D.o.F:25/02/2014
D.o.O:23/08/2014
IN THE CONSUMER DISPUTES REDRESSAL FORUM, KASARAGOD
CC.NO.36/14
Dated this, the 23rd day of August 2014
PRESENT:
SMT.P.RAMADEVI : PRESIDENT
SMT.BEENA K.G : MEMBER
SMT.SHIBA.M.SAMUEL : MEMBER
Ashok Kumar.V.K
R/at. Ashok Nivas, Munnad Post, : Complainant
Kasaragod Kasaragod Kerala
(in person)
1.Jyothis Project, DLS, 40/894 C,
2nd Floor, CRIt Complex, M.G.Road, :
Ernakulam.
Rep. by its Managing Partner.
2. Jyothis Project, Al Jazeel Complex, : Opposite parties
Puthiyakota, Kanhangad.
Rep. by John Mathew, Br.Manager.
R/at Kuzhiyarayil House,
Vellarikund Po,Parappa Via,Kanhangad
(authorised signatory ,Sri.Siby Mathew)
ORDER
SMT.P.RAMADEVI : PRESIDENT
Complainant and opposite parties ‘ authorised signatory ,Sri.Siby Mathew, present. Matter is settled for an amount of Rs.30,000/-. As per settlement the opposite parties undertake to pay the entire amount on 30/6/2015 . Complainant agreed for the same. Hence the complaint is closed accordingly.
In case of default the complainant is entitled to get an interest on defaulted amount at the rate of 12% per annum from the date of complaint till realization
Sd/ Sd/ Sd/
MEMBER MEMBER PRESIDENT
/forwarded by Order/
SENIOR SUPERINTENDENT
eva