Tarlapu Benu filed a consumer case on 30 Nov 2016 against Junior Engineer, SouthCo, in the Rayagada Consumer Court. The case no is CC/88/2016 and the judgment uploaded on 26 Dec 2017.
DISTRICT CONSUMER DISPUTES REDRESSAL FORUM, RAYAGADA
C.C. Case No.88/ 2016.
P R E S E N T .
Sri Pradeep Kumar Dash, LL.B, President.
Sri Gadadhara Sahu, B.Sc, Member
Tar;a[I Benu,S/o Tarlapu Erukulu, Resident of Vill: Gadiseshkhal, P.S.Chandili, Dist. Rayagada. …………..Complainant
Versus
Counsel for the Parties:
For the complainant: Sri N.K.Kanta & Associate Advocate,Rayagada.
For the O.Ps: Self JUDGMENT
The facts of the case in brief is that the complainant is a consumer of the O.ps vide Consumer No.311203620062 and the complainant was regularly depositing the electricity bill as per consumption. On 22.11.2015 the O.P 2 has inspected the premises and imposed a fine of Rs.7142/- on the ground that the meter bypass and assessed charges from October,2014 to October,2015. On the day of inspection the meter was properly sealed. Now the OPO 1 announced to disconnect the connection unless the bill is paid within ten of this month. The complainant is ready to deposit the monthly bills and has requested to the Op 2 to consider the fine amount which is illegal and arbitrary. Hence, prayed to direct the Op No.1 to accept the monthly bill till disposal of the case and not to disconnect the connection and award compensation of Rs.10,000/- towards deficiency of service and mental agony and cost of litigation and other relief as the forum deems fit and proper . Hence, this complaint.
Being noticed, the O.Ps appeared and filed written version inter alia denying the petition allegations on all its material particulars. It is submitted by the O.ps that the complainant is a consumer of the O.ps vide Consumer No.311203620062. On 21.11.2015 the OP 2 inspected the premises of the complainant and during course of the inspection it was found that the complainant is availing power supply through a bypass meter. For such unauthorized use of electricity the opposite party No.2 being empowered under the Electricity Act,2003 made provisional assessment Under Section 126(2) of the Act by way of passing provisional assessment to the tune of Rs.7,142/- and served the complainant on 26.11.15 and calling upon him to file objection within seven days of receipt of such provisional assessment and if the complainant is aggrieved by the final order of assessment made under Sec.126(3) of the Act, he may within 30 days of the said order, prefer an appeal before the Appellate Authority as per the mandate of Section 127 of the Electricity Act,2003 which is a special tribunal constituted under Section 127 of the Indian Electricity Act,2003 for redressal of any grievance against the final order of assessment as regards to unauthorized use of electricity ,as such the Hon’ble Forum has no jurisdiction to entertain the complaint filed by the complainant. Further the jurisdiction of the consumer forum has been barred as per the provision of Se 145 of the Electricity Act, so the complaint filed by the complainant needs to be dismissed in the interest of justice.
FINDINGS
It is admitted by the parties that the meter is Ok and running correctly and showing accurate reading. In view of Sec.3 of the Consumer Protection Act and Sec.175 of Electricity Act, the consumer approached this Forum. Therefore , the C.P.Act is not effected by the Electricity Act. Whenever there is a provision for settlement of the claim , the authority has to follow the same without putting the consumer into trouble and to go for litigation. The complainant approached the authorities but the authorities did not accept the same which shows the gross deficiency in service.
Hence, the OP may establish their claim by the process giving opportunity to the consumer either refute the same or admit the same and such charges will be made only on rectification. Hence, the petition is allowed.
ORDER
In view of the legal provisions stated above the petition of the complainant is allowed . The bill raised at the time of inspection is hereby quashed. The complainant is directed to file a petition before the Electrical authorities and the Ops are directed to consider the application and revise the bill form 10/2014 to 10/2015 within a stipulated period and after final discussion with the Ops the complainant is to deposit the up to date amount. The parties are to bear their own cost.
Pronounced in open forum today on this 19th day of December,2016 under the seal and signature of this forum.
A copy of this order as per the statutory requirements , be forwarded to the parties free of charge.