We agree with the view taken by the State Commission that broken seals do not prove theft of electricity. No evidence was led by the appellant regarding theft of electricity. Meters were being checked every month and found to be in order. Meter was removed and was sent to M&T Laboratory but since this case is relatable to the period before the Electricity Act, 2003 and has to be covered by Section 26 of the Electricity Act, 1910, which reads as under : “26. Meters – (1) In the absence of an agreement to the contrary, the amount of energy supplied to a consumer or the electrical quantity contained in the supply shall be ascertained by means of a correct meter, and the licensee shall, if required by the consumer, cause the consumer to be supplied with such a meter : Provided that the licensee may require the consumer to give him security for the price of a meter and enter into an agreement for the hire thereof, unless the consumer elects to purchase a meter. (2) Where the consumer so enters into an agreement for the hire of a meter, the licensee shall keep the meter correct, and, in default of his doing so, the consumer shall, for so long as the default continues, cease to be liable to pay for the hire of the meter. (3) Where the meter is the property of the consumer, he shall keep the meter correct and, in default of his doing so, the licensee may, after giving him seven days’ notice, for so long as the default continues, cease to supply energy through the meter. (4) The licensee or any person duly authorized by the licensee shall, at any reasonable time and on informing the consumer of his intention, have access to and be at liberty to inspect and test, and for that purpose, if he thinks fit, take off and remove, any meter referred to in sub-section (1); and, except where the meter is so hired as aforesaid, all reasonable expenses of, and incidental to, such inspecting, testing, taking off and removing shall, if the meter is found to be otherwise than correct, be recovered from the consumer; and, where any difference or dispute arises as to the amount of such reasonable expenses, the matter shall be referred to an [Electrical Inspector], and the decision of such Inspector shall be final: Provided that the licensee shall not be at liberty to take off or remove any such meter if any difference or dispute of the nature described in sub-section (6) has arisen until the matter has been determined as therein provided. (5) A consumer shall not connect any meter referred to in sub-section (1) with any electric supply-line through which energy is supplied by a licensee, or disconnect the same from any such electric supply-line [but he may by giving not less than forty-eight hours notice in writing to the licensee requires the licensee to connect or disconnect such meter and on receipt of any such requisition the licensee shall comply with it within the period of the notice]. [(6) Where any difference or dispute arises as to whether any meter referred to in sub-section (1) is or is not correct, the matter shall be decided, upon the application of either party, by an Electrical Inspector; and where the meter has, in the opinion of such Inspector ceased to be correct, such Inspector shall estimate the amount of the energy supplied to the consumer or the electrical quantity contained in the supply, during such time, not exceeding six months, as the meter shall not, in the opinion of such Inspector, have been correct; but save as aforesaid, the register of the meter shall, in the absence of fraud, be conclusive proof of such amount or quantity: Provided that before either a licensee or a consumer applies to the Electrical Inspector under this sub-section, he shall give to the other party not less than seven days’ notice of his intention so to do.] (7) In addition to any meter which may be placed upon the premises of a consumer in pursuance of the provisions of sub-section (1), the licensee may place upon such premises such meter, maximum demand indicator or other apparatus as he may think fit for the purpose of ascertaining or regulating either the amount of energy supplied to the consumer, or the number of hours during which the supply is given, or the rate per unit of time at which energy is supplied to the consumer, or any other quantity or time connected with the supply: Provided that the meter, indicator or apparatus shall not, in the absence of an agreement to the contrary be placed otherwise than between the distributing mains of the licensee and any meter referred to in sub-section (1): Provided also that, where the charges for the supply of energy depend wholly or partly upon the reading or indication of any such meter, indicator or apparatus as aforesaid, the licensee shall, in the absence of an agreement to the contrary, keep the meter, indicator or apparatus correct; and the provisions of sub-sections (4), (5) and (6) shall in that case apply as though the meter, indicator or apparatus were a meter referred to in sub-section (1). Explanation – A meter shall be deemed to be “correct” if it registers the amount of energy supplied, or the electrical quantity contained in the supply, within the prescribed limits of error, and a maximum demand indicator or other apparatus referred to in sub-section (7) shall be deemed to be “correct” if it complies with such conditions as may be prescribed in the case of any such indicator or other apparatus.” It is clear from the perusal of the record that the petitioner did not follow the law laid down under the provision reproduced hereinabove. Hence, this Revision Petition is dismissed.
......................JASHOK BHANPRESIDENT ......................B.K. TAIMNIMEMBER ......................ANUPAM DASGUPTAMEMBER | |