BEFORE THE A.P.STATE CONSUMER DISPUTES REDRESSAL COMMISSION:HYDERABAD
F.A.No.613/2008 against C.C.No.186/2006 , District Forum, Medak at Sangareddy .
Between:
1.NETAFIM Irrigation India Pvt. Ltd.,
Regional Office, H.No.16, Park Avenue Colony,
Ameerpet, Hyderabad-16, represented by its
Regional Manager.
2. NETAFIM Irrigation India Pvt Ltd.,
having its Head Office at 268-270,
GIDC, Manjusar, Savli, Vadodara-391 775,
Gujarat State , represented by its
Managing Director .....Appellants/
Opp.parties 1 & 2
And
Puligilla Janardhan Rao,
S/o. late P.Jagapathi Rao ,
Aged about 54 years, Occ:Agriculture,
R/o.Annaram Village, Papannapet mandal,
Medak District. .... Respondent Complainant
Counsel for the appellants : Mr.M.V.Pratap Reddy
Counsel for the respondent : Party in Person.
CORAM: THE HON’BLE JUSTICE SRI D.APPA RAO, PRESIDENT
SMT M.SHREESHA , HON’BLE MEMBER
AND
SRI G.BHOOPATHI REDDY, HON’BLE MEMBER.
FRIDAY, THE TWENTY SEVENTH DAY OF JUNE,
TWO THOUSAND EIGHT.
Oral Order: (Per Sri G.Bhoopathi Reddy, Hon’ble Member)
***
This is an appeal filed by the appellants/opp.parties 1 AND 2 under Section 15 of the C.P.Act to set aside the order passed by the District Forum, Medak , Sangareddy in C.C.No.186/2006 dt.14.3.2008 .
The respondent herein is the complainant before District Forum . He filed complaint to direct the opp.parties 1 and 2 to rectify the defect and replace with 16 m.m. lateral drip pipe line instead of 12 m.m. lateral pipes, to award compensation of Rs.2 lakhs for the damages caused to the sugar cane crop due to the deficiency in service of the opp.parties and to award costs .
The case of the complainant is as follows:
The complainant is a farmer having five acres of land situated in Sy.no.351 at Annaram village in Papannapet Mandal, Medak District and has been cultivating the land by rising sugarcane crop and supplying the same to the Nizam Deccan Sugar Factory . The opp.party no.3 advertised about the drip irrigation system and introduced the opp.parties 1 & 2 to the complainant for installation of such system .The complainant paid Rs.50,000/- being the half of the estimated cost of the drip irrigation system to the opp.parties 1 and 2 while the remaining cost of Rs.50,000/- was paid by the opp.party no.3 to the opp.parties 1 & 2 towards the subsidy offered by the Government of Andhra Pradesh . The opp.parties 1 & 2 installed the drip irrigation system with 12 mm. lateral pipes and four numbers valves etc during the month of April 2005, but the said drip irrigation system did not work up to the requirement of the complainant . The complainant approached the opp.parties to replace the 12 mm. lateral pipes by installing 16 mm. lateral pipes for functioning of the system upto his needs, but the opp.parties did not do so Because of the deficiency in installation of the system , the sugarcane field of the complainant could not be sufficiently irrigated due to which there was reduction of ten tones per acre in the yield of sugarcane as against the usual yield at 50 tones per acre. Hence the complainant approached the District Forum to direct the opp.parties 1 & 2 to rectify the defect in the drip irrigation system by replacing the 12 mm lateral pipe with that of 16 mm one and also to pay compensation of Rs.2 lakhs towards the damages .
The opp.parties 1 and 2 filed counter denying allegations made in the complaint but admitting to have supplied and installed the drip irrigation system in the sugarcane field of the complainant on receiving Rs.50,000/- from the complainant besides receiving the subsidy amount of Rs.50,000/- from the opp.party no.3 towards the cost of the said system. The opp.parties stated that 12 mm. lateral pipe is sufficient and that 16 mm. one as contended by the complainant is not necessary. The reduced yield in the sugarcane crop of the complainant might be because of other factors i.e. climatic condition , water soil condition, pest management and that the alleged reduction of yield cannot be attributed only to the failure of the drip irrigation system. The opp.parties contended that there is no deficiency in service and prayed for dismissal of the complaint.
The opp.party no.3 filed counter contending that they have paid half of the estimated cost of Rs.50,000/- to the opp.parties 1 & 2 for installation of the drip irrigation system in the sugarcane filed of the complainant as per their guidelines and approved specifications. The opp.party contended that for non functioning of the drip irrigation system they are not responsible as they were not the manufacturers of the said equipment and being a government organisation established for the benefit of the agriculturists is eschewed from the tentacles of the Consumer Protection Act. The opp.party prayed for dismissal of the complaint.
Exs.A1 to A15 documents are marked on behalf of the complainant and Exs.B1 to B11 documents are marked on behalf of the opp.parties 1 & 2 .The District Forum based on the evidence adduced and pleadings allowed the complaint partly directing the opp.parties 1 & 2 to immediately replace the 12 mm diameter lateral pipe with that of 16 mm. one at the drip irrigation system installed in the sugarcane field of the complainant and further directed to pay Rs.20,000/- towards compensation for the loss sustained by him and also pay Rs.1000/- towards costs of the complaint. The complaint against opp.party no.3 is dismissed .
Aggrieved by the said order the opp.parties 1 and 2 preferred this appeal.
The point for determination in this appeal is whether the order passed by the District Forum is sustainable?
The appellants submit that they have produced documentary evidence to show that for the sugarcane crop, 16 mm lateral pipe or 12 mm. lateral pipe can be installed the Dist.Forum failed to understand the same and ignored it completely, the complainant was not ready to pay the extra cost since the govt was giving 50% subsidy of the total cost of the project or a maximum sum of Rs.50,000/- which ever is less , the complainant availed maximum subsidy from the Government by paying remaining balance of Rs.50,000/- through the Project Director A.P.,M.I.P. Sangareddy , Medak . there is no fault with the drip irrigation system installed by them in the fields of the complainant and there is no evidence to show that due to the fault in drip irrigations system in the fields of the complainant he has got reduced yield of sugarcane in his field , order passed by the District Forum may be set aside. The respondent resisted the plea that on account of the drip irrigation system installed by the opp.parties he sustained crop loss , order passed by the District Forum may be confirmed.
There is no dispute that the opp.parties 1 and 2 installed drip irrigation system with 12 mm lateral pipes in the sugarcane field of the complainant to an extent of 5 acres situated in Sy.No.351 at Annaram village in Papannapet. Mandal Medak Dist. . It is also an admitted fact that the drip irrigations system was installed with a subsidy of Rs.50,000/- given by the Government. After installation of the drip irrigation system the complainant made a representation to the Project Director , Dist. Water Management Agency dt.4.1.2006 stating that the drip irrigation installed in his field is not working properly and the discharge of the water through outlets is insufficient for wetting of the crop which is due to the installation of 12 mm. lateral pipes and requesting to arrange for installation of `16 mm. lateral pipes in his sugarcane field and copy of the said letter was addressed to the NETAFIM company . The appellants contended that as per Ex.B1 manual instructions and guidelines of Andhra Pradesh Micro Irrigation Project 12 mm. lateral pipes can be installed for drip irrigation system . After installation of the drip irrigation system in the field of the complainant , it was inspected by the Project director and other authorities and they have certified about the working of the system satisfactorily . Ex.B9 is the certificate issued by OSD (Technical) AP Micro Irrigation Project stating that “In drip irrigation systems water is carried through large network of tubing and delivered to the plant at its base through emitters/drippers . Generally LDPE pipes of 12 mm and 16 mm size are used as lateral pipes to carry water from the sub-main to emitters. While designing the drip irrigation system the size of the subunit is fixed by considering the hydraulics of flow. Generally the pressure variation in the subunit is limited to 20% ,hence the discharge variation with in the subunit is limited to 10%. The pressure head and type of the emitter govern the emitter flow and not the lateral size. By considering the above design criteria the following conclusion can be drawn. 1. In both 12 mm and 16 mm lateral sizes the pressure variation should not exceed 20% this will limit the discharge variation to 10%. 2.The permissible length of 12 mm is lesser than 16 mm., hence the no. of blocks/subunits will be more in 12 mm compared to 16 mm. 3. Emitter discharge is the function of pressure head and not the lateral size. Hence , at given operating pressure in both 12 mm. and 16 mm. lateral sizes , the emitter will give the same discharge. “
The grievance of the complainant is that on account of 12 mm lateral pipes insufficient water was supplied to his fields which affected his sugarcane crop. Ex.B8 is the statement showing the maximum permissible length of drip lines. At the time of installation of drip irrigation system in his fields the complainant did not object for the installation of 12 mm lateral pipes. The District Forum has not properly appreciated the evidence filed by the opp.parties . The opp.parties were ready to install 16 mm lateral pipes if the complainant paid extra amount but the complainant has not paid extra amount . The complainant has signed annexure 8a (d) Soil Health Card stating that the works of drip irrigation system completed to his satisfaction. Thereafter the complainant has complained that the drip system is not working properly and the opp.parties 1 & 2 along with others inspected the land and also rectified the defects of working system . is the letter addressed by the opp.parties 1 and 2 to the opp.party no.3 As per the said letter it is stated that “ a team of officials consisting of DGM –NDSL Medak , CDO – Sugar Dept. ML Specialist DWMA Medak , company DCO & Technical staff visited the field along with the farmer and studied the case in detail & concluded that the laterals are to be placed for every single row & separate sub main line should be given for increased flow. Accordingly the rectification was done at company’s cost (Rs.10,000) After this the farmer was satisfied and also said that whatever area covered under single row is OK ( i.e. from 2.24 Ha to 0.70 Ha). Now one month after the rectification is done, the farmer has published this article and says that Drip system is not useful.” The District Forum has not considered the said letter Ex.B10. The District Forum without properly appreciating the documentary evidence filed by the opp.parties allowed the complaint directing to replace the 12 mm lateral pipe with that of 16 mm one at the drip irrigation system installed in the field of the complainant. .
The respondent submits that on account of the installation of drip irrigation system there is 20% loss of sugar cane crop and compensation awarded at Rs.20,000/- may be confirmed . For the submission made by the respondent is concerned we have gone through the documentary evidence filed by the complainant . He has not filed any documentary evidence with regard to crop loss is concerned. When the complainant complained to the opp.parties they have immediately rectified the defects in the drip irrigation system. We are of the opinion that the compensation awarded by the District Forum without any basis . The complainant could have filed village accounts to show loss of crop. He could have taken the Village Assistant and Agricultural Officer to show that he sustained loss of crop . Except his oral assertion there is no proof that he sustained loss of crop. Therefore we are unable to agree with the finding of the District Forum.
In the result appeal is allowed . Order of the District Forum is set aside. No costs.
PRESIDENT LADY MEMBER MALE MEMBER
DT.27.6.2008
Pm*