clause 2.9 of the MOU it is clear that the allotee who availed loan is liable to pay only 55% of the total sale consideration for registration and the remaining amount to be paid stage wise. On 05.10.2017 a legal notice was sent to the Complainant regarding the delay in construction, for which no reply was sent by the Opposite Party. The Complainant received a mail on 15.03.2018 stating that the Opposite Party has completed the apartment and was issued with a completion certificate by the CMDA, which certificate is only to get electricity, sewage and water connection. On 15.03.2018 when the complainant visited the premises it was still in inhabitable condition. On 09.04.2018 the Complainant issued notice to the Opposite Party stating that the Opposite Party has not completed the building in a manner suitable for occupancy. By email dated 15.03.2018 the Opposite Party has demanded a sum of Rs.23,63,149/- which is bogus claim with interest as if the flat has been completed and ready to be occupied. The Complainant has suffered loss due to delay in completion of construction and had to pay Rs.25,000/-per month which has inccurred a sum of Rs.5,00,000/- from September 2016, the date of handing over as per the MOU and the same is liable to be payable by the Opposite Party. The Complainant had suffered mental agony due to the act of the Opposite Party. Hence the complaint.
3. The Complainant submitted his Proof Affidavit and Written Arguments. On the side of the Complainant, documents Ex.A-1 to Ex.A-31 were marked.
4. The Opposite Party did not appear before this Commission even after notice was served on them and remained set exparte.
Points for Consideration
1. Whether there is deficiency in service on the part of the Opposite Party?
2. Whether the Complainant is entitled for reliefs claimed?
3. To what other reliefs the Complainant is entitled?
Point No.1:-
Upon careful perusal of records it is evident that on payment of Rs.49,500/- as advance on 26.02.2015, the Opposite Party had issued Letter of Allotment, Ex.A-2, informing that an Apartment in E-Block, 3rd Floor, bearing No.3E with a built up area of 1121 sq.ft along with undivided share of 531.79 sq.ft and a car parking had been allotted to the Complainant for a total sale consideration of Rs.63,25,859/- which payment is to be made stage wise. The Complainant had also paid a sum of Rs.49,500/- on 27.02.2015, Ex.A-3, subsequent to which Memorandum of Understanding dated 03.03.2015, Ex.A-4 was entered between the Vendors, Opposite Party and the Complainant. As per Clause 12 of the Memorandum of Understanding, the Opposite Party agreed to complete the construction of the Building/Apartment within a period of 24 months from the date of obtaining necessary approvals from the concerned authorities or commencement of the construction, whichever is later i.e. by April 2016 with a grace period of 3 months to complete the construction of the said Building/Apartment.
The contention of the Complainant was that as per the schedule of payments to be made in Annexure D of the MOU, the Complainant had paid a sum of Rs.4,98,182 and Rs.22,90,135/-.
As per Ex.A-8, the status report of the Opposite Party and the photographs reveal that the piling work of Block E was in progress, which shows that the Opposite Party started the construction work for Block E only in April 2016. The Opposite Party had demanded payment on 30.11.2016 and 03.12.2016, remaining silent about the completion of construction. Hence the Complainant had sent an e-mail dated 07.03.2017, Ex.A-16, stating that he had already paid 50% of the total cost and that he is paying rent and interest for the loan every month and sought information regarding date of completion of his apartment. The Opposite Party assured of handing over the Apartment by July 2017. The Complainant had made further payment of Rs.14,91,815/-in March 2017.
The Opposite Party by its E-mail dated 24.04.2017, Ex.A-20, demanded for 95% payment of total consideration for preparing Construction Agreement and for the Sale Deed of the Undivided Share, which payment as per the MOU is to be paid after completion of construction of the Apartment. However, Clause 2.9 of the MOU stipulates that allotee who has availed loan is liable to pay only 55% of the total sale consideration for UDS registration.
The Complainant had caused a legal notice dated 05.10.2017, Ex.A-22, claiming damages for the delay in completing the construction and to execute the Sale Deed in respect of the Undivided Share of Land and to give a probable date of completion of construction. On 15.03.2018, the Opposite Party informed that the CMDA had issued Completion Certificate, but according to the Complainant as the building was found inhabitable another legal notice was sent on 09.04.2018 to complete the building suitable for occupation.
On careful perusal of records and upon hearing the submissions of the Complainant, it is found that the Opposite Party had agreed to hand over the possession of the Apartment by April 2016 with a grace period of 3 months i.e., in the month of July 2016. The Opposite Party had also obtained Planning Permission from CMDA on 30.04.2014 itself. After a delay of nearly 2 years on 15.03.2018 had sent a e mail informing that the CMDA had issued Completion Certificate and sought for further payments. According to the Complainant, he had made payments towards purchase of Flat on various dates amounting to Rs.49,74,364/- and the Opposite Party vide notice dated 15.03.2018 had demanded a sum of Rs.23,63,149/-. The Complainant had sought for the relief of loss due to payment of rent from 18.09.2006, the due date of completion of construction as agreed in the MOU dated 30.03.2015 at Rs.4,80,000/- which is not supported by any valid documentary evidence and hence this Commission is not inclined to grant relief for compensation for the loss due to payment of rent. However the Complainant had established that there was delay on the part of the Opposite Party in completing the construction. Considering the facts and circumstances of the case this Commission is of the considered view that the Opposite Party committed deficiency in service on account of the delay in completing the construction of Apartment allotted to the Complainant. Accordingly, Point No.1 is answered.
Point No.2 and 3:-
As discussed and decided in Point No.1, the Opposite Party is liable to pay a sum of Rs.1,00,000/- as compensation for the deficiency in service and mental agony caused to the Complainant along with cost of Rs.3000/- to the Complainant. Accordingly, Point Nos.2 and 3 are answered.
In the result the Complaint is allowed in part. The opposite party is directed to pay a sum of Rs.1,00,000/- (Rupees One Lakh Only) towards deficiency in service and mental agony caused to the Complainant and to pay a sum of Rs.3,000/- (Rupees Three Thousand Only) towards costs, to the Complainant, within 8 weeks from the date of receipt of this order, failing which the above amounts shall carry interest at the rate of 9% p.a from the date of receipt of this order till the date of realisation.
In the result the Complaint is allowed.
Dictated to Steno-Typist, transcribed and typed by her, corrected and pronounced by us in the Open Commission, on 12th day of October 2022.
S. NANDAGOPALAN T.R. SIVAKUMHAR B.JIJAA
MEMBER II MEMBER I PRESIDENT
List of documents filed on the side of the Complainant:-
Ex.A1 | 25.02.2015 | Copy of Payment receipt copy |
Ex.A2 | 25.02.2015 | Copy of Letter of allotment |
Ex.A3 | 26.02.2015 | Copy of Payment receipt copy |
Ex.A4 | 03.03.2015 | Copy of the MoU |
Ex.A5 | 06.03.2015 | Copy of Payment receipt copy |
Ex.A6 | 14.09.2015 | Copy of Disbursement Details |
Ex.A7 | 05.01.2016 | Copy of Status Report |
Ex.A8 | 22.04.2016 | Copy of Status Report |
Ex.A9 | 30.11.2016 | Copy of e-mail |
Ex.A10 | 01.12.2016 | Copy of e-mail |
Ex.A11 | 02.12.2016 | Copy of e-mail |
Ex.A12 | 30.12.2016 | Copy of e-mail |
Ex.A13 | 07.01.2017 | Copy of Status Report |
Ex.A14 | 02.03.2017 | Copy of e-mail |
Ex.A15 | 21.02.2017 | Copy of e-mail |
Ex.A16 | 07.03.2017 | Copy of e-mail |
Ex.A17 | 07.03.2017 | Copy of e-mail |
Ex.A18 | 24.03.2017 | Copy of Disbursement Details |
Ex.A19 | 02.05.2017 | Copy of Status Report |
Ex.A20 | 24.04.2017 | Copy of e-mail |
Ex.A21 | 25.04.2017 | Copy of Payment claim |
Ex.A22 | 05.10.2017 | Copy of Advocate Notice |
Ex.A23 | 15.03.2018 | Copy of e-mail |
Ex.A24 | 16.03.2018 | Copy of e-mail |
Ex.A25 | 09.04.2018 | Copy of Advocate notice |
Ex.A26 | 27.01.2018 | Copy of Rental Agreement |
Ex.A27 | - | Copy of Statement of Account of ICICI Bank |
Ex.A28 | 10.05.2018 | Copy of Photos showing status of Project area and flat No.3E(No.11) |
Ex.A29 | 10.10.2018 | Copy of Statement of account showing interest paid by the Complainant from 01.04.2016 to 31.03.2017 |
Ex.A30 | 10.10.2018 | Copy of Statement of Account showing interest paid by the Complainant period from 01.04.2017 to 31.03.2018 |
Ex.A31 | 23.08.2017 | Copy of E-mail sent by Opposite Party regarding payment made by the Complainant |
List of documents filed on the side of the Opposite Party:-
NIL
S. NANDAGOPALAN T.R. SIVAKUMHAR B.JIJAA
MEMBER II MEMBER I PRESIDENT
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.