IN THE CONSUMER DISPUTES REDRESSAL FORUM, KOLLAM
Dated this the 1st day of December 2018
Present: - Sri. E.M.Muhammed Ibrahim, B.A, LL.M. President
Sri. M.Praveen Kumar,Bsc, LL.B ,Member
CC.No.150/18
Mr.Rajagopalan : Complainant
Kairali, Thrikkanamangal
Kottarakkara P.O
Kottarakkara Village
Kottarakkara Taluk
[By Adv.Bijeesh.S.Pillai]
V/s
- Managing Director : Opposite parties
M/s Alia Formtech Steel Industries
Kannamkodu, Adoor
Pathanamthitta Dist.
Kerala-691523
- Mr.K.R.Shajahan
Managing Director
Alia Form Tech Steel Industries
Building No.137/3
Opposite Kottamukal Juma Masjid
Kannamkodu, Adoor
Pathanamthitta-691523.
FAIR ORDER
E.M.MUHAMMED IBRAHIM , President
This is a consumer complaint filed under section 12 of the Consumer Protection Act.
The averments in the complaint in short are as follows:-
The 1st opposite party is an industry engaged in steel fabrication and roofing systems and carries on business in Kannamcode, Adoor Taluk. The 2nd opposite party is the Managing Director of the 1st opposite party industry. The complainant entered into a contract with the 2nd opposite party for the
2
construction of his terrace roofing works due to avoid leakage of concrete roofing of his house. The 2nd opposite party made the complainant to believe that the leakage of the concrete roof of his house will be cured with the fabrication and complete erection of Royal Alia Rainbow Roofing System with a model “Alia Modular Cantleaver”. As per the agreement the above said work consists of 575.5 sq feet and will be completed within 10 to 15 days and the total construction cost including labour and materials is Rs.1,67,900/-. Out of which the complainant had given advance of Rs.50,000/- by way of cheque while executing the agreement. On 3rd May 2017 the project was almost completed and as per the demand of the opposite party the complainant had given a cheque for Rs.1,13,900/- towards the balance amount to Mr.Ramesan Pillai the work supervisor of the 1st opposite party who in turn has executed a cheque acceptance letter to the complainant. Before receiving the cheque for
the final balance the said work supervisor received altogether Rs.10,000/- in cash in 4 occasions and there by the complainant paid the entire constructed amount to the 2nd opposite party in time. However the opposite parties carried out the work by utilising inexperienced labours and used low quality materials which has caused serious defects in the construction of roofing. The defects in the construction were noticed by the complainant only when the 1st raining on 28.05.17 and thereupon the complainant made a complaint before the opposite parties. At the very 1st raining itself the entire rain water started to fall into the terrace and that oozed into the rooms of the house and there by defeated the very purpose of roofing. After the roofing work was completed the complainant repainted the house by spending 1.5 lakhs rupees. But due to the leakage and continuous oozing of rain water the new painting and cement plastering were fully destroyed. The complainant brought the above defects in the roofing to the 2nd opposite party and requested to cure the defects but in vain. There after the complainant caused to sent lawyer notice dated 14.12.17
3
requesting to cure the defects in the construction of roofing. But the opposite party has not responded the above complaint and lawyer notice nor even sent any reply. According to the complainant there is clear negligence and deficiency in service on the part of the opposite parties and thereby the complainant sustained a loss of Rs.1,50,000/-. Apart from the monitory loss, the complainant has sustained physical harassment and mental agony and there by the complainant is entitled to get compensation to the tune of Rs.1,00,000/- . The complainant further prays for refund of the amount of Rs.1,67,900/- paid to the opposite parties along with interest @ 8% p.a and costs. Hence the complaint.
Notice issued from this forum has been served to the opposite parties but they have not turned up. Hence the opposite parties were set exparte.
The complainant filed affidavit by re-iterating the averments in the complaint and got marked Ext.P1,P2,P3, P4 series and P5 documents. Ext.p1 is the agreement executed by the 2nd opposite party on behalf of the 1st opposite party in favour of the complainant which would show that total construction costs of the erection of Royal Alia Rainbow Roofing System with a model “Alia Modular Cantleave” is Rs.1,67,900/- out of which the 2nd opposite party has received cheque for Rs.50,000/- as advance on the date of execution of the agreement which is on 17.07.17. Ext.P2 is the demand letter issued by the Manager of the 1st opposite party demanding to pay the balance of Rs.1,15,900/- due on the above agreement. Ext.P3 is the letter issued by one Ramesan Pillai the supervisor of 1st opposite party company acknowledging the receipt of Rs.1,13,900/- from the complainant. Ext.P4 series is the advocate notice send by the complainant intimating the defects of the roofing work done by the opposite parties and also demanding to set right the construction defects within 15 days from the date of receipt of notice along with postal receipt evidencing of sending lawyer notice. Ext.P5 is the postal acknowledgement
4
card evidencing the receipt of lawyer notice. The unchallenged averments in the affidavit coupled with Ext.P1 to P3,P4 series and P5 documents would establish the case of the complainant. Therefore the complaint is only to be allowed. In the result the complaint stands allowed in the following terms.
The opposite party No.1&2 are directed to set right the defect in the roofing construction work to the satisfaction of the complainant within 30 days from the receipt of copy of this order failing which the complainant is allowed to recover Rs.1,67,900/- paid to the opposite parties as construction costs with interest @ 9% p.a from the date of complaint till realisation from the opposite party No.1&2 and from their assets.
- Opposite party No.1&2 are further directed to pay Rs.25,000/- as compensation and Rs.5000/- as costs of the proceedings to the complaint within 30 days.
If the opposite parties failed to comply with the direction No.1&2 the complainant is allowed to recover Rs.1,92,900/-(Rs.1,67,900+25000) with interest @ 12% p.a from the date of complaint till realisation along with costs Rs.5000/- from the opposite party No.1&2 and from their assets.
Dictated to the Confidential Assistant Smt.Deepa.S transcribed and typed by her corrected by me and pronounced in the Open Forum on this the 1st day of December 2018.
E.M.Muhammed Ibrahim:Sd/-
M.Praveen Kumar:Sd/-
Forwarded/by Order
5
INDEX
Witnesses Examined for the Complainant:-Nil
Documents marked for the complainant
Ext.P1 : Contract Agreement
Ext.P2 : Letter
Ext.P3 : Cheque acceptance letter
Ext.P4 series : Postal receipt and lawyer notice
Ext.P5 : Acknowledgment card
Witness examined for the opposite party:-Nil
E.M.Muhammed Ibrahim:Sd/-
M.Praveen Kumar:Sd/-
Forwarded/by Order
SENIOR SUPERINTENDENT