PBEFORE THE CONSUMER DISPUTES REDRESSAL FORUM, ERNAKULAM.
Dated this the 28th day of December 2011
Filed on : 10/08/2011
Present :
Shri. A Rajesh, President.
Shri. Paul Gomez, Member. Member.
Smt. C.K. Lekhamma, Member
C.C. No. 434/2011
Between
K.A. Ashlin : Complainant
Kurisunkal house, (party-in-person)
Nambrath,
Kochi, 682 002.
And
1. Mobile Sone, : Opposite parties
Penta Menaka, (1st O.P. Absent)
Ernakulam,
Kochi-682 031.
2. Ranni Enterprises, (2nd O.P.By Adv. T.S. Rajan,
F-15, 1st Floor, P.H.E. Road, Cochin-18)
Island Casile,
Opp. YMCA,
Chittoor road, Kochi.
O R D E R
C.K. Lekhamma, Member.
Facts of the complainant’s case are as follows:
The complainant purchased a mobile phone B-430 fly on 30/09/2010 from the 1st opposite party. The warranty has been provided for one year. After 7 months from its purchase the gadget became defunct. On 16-06-2011 the product was entrusted with the 2nd opposite party for repairing. It was informed that they sent it to their Chennai centre for repairing. After two months on repeated enquiries they informed that they are ready to repair the same provided the complainant meets half the repairing charge. Then the complainant approaches this Forum seeking direction against the opposite parties.
to rectify the defects of the handset under dispute with six months warranty and to pay a compensation of Rs. 2,000/- to the complainant.
2. The complainant appeared in person. The 1st opposite party remained absent. Initially the 2nd opposite party appeared through counsel, thereafter they abstained from the proceedings. The complainant adduced only documentary evidence. Exts. A1 and A2 were marked. Thereafter we have heard the complainant.
3. The points that arose for determination are as follows:
i. whether the complainant is entitled to get his handset repaired with fresh warranty from the opposite parties?
ii. Compensation if any
4. Points Nos.i&ii. Ext. A1 copy of bill shows that the complainant purchased the disputed handset from the 1st opposite party on 30/09/2010. Ext. A2 is the copy of job sheet dated 16-06-2011. The said would show that within one year from the date of purchase the gadget became defunct and the same was entrusted with the 2nd opposite party for repairing. The relief sought for against the opposite parties is to rectify the defects of the mobile phone and to provide fresh warranty and compensation from the opposite party. No contrary evidence is before us to disbelieve the complainant. As per the evidence the mobile set is with the 2nd opposite party. Admittedly the defects were occurred within 7 months from the date of purchase, i.e. within the warranty period. Since the handset is in the warranty period the 2nd opposite party is contractually liable to rectify the defect and the complainant is entitled to get the handset repaired free of cost. More over, the 1st opposite party the dealer is bound to give additional warranty to the product since the privity of contract is between the manufacturer and the dealer. Secondly the gadget was entrusted with the 2nd opposite party for its repair on 16/06/2011 but the 2nd opposite party did not rectify the defects. During this period the complainant was deprived of enjoying the benefits out the disputed product for which the opposite parties are answerable. Hence the opposite parties are liable to pay compensation to the complainant for the deficiency in service on their part. We fix the compensation at Rs. 2,000/-.
5. Accordingly we allow the complaint as follows:
i. The 2nd opposite party shall forthwith rectify the defects of the mobile handset on free of cost and return the same to the complainant
ii. the 1st opposite party shall provide further 6 months warranty to the handset from the date of delivery of the same.
ii. The opposite parties shall jointly and severally pay Rs. 2,000/- towards compensation to the complainant.
The above said order shall be complied with within a period of one month from the date of receipt of a copy of the order, failing which the above amount shall carry interest @ 9% p.a. till realization.
Pronounced in the open Forum on this the 28th day of December 2011.
Sd/-C.K. Lekhamma, Member.
Sd/- A Rajesh, President.
Sd/- Paul Gomez, Member.
Forwarded/By Order,
Senior Superintendent.