Ld. Advocate(s)
For Complainant: Makbul Rahaman
For OP/OPs : Joydip Mitra
Date of filing of the case :12.08.2020
Date of Disposal of the case :30.11.2023
Final Order / Judgment dtd.30.11.2023
The gist of the case of the complaint is that the complainant had a vehicle bearing no. WB57B 9171 Chassis No.MAT466420E3G16465, Engine No.B591803241G63387327 insured with the OP No.1 Shriram General Insurance Company Limited, Kolkata vide policy no.334027/31/20/004821, period of Insurance from 19.09.2019 to 18.09.2020. The said vehicle is the only earning source of the complainant to maintain his livelihood. The aforesaid vehicle met with an accident on 17.12.2019 and it was informed to the OP No.1 Shriram General Insurance Company Limited. The complainant sent his vehicle to Rohan Engineering Workshop Gobindapur, Post Office Plassey, District Nadia. Thereafter the OP NO.1 appointed a surveyor to assess the loss. The said Rohan Engineering Workshop gave an estimate to the complainant for Rs.2,02,860/-. The complainant got repaired the said vehicle and gave a bill to the said Rohan Engineering Workshop for Rs.8,500.00+31,910.00+14,690.00+28,350.00+9,280.00+49,050.00+19,473.20+18,000.00= total Rs.1,79,253.20 which was paid by the complainant. Thereafter, the complainant submitted all the bills along with all relevant documents and filled up claim form to the OP No.1 through surveyor of the OP No.1. Subsequently, the complainant requested to the OP NO.1 and OP NO.2 for settlement of his claim as soon as possible but the OP No.1 did not settle the claim. On 18.06.2020 the complainant shown the status of his claim which is actually no claim but there is no claim. The OP NO.1 did not send any letter regarding no claim. Thereafter, the complainant contacted with the OP No.1 over phone but they did not explain to the complainant as to what is the ground for no claim. Thus the OP NO.1 intentionally and cleverly treated the claim of the complainant as “no claim.” So the present case is filed. The cause of action for the present case arose on and from 18.06.2020 and thereafter each and every day. The complainant therefore prayed for an award for Rs.1,79,253.20 being actual claim amount, interest at the rate of 12% on the claim amount, from the date of accident dated 17.12.2019, payment of Rs.50,000/- for loss and damages and mental pain and agony. The complainant prayed for an award for the aforesaid relief.
The OPs contested the case by filing W/V wherein they denied the major allegation by filing W/V. The positive defence case of the OP No.1 in brief is that the complainant approached the OP No.1 Shriram General Insurance Company Limited in the engine of his vehicle. The OP NO.1 explained the terms and conditions to the complainant and being satisfied the terms and conditions the complainant obtained the vehicle insurance policy bearing no.334027/004821(Motor Commercial Vehicle Package Policy for securing his vehicle being No.WB57B 9171). Thereafter, the complainant intimated the claim with the OPs for the said compensation. The claim of the complainant was duly processed by the OP No.1 Shriram Insurance Company Limited by this way of appointment of surveyor and loss assessor. On receipt of the survey report the complainant came to know that a sum of Rs.97,000/- was ascertained as actual loss after deducting applicable depreciation and as per policy terms and conditions. The insured suppressed the actual cause of accident. Upon scrutiny of documents of the insured, it was found that the documents like proof of private carriers, permit of the vehicle, last loaded material details, dealer bills, NCB confirmation and FIR copy were pending from the insured. The OPs insurance company sent several letters to provide the said document to the complainant but he did not respond. Due to non-submission of documents the OPs closed the claim as no claim. The OP No.1 challenged the case as not-maintainable and bad for mis-joinder and non-joinder of necessary parties. The OP No.1 claimed that the case is liable to be dismissed with cost. OP No.1` denied almost all the allegations by filing W/V wherein they made out a defence case to the effect that the complainant filed the case for wrongful gain and extortion of money from the OP No.1. The OP No.2 approached to the complainant for purchasing the policy under Shriram General Insurance Company Limited in the house of the complainant and at the same place. The complainant filled up the proposal form and sending the same. The complainant also paid Rs.26,959/- to the OP No.2 at Village Gobindapur, Post office Plassey, P.S. Kaliganj, District Nadia. After receiving the premium OP No.2 deposited it to the office of the OP No.1 and after receiving the said premium Insurance Policy was issued and handed over to the complainant by the OP No.2. So, the OP NO.2 claimed that the case is liable to be dismissed with the cost.
The respective conflicting pleadings of both the parties led this Commission to ascertain the following points.
Points for determination
Point No.1
Whether the case is maintainable in its present form and prayer.
Point No.2
Whether the complainant is entitled to get the relief as prayed for.
Point No.3
To what other relief if any the complainant is entitled to get.
Decision with Reasons
Point No.1
The OP challenged the case as not maintainable on the ground that the case is bad for defect of parties.
But the OPs could not specify as to who others are the necessary parties to this case. Both the insurance company and its agent are made parties to the case. So, there is nothing to show that the case is bad for defect of parties. Both the parties to this case reside within the territorial jurisdiction of this Commission and the amount of claim also false within the pecuniary jurisdiction of this Commission. Accordingly, having considered the pleadings of the parties and the evidence on the case record the Commission is of the view that the case is maintainable in its present form and prayer.
Accordingly, point no. 1 is answered in favour of the complainant.
Point No.2 & 3
Both the points are very closely interlinked with each other and as such these are taken up together for brevity and convenience of discussion.
The complainant Samiul Islam in order to establish the case adduced both the oral evidence by filing affidavit in chief and documentary evidence. The complainant proved the following documents:-
1) Annexure-1 is the Certificate of Registration.
2) Annexure-2 is the policy of vehicle bearing no. WB57B 9171.
3) Annexure-3 is the estimate given by Rohan Engineering Workshop for Rs.2,02,860/-.
4) Annexure-4 is the bill for repairing for Rs. 8,500/-.
5) Annexure-5 is the bill for repairing dated 28.01.2020 for Rs.31,910/-.
6) Annexurte-6 is the bill for Rs.14,690/- for repairing dated 13.01.2020
7) Annexure-7 is the bill for repairing for Rs. 28,350/- dated 07.01.2020.
8) Annexure-8 is the bill for repairing for Rs.9,280/- dated 09.01.2020.
9) Annexure-9 is the bill for Rs.49,050/- dated 17.01.2020.
10) Annexure-10 is the bill for Rs.19,473.20 dated 10.01.2020.
11) Annexure-11 is the bill for Rs.18,000/- dated 02.01.2020.
12) Annexure-12 is the online claim status information given by the OP as no claim.
The opposite parties denied the claim of the complainant on the ground that there is no claim as the complainant failed to provide the documents asked for.
The complainant challenged the said refusal of the OP.
Ld. Advocate for the complainant argued that the OP never demanded any document from the complainant. The complainant never receive any letter from the OP and there is no document with the OP to establish that the OP served the said letter upon the complainant.
It is fact that the OP did not file any specific document to show that the said letters were served upon the complainant but the main point for consideration is that a surveyor was appointed for the purpose of ascertaining the claim of the complainant and the surveyor submitted a report in favour of the complainant. As per the final survey report the actual loss assessed is Rs.97,000/-.
Now, the main point for consideration is whether the said permit of the vehicle was valid during the relevant period. Ld. Advocate for the complainant filed several permits of the disputed vehicle where from it is revealed that the permit of the vehicle was valid during the relevant period. The OP filed the surveyor reports where from it is also revealed that the surveyor assessed the loss to the tune of Rs.97,000/- with a note, “please up to date the PSR report with complete documents and your observation on urgent basis.”
After analysing the entire documents of both the parties it is crystal clear that the OP company finally assessed the loss for a sum of Rs.97,000/-. But there is nothing within the case record to show that the claim of the complainant was repudiated by the OP company.
Ld. Defence Council further argued that the complainant could not prove the actual cost incurred by the said Rohan Engineering. The bill submitted by the complainant are different bills of different companies. So, due to lack of submission of documents being pending the complainant is not entitled to get the relief.
Having considered the documents filed by the complainant in the case record it is found that the complainant incurred several expenses with different repairing company but since the entire bill was not actually incurred in respect of Rohan Engineering, so, the total claim of the complainant should be reduced on the basis of the actual loss assessed by the OP company.
Ld Defence counsel for the OP further argued that the permit a relates from 2020 to 2024, but the actual accident took place in December, 2019. After scrutiny all the permits filed by the complainant it appears that the complainant had valid permit during the relieved period so the claim cannot repudiated on the plea that the complainant had no permit at the relevant time.
Ld. Defence Counsel referred to a decision reported in Volume IV (2005) CPJ 115 (NC) wherein it was held that the respondent is not entitled to any amount under the policy since he had no valid permit at the relevant time of the date of the accident.
The case law is not applicable since the complainant filed document to show that he had valid permit at the relevant. So, the complainant is entitled to get the actual loss assessed by the surveyor.
In the backdrop of the aforesaid assessment of evidence and observation made herein above the Commission comes to the findings that the complainant is entitled to the relief to a limited extent along with compensation for harassment and mental pain and agony.
Point No. 2 &3 are accordingly answered in affirmative and decided in favour of the complainant.
Consequently the complaint case succeeds on contest with cost.
Hence,
It is
Ordered
that the complaint Case No.CC/40/2020 be and the same is allowed on contest with cost of Rs.5,000/- (Rupees five thousand) against the OPs jointly and severally. The complainant do get an award for a sum of Rs.97,000/- (Rupees ninety seven thousand) along with interest at the rate of 8% per annum from the date of filing of this case till the date of its realisation, Rs.20,000/- (Rupees twenty thousand) for the compensation for mental pain and agony and harassment against the OPs. Both the OPs are jointly or severally directed to pay Rs.1,22,000/- (Rupees one lakh twenty two thousand) to the complainant within 30 days from the date of passing the final order failing which the entire award money shall carry an interest at the rate of 8% per annum from the date of final order till the date of its realisation.
Dealing Assistant to note in the trial register.
The case is accordingly disposed of.
Let a copy of this final order be supplied to both the parties at free of costs.
Dictated & corrected by me
............................................
PRESIDENT
(Shri HARADHAN MUKHOPADHYAY,) ................ ..........................................
PRESIDENT
(Shri HARADHAN MUKHOPADHYAY,)
I concur,
........................................
MEMBER
(NIROD BARAN ROY CHOWDHURY)