Upon notice opposite party appeared before the Commission and filed separate version in all cases . All the averments contained in all the versions are same and are as follows. It is true that the opposite party is engaged in the construction of apartments and is one of the oldest business groups in Kottayam through 5 generations of credible practice. The opposite party always using only the branded first grade raw materials directly purchased from the factory and this guarantees efficient quality control management. The after sale service should give utmost satisfaction to the customers and the quality of the construction can be scrutinized at site by each customer even at all the stages of construction. There was no pressure or compulsion made by the opposite party for purchasing the apartments by anybody. The complainant purchased the apartment after fully convincing about the workmanship, materials and after sales services of the opposite party. The construction of the apartment was done as mentioned in the agreement at the cost and request of the complainant. The total construction cost for the apartment is Rs. 1350/Sq as a launching offer and the complainant very well knew that the said cost of the apartment is the lowest price for an apartment in such an important locality with such an ambience and paraphernalia. Therefore payment schedule was fixed and stated in the two agreements along with other charges mentioned therein. All the customers/occupants are very much satisfied with the terms of the agreement with the specifications mentioned in the agreement. But some of the customers failed to pay the installments in the correct schedules as stated in the agreement or even at the time of the first occupancy certificate issued to the complainant. The opposite party started the construction of the apartment with building permit no. PW7/BA/18506-07 dated 6-10-2007 along with No objection Certificate from pollution control board. The first occupancy certificate received vide no. PW7/BA/18506-07 dated 23-5-2009. Thereafter by mistake the government authorities issued an order for cancellation of the above occupancy certificate and they served the order dated 28-5-2009 on 3-6-2009. It was mistakenly ordered that the subsequent changes in the building rules will affect the previous building permits obtained prior to the amendment. Hence the entire further construction works were stopped due to the reasons beyond the control of the opposite party. Thereafter opposite party approached the tribunal and obtained an order in FA no. 833/2009 dated 27-7-2009 and the final order on 19-8-2009 in appeal no. 618 /2009. The owner of the property issued a detailed explanation on 7-11-2009 to the municipality against the wrong order served for restraining the construction work. Therefore the municipality issued notices on 19-10-2009 along with the provisional occupancy proceedings dated 9-4-2010. The tribunal and Hon’ble high court also passed orders in favour of the opposite party on 18-2-2010 and 25-3-2010 respectively. Accordingly the further construction of apartments are completed by the opposite party and water connection and electric connection for all occupants were obtained on 14-6-2010 and 15-6-2010. These facts are known to the complainant since they are also parties in the previous proceedings pending before different courts. There is no violation of construction in Building rule and completed construction in accordance with the approved plan. Hence no delay caused due to any latches or act committed by the opposite party. The apartments handed over to the complainant even before getting consideration and they were never charged with electricity and water charges during the time they were occupied the apartment and the said amount paid by the opposite party in commercial tariff. It is further averred in the version that in the detailed reply sent to the complainant it was explained by the opposite party about the services rendered to them and thereafter 7 persons withdrew their complaint out of the 12 persons issued notice and the treasurer of the owners association executed an affidavit stating the whole true facts. The opposite party handed over all the title deeds and other relevant documents of each apartment to the respective owners except 4 and was acknowledged by the official representatives of the apartment owners. As per clause 19 of the construction agreement it is made clear that an amount of Rs.10,000/- each kept with opposite party as a deposit to meet on going expenses as the maintenance, management , watchman expenses, sweeper , water and charges for common use. The said sum shall not carry interest and will remain with the opposite party up to the formation of the association. The opposite party will have the authority to deduct the dues if any from the customer’s on account of maintenance. The non formation of association is only due to the above mentioned reasons and from evading the responsibility by the owners association. It is further averred in the version that all the customers are bound to pay the common expenses for the entire two years ie. an additional amount of Rs. 8000/- per apartment. The opposite party has the right to construct additional structures over the roof and over the strip of vacant land around the building within the norms of municipality. No specified area provided in the agreement for landscape garden , free space and inter com connection, cable connection in each apartment lift and security room. There is no leak on the entrance portion and the opposite party will take care of any construction defect, either quality wise or workmanship. The opposite party paved good quality tiles in the exterior portion and used interlock paving. The opposite party used hard wood for doors and shutters, and good quality hand rail materials and plumping materials as per the specifications mentioned in the agreement and the overhead tank’s inner floor and side wall is covered properly on the top for preventing contaminations. There is no specific rule for providing minimum distance for manhole and the manhole is constructed in a safer distance from the well and well built and protected from leakage. The alleged trickling of waste water is not due to leakage but only due to the blockage of pipes due to deposit of foreign particles especially toilet napkins by the customers. There is no mistake in water treatment plant and the fire fighting system; the owners association will take care, if any, mistake occurred during the time of its warranty. The amount collected as cable and electricity charges is purely on the basis of the concluded contract and it is binding to the parties in the agreement. There are sufficient car parking facilities provided in the apartment and nobody other than the 5 complainants had any grievances for the same. The complainants never made prompt payments as scheduled in the agreements. Even before getting the scheduled payments the opposite party not only permitted them to occupy but also executed sale deeds in their favour. Therefore the complainants failed to perform their part of the contract and came before this commission with unclean hands. It is the duty of the association of owners to manage the day to day affairs of the apartment and the opposite party is not in a position to follow the requirements of customers after the date of occupation / formation of association. There is no deficiency in service and unfair trade practice from the side of the opposite party. All the complainants filed proof affidavit in lieu of chief examination. Our predecessor vide order in IA 155 of 2012 allowed joint trial by considering cc 295of 2011 as leading case. T.M. Binoy who is the complainant in CC 295 of 2011was examined as Pw1 and exhibits A1 to A4 were marked. George Scaria is examined as Pw2. Shajilal who is the first Expert Commissioner examined as Pw3 and /Exhibit C1 commission report marked through him. DW1 and Dw2 were examined from the side of the opposite party and exhibits B1 to B25 were marked. Exhibit B1 is marked through the Pw1. X1 commission report marked through Dw2. On evaluation of complaint, version and evidence on record we would like to consider the following points. - Whether there is any deficiency in service or unfair trade practice from the side of the opposite party?
- If so what are the reliefs?
For the sake of convenience we would like to consider point number 1 and 2 together Point No.1 and 2 There is no dispute that the complainant purchased an apartment in the Wexco Olive Yard Luxury Apartments at Puthanagady, Kottayam. The total construction cost for the apartment is Rs. 1350/Sq. Exhibit A3 and B24 is same and the agreement executed between the Pw1 and opposite party for the construction of apartment. On perusal of exhibit A3 and B24 we can see that the opposite party agreed to finish the construction work on or before 20-9-2007 and to hand over the possession of the building within 90 days after completion of the apartment. Admittedly the possession was handed over to the complainants in the month of March 2011. It is contended by the opposite party that the delay caused in delivery of possession was not due to unavoidable circumstances. According to the opposite party though the Exhibit B4 first occupancy certificate received vide no. PW7/BA/18506-07 dated 23-5-2009, thereafter by mistake the government authorities issued an order for cancellation of the above occupancy certificate and served the order dated 28-5-2009 on 3-6-2009. Exhibit B5 is the photocopy of the notice issued by the secretary , local self government department directing the Secretary, Kottayam Municipality to take action on the basis of the report filed by the town planner, Kottayam. In pursuance of Exhibit B5 Secretary, Kottayam municipality issued Exhibit B5(a) order by which they revoked the exhibit B4 occupancy certificate. It is submitted that then the opposite party was constrained to took the matter before the tribunal and obtained a exhibit B7 final order on 19-8-2009 in appeal no. 618 /2009 by which the tribunal set aside the exhibit B5(a) order. Thereafter municipality has issued Exhibit B8 notice to the land owner for which he submitted B9 reply. The tribunal and Hon’ble high court also passed Exhibit B10 and B11 orders in favour of the opposite party on 18-2-2010 and 25-3-2010 respectively. In pursuance of exhibit B10 and 11 the municipality issued Exhibit B12 provisional occupancy certificate on 9-4-2010. It is contended by the opposite party that the further construction of apartments are completed by the opposite party and water connection and electric connection for all occupants were obtained on 14-6-2010 and 15-6-2010. On perusal of exhibit A3 and B24 agreement we can see that the opposite party undertakes that the land owners got building permit on 9-10-2006. On perusal of exhibits B5 we can see that it was issued in pursuance of a report filed by the town planner stating that there was a violation from the approved plan and thereby opposite party has committed the violation of the building rules. On perusal of exhibit B10 and B11 we cannot see any finding either by the tribunal or Hon’ble high court that there was no violation of building rules which was prevailed at the time of the issuance of the occupancy certificate. Moreover it is pertinent to note that there was no finding on Exhibit B10 or B11 that the Exhibit B5 and B5(a) were issued under the provisions of the subsequent amendments in the Kerala Municipal building rules and the same was illegal. However it was observed by the Hon’ble high court that numbering of the building and the issuance of occupancy certificate will be subject to the outcome of any fresh proceeding , which the municipality may initiate in pursuance to exhibit B10 order of the tribunal. On perusal of exhibit B5 we can see that the town planner has pointed out that the opposite party has completed construction of multistoried building by committing several deviations from the approved plan and by violating the provisions of the existing building rule. It is pertinent to note that though the provisional building permit was issued on 9-4-2010 the opposite party handed over the possession of the building to the complainant only in the month of March 2011. Thus we are of the opinion that the delay caused in construction of apartments and handing over the same to complainant was not due to the reasons beyond the control of the opposite party. Another allegation in the complaint is that there are several defects in the building . C1 which is the first commission report filed by the pw3 and X1 which is the report filed by the second commissioner who is appointed as an expert Commissioner at the instance of the opposite party proves that there is a leak on the entrance portion from the toilet of an apartment in the first floor and the waste water is dripping from the said portion. Dw2 would depose that the same could be rectified only by re-plastering the floor of the said toilet. X1 proves that due to the lack of sunshades in the building some of the outer walls are exposed to the direct weather conditions. It is reported in X1 that the same defect can be cured by providing additional sunshades. It is further reported in X1 that some of the pipes provided on the terrace portion were exposed to direct sun and some of the fittings such as controlled valves are damaged due to direct expose to the extreme weather conditions. It is further reported that it can be rectified by using high quality pipes and fittings. Dw2 further deposed that the KSEB authorities ban the two spaces which are provided in front of the electrical rooms and transformer. Dw2 further deposed before this commission that all these defects are due to the deficiency in construction. Thus we are of the opinion that the opposite party has committed deficiency in service due to the defective construction of the apartment. According to the opposite parties facilities like play ground, indoor game, association hall, club house , landscape garden, gymnasium etc , which are printed in exhibit A4 brochure is not provided in the agreement. Dw1 deposed before the commission that they have completed the construction of apartment complex as per the specification which were annexed to exhibit A3 agreement. On perusal of exhibit A3 and B 24 agreement we cannot see any terms and conditions therein with regard to the common facilities. However in clause 24 (d) of exhibit A3 and B24 it is stated that the maintenance of landscape garden, plantations and related fixtures are the duty of the association of the flat owners. Thus even though there was no specific clause for the construction of landscape garden, it can be inferred from the clause 24(d) of Exhibit A3 that the opposite party undertakes to provide a landscape garden for the apartment complex. In exhibit X1 it is reported that though facilities like play ground, indoor game, association hall, club house, landscape garden, gymnasium etc were not specified in Exhibit A3 and B24 ,but one hall has been provided at the terrace floor. In C1 it is reported that facilities like play ground, indoor game, association hall, club house, landscape garden etc could not be located by the expert commissioner in the apartment complex. On perusal of Exhibit A4 brochure we can see that in the second page there was a picture visualization of the apartment complex and it is printed therein as capsule lift, children’s play area , landscaped garden, 24 hours security, club house, fitness centre, indoor game. On seeing that even a common man might have been under the impression that the said apartment complex would have the aforesaid facilities. During the cross examination Dw1 would depose that the car parking facility is provided in the space which was shown as landscape garden in A4 brochure. Dw1 deposed that exhibit A4 is only intended for demonstration purpose. He further deposed that the opposite party used Exhibit A4 for canvasing their prospective customers including the complainants to purchase the apartment. Section 2(1)(r) of the consumer protection act 1986 defines “unfair trade practice” as a trade practice which, for the purpose of the promoting the sale, use or supply of any goods of for the provision of any service, adopts any unfair trade method or unfair or deceptive practice including any of the following practices, namely- (1) the practice of making any statement, whether orally or in writing or by visible representation which,- (i) falsely represents that the goods are of a particular standard, quality, quantity, grade, composition, style or model, (ii) falsely represents that the services are of a particular standard quality or grade, (iii)************** Here in case on hand Dw1 admitted that they have published the A4 brochure to canvas the customers and they are not intended to provide the facilities which were shown in A4 to their customers. Thus we are of the opinion that opposite parties have committed unfair trade practice by not providing common facilities to the complainants which were published and represented thorough exhibit A4. Learned counsel for the opposite parties argued that out of the 12 the flat owners who issued Exhibit A1 lawyers notice, only 5 apartments owners filed the complaint. It is argued by the opposite parties that the common allegation in Exhibit a1 notice and complaints are regarding the amount collected by the opposite parties as security deposit, electricity and other charges from 51 persons and value of car parking from 7 persons. According to the opposite parties hence the matter in issue is related to all the complaints which affect numerous persons. Learned counsel for the opposite parties argued that the claims of damages or compensation is on behalf of persons and without filing permission petition under section 12(1)(c) of the consumer protection act is barred and unsustainable. Counsel for the opposite parties relied on the decision of supreme Court reported in 2020 KHC 5411(SC). In that case the one complaint was instituted by 26 flat owners, against the builder. Here the five separate complaints were filed by separate complainants and they are tried jointly by virtue of the order passes by our predecessor . Thus we are of the opinion that the contention of the opposite parties in this regard is not sustainable. It is further contended that the special damages for getting compensation and for mental agony were not separately pleaded or proved by the complainants. In Godfray Philips India Ltd vs Ajay Kumar (2008) KHC 4538 SC Hon’ble supreme court has held that when serious allegation which was required to be established was not even specifically pleaded when nothing specific was indicated in the complaint, the commission should not have been given the direction on pure surmises. On going through the aforesaid decision it can be seen that in the case referred spura there was no prayer for compensation and no allegation that the complainant had suffered any loss. Here in all complaints in the prayer portion the first relief is that “allow the complainant to realize an amount of Rs. 5,00,000/- towards compensation for deficiency in service and for the mental agony caused to the complainant due to the act of the opposite party.” We can see that there is a specific prayer in the complaint for the compensation for mental agony. Thus we are of the opinion that the proposition laid down by the Hon’ble supreme court in above stated decision has no relevancy in case on hand. It is further argued that Pw1 is not representing other complainants and is not competent to submit about the quantum of damages or compensation for other complainants. It is argued that so far as the compensation, damages and mental agony are concerned the party who suffered such damages must plead such damages in their complaint and prove the same with reasonable certainty. In support of his case the learned counsel for the opposite party relied on the decision of hon’ble supreme court in Fortune Infrastructures (M/s) and another vs Trevor D’lima and others (2018 )KHC 6198 SC . The Hon’ble apex court has held that every breach of contract gives rise to an action for damages and such amount of damages must be proved with reasonable certainty. He further relied on the decisions reported in 1963 KHC 631(SC) and 1982 KHC 179 and argued that court is not bound to award compensation when no legal injury has resulted. It is to be noted that in every consumer disputes there will be some sort of breach of contract. It is also to be born in mind that the consumer disputes are also disputes of civil nature and the remedy or remedies that can be claimed are also civil remedies. But the pertinent aspect is as to whether the breach of contract has resulted in causing deficiency of service or unfair trade practice. The definite case of the complainant herein is that due to the breach of contract on the part of the opposite party, the complainants suffered mental agony, inconvenience and financial loss on account of the deficiency of service and unfair trade practice. The complainant have claimed compensation for the deficiency of service and unfair trade practice on the part of the opposite party. It is true that deficiency of service and tortuous acts, are to be distinguished and differentiated. By distinguishing the case of deficiency of service from the tortuous acts it can be concluded that the case of the complainants is based on deficiency of service and unfair trade practice on the part of the opposite party in executing the work based on A3 and B24 agreements. The mere fact that there occurred breach of contract on the part of the parties to the agreement cannot be taken as a ground to hold that there was no deficiency of service or unfair trade practice as alleged by the complainant. No doubt, that the complainants will succeed in getting the reliefs sought for only on establishing the alleged deficiency of service and unfair trade practice. Learned counsel for the opposite party resisted the complaint on the ground that the Pw1 is not competent to submit the quantum of damages or compensation for other complainants. On going through the complaints we can see that the allegations in all the five complaints are the same. Similarly, though the opposite party filed separate version in all five cases the contentions in all cases are the same. It is pertinent to note that though all the complainant filed separate proof affidavit during July 2017, the opposite party did not file any petition seeking permission to cross examine other complainants except Pw1.The opposite parties have no case that the terms and conditions of the agreements which they made with the other complainants are not same as enumerated in Exhibit A3 and B24. It is a settled proposition of law that the procedure which is followed by the Consumer Commission is a summary procedure. It is also the settled proposition of law that the facts which can be proved by documents, no oral testimony is needed. The oral deposition is required to be made to prove the facts which cannot be proved by way of a document. In the present complaint, the contentions of the parties are based on the documents executed between them and therefore to deal with these issues, no oral testimony is relevant. Therefore we are of the opinion that there will be no chance for causing prejudice to the opposite party. In Savita Garg v. Director, National Heart Institute (2004) 8 SCC 56 para 7 Hon’ble SC observed that: "... ... ...Therefore, as far as the Commission is concerned, the provisions of the Code of Civil Procedure are applicable to a limited extent and not all the provisions of the Code of Civil Procedure are made applicable to the proceedings of the National Forum.... ... ..." In para 10 of the said judgment the Court further observed as under: "The Consumer Forum is primarily meant to provide better protection in the interest of the consumers and not to short-circuit the matter or to defeat the claim on technical grounds. ...” Ireo Grace Realtech Pvt. Ltd. vs. Abhishek Khanna and Ors. reported at AIR 2021 SC 437 wherein it has been held as under: “If the service is defective or it is not what was represented then it would be unfair trade practice as defined in the Act. Any defect in construction activity would be denial of comfort and service to a consumer. When possession of property is not delivered within stipulated period the delay so caused is denial of service. Such disputes or claims are not in respect of immoveable property as argued but deficiency in rendering of service of particular standard, quality or grade. Such deficiencies or omissions are defined in sub-clause (ii) of clause (r) of Section 2 as unfair trade practice”. A person who applies for allotment of a building site or for a flat constructed by the development authority or enters into an agreement with a builder or a contractor is a potential user and nature of transaction is covered in the expression 'service of any description'. It further indicates that the definition is not exhaustive. The inclusive clause succeeded in widening its scope but not exhausting the services which could be covered in earlier part. So any service except when it is free of charge or under a constraint of personal service is included in it. Since housing activity is a service it was covered in the clause as it stood before 1993 19.4 Clause 2(1)(r) of the Consumer Protection Act, 1986 defines ―unfair trade practice as follows :- ―2(1)(r) ―unfair trade practice means a trade practice which, for the purpose of promoting the sale, use or supply of any goods or for the provision of any service, adopts any unfair method or unfair or deceptive practice including any of the following practices, namely:-
(emphasis supplied)
The said definition is an inclusive one, as held by this Court in Pioneer Urban Land & Infrastructure Ltd. v. Govindan Raghavan,4 wherein this Court speaking through one of us (J. Indu Malhotra) held :- ―6.1 …. The inordinate delay in handing over possession of the flat clearly amounts to deficiency of service. In Fortune Infrastructure v. Trevor D'Lima [Fortune Infrastructure v. Trevor D'Lima, (2018) 5 SCC 442 : (2018) 3 SCC (Civ) 1] , this Court held that a person cannot be made to wait indefinitely for possession of the flat allotted to him, and is entitled to seek refund of the amount paid by him, along with compensation.” In Wg. Cdr. Arifur Rahman Khan And ... vs Dlf Southern Homes Pvt. Ltd. reported in 2020 KHC 6499 wherin the hon’ble supreme Court has held that “In other words, what the developer holds out as a defence is that though there has been a failure on their part to provide the amenities, the flat buyers have the benefit of facilities in the surrounding area which has become urbanized. We cannot agree with this line of submissions. The reply of the developer seeks to explain the failure to construct the facilities on the ground that the “existing population cannot sustain these facilities” – a school, commercial complex and health care facilities. This is a case involving an experienced developer who knew the nature of the representation which was being held out to the flat purchasers. Developers sell dreams to home buyers. Implicit in their representations is that the facilities which will be developed by the developer will provide convenience of living and a certain lifestyle based on the existence of those amenities. Having sold the flats, the developer may find it economically unviable to provide the amenities. The flat purchasers cannot be left in the lurch or, as in the present case, be told that the absence of facilities which were to be provided by the developer is compensated by other amenities which are available in the area. The developer must be held accountable to its representation. A flat purchaser who invests in a flat does so on an assessment of its potential. The amenities which the builder has committed to provide impinge on the quality of life for the families of purchasers and the potential for appreciation in the value of the flat. The representation held out by the developer cannot be dismissed as chaff. True, in a situation such as the present it may be difficult for the court to quantify the exact nature of the compensation that should be provided to the flat buyers. The general appreciation in land values results in an increase in the value of the investment made by the buyers. Difficulties in determining the measure of compensation cannot however dilute the liability to pay. A developer who has breached a clear representation which has been made to the buyers of the amenities which will be provided to them should be held accountable to the process of law. To allow the developer to escape their obligation would put a premium on false assurances and representations made to the flat purchasers. Hence, in factoring in the compensation which should be provided to the flat buyers who are concerned in the present batch of appeals, we would necessarily have to bear this issue in mind.” The word compensation is of a very wide connotation. It may constitute actual loss or expected loss and may extend to compensation for physical, mental or even emotional suffering, insult or injury or loss. The provisions of the Consumer Protection Act enable a consumer to claim and empower the Commission to redress any injustice done. The Commission or the Forum is entitled to award not only value of goods or services but also to compensate a consumer for injustice suffered by him. The next question, that falls for consideration, in quantifying the damages/compensation, on account of mental agony and physical harassment caused to the complainant, deficiency in rendering service and indulgence into unfair trade practice by the Opposite Party, the Consumer commissions are required to make an attempt to serve ends of justice so that compensation is awarded, in an established case, which not only serves the purpose of recompensing the individual, but which also, at the same time, aims to bring about a qualitative change, in the attitude of the service provider. Indeed, calculation of damages depends on the facts and circumstances of each case. No hard and fast rule could be laid down, for universal application. While awarding compensation, we have to take into account, all the relevant factors and assess compensation, on the basis of accepted legal principles, on moderation. It is for the Consumer Forum, to grant compensation to the extent, it finds it reasonable, fair and proper, in the facts and circumstances of a given case, according to the established judicial standards. Similar principle of law, was laid down, in Charan Singh, Vs. Healing Touch Hospital and others AIR 2000 Supreme Court 3138. In Surendra Kumar Tyagi Vs. Jagat Nursing Home and Hospital and Another, IV (2010) CPJ 199 (N.C.), the principle of law, laid down, by the National Consumer Disputes Redressal Commission, New Delhi, was to the effect, that the compensation should be commensurate with loss and injury, suffered by the complainant. The Consumer Foras are not meant to enrich the consumers, at the hands of the service providers, by awarding unfair, unjust and excessive compensate..on. The principle of law, laid down, in the aforesaid cases, is fully applicable to the instant case. The complainants has been in possession of the apartments, since March 2011, and has been living therein, uncomfortably. The Opposite Parties also never refused to execute the sale deed, and get it registered, from the Competent Authority. Though the opposite party submitted that they are ready and willing to rectify the defects in the apartment if any, even after the X1 report they did not take any initiative to rectify the defects which were reported by expert commissioner in X2 report. The compensation must be commensurate with the facts and circumstances of the case, and injustice occasioned to the complainant. It should be neither unreasonable and excessive, nor meager. Keeping in view, the facts and circumstances of the case, the injustice occasioned to the complainants, mental agony and hardships caused to them , and the extent of deficiency, in rendering service and unfair trade practice, on the part of the Opposite Party, in our considered opinion, the compensation, is required to be Rs 3 lakhs, which would serve the ends of justice. On the basis of above discussed evidence and decisions we allow this complaint along with CC No. 294 0f 2011, CC 295 of 2011, CC 296 OF 2011,297 OF 2011 and 298 OF 2011 and pass the following order. - We hereby direct the opposite party to pay Rs. 3 lakhs to the complainant as compensation for the mental agony caused due to the deficiency in service from the part of the opposite party.
- We herby direct the opposite party to cure the defect of the apartment complex which is reported by the expert commissioner in his X1 report.
Order shall be complied within 30 days from the receipt of this order failing which the compensation amount will carry 9% from 21-11-2011 i.e. the date on which the complaint filed. Pronounced in the Open Commission on this the 21st day of October, 2021. Sri. Manulal V.S. President Sd/- Smt. Bindhu R, Member Sd/- Appendix Witness from the side of complainants. Pw1 – Binoy T.M. Pw2 – George Scaria Pw3 – Shajilal Witness from the side of opposite party Dw1 – Johnson Varghese Dw2 – Jaison Joseph Exhibits marked from the side of complainant A1- Office copy of the lawyers notice dtd.19-07-2011 A2 – Lawyers notice dtd.06-08-11 issued by Adv. P.A. Rabeez to Adv. Jayakrishnan R. A3 – Copy of agreement dtd.28-10-2006 A4 – Brochure Exhibits marked from the side of opposite party B1 – Copy of receipt dtd.28-03-11 B2 – Copy of Memorandum of Association of Wexco Homes Pvt. Ltd. B3 – Copy of building permit No.Pw7/BA/185/06-07 dtd.06-10-07 by Kottayam Municipality B4- Copy of Occupancy certificate dtd.23-05-09 by Kottayam Municipal Council B5 – Copy of Order No.48842/RA3/2008LSGD by Local Self Govt. (RA) Department dtd.25-08-2009 B5(a) – Copy of notice No.PW7/BA/185/06-07 dtd.03-06-09 from Kottayam Municipality B6 – Copy of IA No.833/2009 in Appeal No.618/2009 in the Court of Tribunal for Local Self Government Institutions, Thiruvananthapuram. B7 – Copy of judgment in Appeal No.618/2009 dtd.19-08-2009 in the Court of the Tribunal for Local Self Government Institutions, Thiruvananthapuram B8 – Copy of notice dtd.19-10-2009 by Secretary, Kottayam Municipality. B9 –Copy of letter dtd.07-11-09 by M.J. Alexander to Secretary, Kottayam Municipality B10 -Copy of judgment in Appeal No.983/2009 dtd.18-02-2010 in the Court of the Tribunal for Local Self Government Institutions, Thiruvananthapuram B11- Copy of judgment in W.P. (C) No.7778 of 2010(V) dtd.25-03-10 in the High Court of Kerala. B12- Copy of Provisional occupancy certificate dtd.09-04-2010 B13- Copy of certificate by Kottayam Municipality for the approval of water connection. B14 - Copy of certificate by Kottayam Municipality for the approval of electric connection. B15 – Copy of Non objection certificate dtd.06-07-2007 B16 - Copy of terms and conditions of Kerala State Pollution Control Board,. B17 series – Copies of list of documents dtd.23-03-2011 by opposite party (36nos.) B18 – Copy of agreement B19 – Copy of notice dtd.26-05-2010 B20 – Copies of receipt issued by Kottayam Municipality B21 – Copy of the minutes of the meeting of Olive Yard dtd.29-01-2011 B22 – Copy of Form II (Return under sub-sections (1) or (3) of Section 7 or Section 8 B23 –Copy of letter dtd.30-06-2010 by M.J. Alexander to the Secretary, Municipality, Kottayam B24 – Copy of common expenses of one year of Wexco Olive Yard B25 – Copy of lawyers notice dtd.06-08-2011 B26 – Board resolution Commission report C1 – inspection report submitted by Shajilal C.E. X1 – Report submitted by Er.Jaison Joseph |