So it is clear that The Consumer Protection Act is a special type of act and even if there is a clause of arbitrator in the application form, it will not oust the jurisdiction of the consumer courts. So this court has jurisdiction to try the case.
It is also clear that the complainant has deposited a good amount of money towards this flat. In the provisional allotment letter dtd 16.04.2012 the opposite party has promised to deliver the possession of the said within 42 months meaning thereby that the possession was to be given by 15 October 2015. The opposite party failed to honour his promise. Now the opposite party has brought the story of Yamuna Express way, story of Jayprakash associates and infratecetcetc .Provisional allotment letter dtd 16.04.2012 has been issued jointly by Jaiprakash Associates Ltd and Jaypee Infra Tech Ltd , meaning thereby that both the firm jointly and severally liable for this transaction. Now the story of moratorium etc in relation to Jaypee Infra Tech Ltd has nothing to do with this joint responsibility. Jaiprakash Infratech Ltd has issued the receipts of deposits so he has collected the money from the complainant and if Jaiprakash Infratech Ltd comes in picture and collect money, the matter rates between those two individuals and not between complainant and opposite parties.
In the light of above mentioned facts we have to see the latest judicial pronouncement of Hon’ble NCDRC in First Appeal no 380 of 2019 , Judgement dated 26.09.22 Jaiprakash associates Ltd Vs Deepti Kumar & two ors. In this case the matter rates to “ Garden Isles” and in the present case the matter also relates to “ Garden Isles” . Both these Isles are same and situated in JP Greens .Soit is clear that the Hon’ble NCDRC has dealt with one of the same matter and pronounced its judgement which is very important in the present circumstances of the case. The Hon’ble NCDRC has held in this case ,
- “ThecomplainantstatedthatJaypeeInfratechLimited(respondent-2)andJaiprakashAssociatesLimited(theappellant)(hereinafterreferredtoasthebuilders)werecompanies,registeredunderCompaniesAct,1956andengagedinthebusinessofdevelopingandconstructinggrouphousingproject.Theylaunchedagrouphousingprojectinthenameof“GardenIsles”atJaypeeGreens,Sector-131&133,Noidaandmadewidepublicityintheyear2011.Alluredwithlucrativeadvertisementsandbelievingonit,thecomplainantappliedforaflatanddepositedtherequiredmoneyofRs.2.5/-lacson06.02.2012.ThebuildersprovisionallyallottedUnitNo.-GDI25-2103(superarea1205sq.ft.,BasicSalePriceofRs.4359690/-TotalConsiderationofRs.4898890/-,includingRs.2.5/-lacsforCarParkingSpace)on16.05.2012.Undertheallotmentletterdated16.05.2012,thebuilderspromisedtodeliverpossessionwithin42monthsfromthedateofallotment.Thebuildersprovidedsubventionscheme,underwhich,loanwasadvancedfromAxisBankLimited(oppositeparty-3).Aquadripartiteagreementdated29.06.2012wasexecutedbetweenthepartiesandAxisBankLimiteddirectlyadvancedRs.3889200/-on03.08.2012tothebuilders.ThecomplainantpaidRs.490000/-on18.06.2012,Rs.134233/-onRs.29.08.2012andRs.12847/-on28.03.2013(totalRs.4776280/-includingloanamount).The
periodof42monthsexpiredon16.11.2015andgraceperiodof180daysasgivenunderClause-
7.2ofStandardTermsandConditionsexpiredon16.05.2016.ThebuildersdidnotgiveanyinformationregardingprogressoftheconstructionnorofferedpossessiontillthenandpaiddelayedcompensationasperClause-7.2.Thecomplainant,videletterdated01.09.2016inquiredaboutdateofdeliverypossessionandrequestedforpaymentofdelayedcompensationbutthebuildersdidnotrespond.Thenthecomplaintwasfiled,claimingdeficiencyinserviceandunfairtradepractice.
- TheappellantandJaypeeInfratechLimited(respondent-2)fileditsjointwrittenreplyinthecomplaint,inwhich,materialfactsrelatingbooking/allotmentoftheflatandpaymentsmadebythecomplainant,includingmoneyadvancedbyAxisBankLimitedhavenotbeendisputed.However,theytookpleathatthecomplainantmadepaymentwithdelayforwhich,shewasliabletopayinterestofRs.78515/-.Theydeniedofcommittingdeficiencyinserviceandunfairtradepractice.TheystatedthatTajExpresswayProjectwasconceivedbyGovernmentofU.P.,intheyear2002,forconnectingNoidatoAgra.Theprojectalsoenvisageddevelopmentof25millionSq.Mtrs.landalongwiththeexpresswayon“Build-Operate-Transfer”basis,forwhichbidswereinvited.BidofM/s.JaiprakashIndustriesLimitedwaslowestassuchtheprojectwasawardedtoitandConcessionAgreementdated07.02.2003wasexecutedbetweenTajExpresswayAuthority(nowrenamedasYamunaExpresswayIndustrialDevelopmentAuthority)andM/s.JaiprakashIndustriesLimited.Byaschemeofamalgamation,approvedbyAllahabadHighCourt,videorderdated10.03.2004,M/s.JaiprakashIndustriesLimitedwasamalgamatedwithJaypeeCementLimitedw.e.f.01.04.2002andthenameofJaypeeCementLimitedwaschangedasJaiprakashAssociatesLimitedw.e.f.11.03.2004.StateofU.P.appointedanEnquiryCommissionofJusticeSiddheshwarNarayan(retd.)tolookintotheConcessionAgreement.Hesubmittedhisreportdated12.10.2006,recommending,setupaSpecialPurposeVehicle,forthepurposesofcarryingouttheproject.AsperdirectionofYamunaExpresswayIndustrialDevelopmentAuthority,inthelettersdated06.11.2006and15.02.2007,JaypeeInfratechLimitedwasincorporatedon05.04.2007asaSpecialPurposeVehicleforcompletionoftheproject.ByProjectTransferAgreementdated19.10.2007(registeredon17.12.2007),thedevelopmentworkoftheprojectofexpresswayfromNoidatoAgrawasassignedtoJaypeeInfratechLimited,whowasrequiredtofundtheProjectbydevelopmentandsaleofflats/landinfivetownships.Entirelandfordevelopmentatfivelocations,includingthelandofJaypeeGreensWishTownProjectwasleasedtoJaypeeInfratechLimitedon27.11.2007.ADevelopmentAgreementdated01.05.2009wasexecutedbetweenJaypeeInfratechLimitedandJaiprakashAssociatesLimited,underwhichtaskofdevelopment,construction,marketing,saleetc.wereassignedtoJaiprakashAssociatesLimited.Afterobtainingnecessaryapproval,developmentworkofthe“GardenIsles”wasstarted.However,forthereasonsbeyondtheircontroli.e.duetoforcemajeureevents,viz.shortageoflabour,scarcityofwater,restrictionsinexcavations,villager’sagitations,legalimpedimentsetc.,theconstructionwasdelayed.Thefundingofthedevelopmentoftheprojecthadtobedonepartlyfromsaleofapartmentandpartlyfromsaleofland.Intheyear2010,saleofparcelsoflandwashaltedandseriouslawandorderproblemwascreatedduetofarmer’sagitation.Governmentof U.P.issuedorderdated29.08.2014forpaymentofadditionalincentiveof64%tothefarmers,whichresultedtotalscarcityoffundsfordevelopmentoftheproject.Thevillagersstoppedtheworkofdevelopmenttillpaymentoftheamount.StateGovernmentdecidednottohandovertheExpresswayconnectingNoidaandGreaterNoidatothebuildersin2012,resultingsubstantialloss
ofrevenuetoJaypeeInfratechLimited.NationalGreenTribunal,videorderdated11.01.2013,restrainedallthebuildersofNoidaandGreaterNoidafromextractingundergroundwater.
NationalGreenTribunalvideorderdated14.08.2013,restrainedallconstructionworkswithinaradiusof10kmfromOkhlaBirdSanctuaryandvideorderdated28.10.2013restrainedtheauthoritiesfromgrantingcompletioncertificatetoanybuilding.Byanorderdated03.04.2014directedtheauthoritiestocreateaneco-sensitivezoneforOkhlaBirdSanctuary.Thebuildersfiled M.A.No.240of2014formodificationoftheorderdated03.04.2014,whichwasrejectedon30.05.2014.AgainsttheseordersCivilAppealNos.5822-5823of2014werefiled,whichweredismissedbySupremeCourton10.06.2014.StateGovernmentnotifiedeco-sensitivezoneon19.08.2015.UnderClauses-7.1and7.2ofStandardTermsandConditions,thebuilderswereentitledforextensionofperiodforwhichtheconstructionwasobstructedduetoforcemajeurecauses.ThebuildersgaveadiscountofRs.327760/-tothecomplainantasperClause-7.2ofStandardTermsandConditionsandthebuildersthroughoutactedinfairandbonafidemanner.Therewasnounfairtradepractice.ThebuilderswerereadytorefundtheamountasperStandardTermsandConditions.Thebuilderswereknownfortheirqualityandcommitmentandtheyweretryingtocompletetheprojectandhandoverpossessionattheearliest.Thepreliminaryissuesthatthecomplainanthadbookedtheflatforcommercialpurpose,asisprovedfromthefactthatduetodownfallofmarketinrealestate,thecomplaintwasfiledforrefundofmoneyandnotforpossessionandsheisnotaconsumerandStandardTermsandConditionscontainedanarbitrationclauseandsheberelegatedforarbitration,havealsobeenraised.”
“ 9. ThecounselfortheappellantsubmittedthatNationalCompanyLawTribunal,AllahabadhasdeclaredmoratoriumagainstJaypeeInfratechLimited,videorderdated09.08.2017undertheCode,2016andtheproceedingisstillgoingon.Section-63barsjurisdictionofCivilCourtandbyvirtueofSection238,theprovisionsoftheCode,2016haveoverridingeffect.SupremeCourtinHirakundIndustrialWorksVs.VarshaFabrics(P)Ltd.(2020)14SCC198andGhanshyamMishraandsons.Pvt.Ltd.Vs.EdelweissARCLtd.(2021)9SCC657,heldthattheprovisionsoftheCode,2016hadoverridingeffectoverallotherstatuteincludingConsumerProtectionAct,1986.TheremedyofthehomebuyeristosubmithisclaimbeforeInterimResolutionProfessional.DeeptiKumar(respondent-1)hassubmittedherclaimofRs.4776280/-alongwithinterest,on21.08.2017beforeInterimResolutionProfessional.Homebuyersare‘financialcreditors’withinthemeaningofSection5(7)readwithExplanationtoSection5(8)(f)oftheCode,2016.CommitteeofCreditorsapprovedtheplanofSurakshaRealtyLimitedon09.07.2021,underwhich,SurakshaRealtyLimitedproposedtocompletetheprojectwithin40monthsandthehomebuyerswouldbegivenpossessionoftheirflatwithoutanydelayedcompensation.Resolutionofapprovaloftheplanisbindingonall‘financialcreditors’.Inviewofmoratoriumdated09.08.2017,StateCommissionoughttohaveabatedtheproceedingofthecomplaintbeforeit.SomeofthehomebuyersfiledwritpetitionbeforeSupremeCourt,i.e.inChitraSharmaandothersVs.UnionofIndiaandothers,(2018)18SCC575,byfinalorder,SupremeCourtdeclinedtodisbursetheamountdepositedbytheappellanttothehomebuyersofJaypeeInfratechLimited,holdingthathomebuyerswere‘financialcreditors’andmemberofCommitteeofCreditorsanddirectingthemtosubmittheirclaimbeforeInterimResolutionProfessional.SupremeCourtinInnoventiveIndustriesLimitedVs.ICICIBankandanr.,(2018)1SCC407,heldthattheCode,2016isacompletecode.UnderSection-28oftheCode,2016,CommitteeofCreditorssupervisestheaffairsofInterimResolutionProfessional,inrespectofcorporatedebtor.UnderSection30(4)oftheCode,2016,theresolutionplanhastobeapprovedbyCommitteeofCreditorsbyamajorityvotingshareofatleast66%.Inthepresentcase,thereweremorethan21000homebuyer’svotes.CommitteeofCreditorshasapprovedtheplanofSurakshaRealtyLimitedon09.07.2021,underwhich,homebuyerwouldbegivenpossessionoftheirflat.ThisisbindinguponthemasheldbySupremeCourtinJaypeeKensingtonBoulevardApartmentWelfareAssociationandothersVs.NBCC(India)Ltd.andors.,(2021)SCCOnLineSC253.InCommitteeofCreditorsofEssarSteelIndiaLtd.Vs.SatishKumarGupta,(2020)8SCC531,heldthatCommitteeofCreditorsalonesdeterminesitsfeasibilityandviabilitybasedonitsowncommercialwisdom.EvenNationalCompanyLawTribunalhaslimitedjurisdictiontointerferewiththeapprovedplan.ItisnotopenforthehomebuyertoclaimflatfromJaypeeInfratechLimitedandalsotakerefundfromJayprakashAssociatesLimited.SupremeCourtinSAILVs.UnionofIndia,(2006)12SCC233,heldthatalitigantisestoppedfromraisinginconsistentandmutuallydestructiveplea.RelyinguponDevelopmentAgreementdated01.05.2009,executedbetweenJaypeeInfratechLimitedandJaiprakashAssociatesLimited,inwhichtaskofdevelopment,construction,marketing,saleetc.wereassignedtoJaiprakashAssociatesLimitedaswellasvariousclausesofprovisionalallotmentletterandStandardTermsandCondition,ithasbeensubmittedthatJaiprakashAssociatesLimitedwasanagentofJaypeeInfratechLimited.ThehomebuyerpaidentiremoneytoJaypeeInfratechLimited.ThisCommissionhastakenviewthattheperson,whohadreceivedmoney,wasliabletoreturnit.In viewofSection230ofContractAct,1872,recoveryproceedingcannotbeinitiated/continuedagainstanagentfortheactsofadisclosedprincipal.HerelieduponthejudgmentsinMarineContainerServicesSouthPvt.Ltd.Vs.GoGoGarments,(1998)3SCC247,PremNathMotorsVs.AnuragMittal,(2009)16SCC274,VivekAutomobilesVs.IndianInc.,(2009)17SCC657,forthepropositionthatanagentcannotbeheldliablefortheactsofadisclosedprincipal.Clause-9.1.5ofStandardTermsandConditionsprovidesforreturnofthemoneywithoutanyinterestorcompensationandearnestmoney.StateCommissionhasillegallydirectedforpaymentofinterest@18%perannum.DelaywascausedforthereasonsofforcemajeureandtheperiodwasliabletobeextendedunderCluase-7.1ofStandardTermsandConditions.ThejudgmentsofthisCommissioninCC/1495/2015,ArvindDhingraVs.JAL(decidedon01.10.2018)hasbeensetasidebySupremeCourt.CC/2194/2016AnishSinghalVs.JAL(decidedon01.10.2019)wasnotrelatedtotheprojectofJaypeeInfratechLimited.JudgementinCC/11320-11329/2018GauravGoel&anr.vs.JALwaschallengedinCivilAppealDiaryNo.
5804of2020,whichwasdecidedintermsofsettlementvideorderdated25.10.2021.JudgmentinCC/976/2017RajeevKumarSinghVs.JAL,(decidedon15.06.2020)hasbeenstayedbySupremeCourtinCivilAppealNo.4724-4725of2021,videorderdated16.08.2021.Noneofthesejudgmentscanbeconsideredasbindingprecedent.JudgmentofAnjaliRathiVs.TodayHomes,(2021)SCCOnLineSC729,isdistinguishableasthepromoterhadgivenundertakingbeforeSupremeCourttobeartheliability,inthatcase.
- ThecomplainantdoesnotdisputethatNationalCompanyLawTribunal,AllahabadhasdeclaredmoratoriumagainstJaypeeInfratechLimited,videorderdated09.08.2017undertheCode,2016andtheproceedingwasgoingon.However,thecomplainantarguedthatJaiprakashAssociatesLimitedwasoneofajointpromisorassuchheisseverallyliabletorefundtheamountunderSection43oftheContractAct,1872.JaiprakashAssociatesLimitedwasthe‘promoter”asdefinedundertheRealEstate(RegulationandDevelopment)Act,2016andthecomplainantisentitledtoclaimrefundofmoneyfromhimunderSection19(4)ofthisAct.ThecomplaintisnotliabletobeabatedduetopendencyofinsolvencyproceedingagainstJaypeeInfratechLimitedastheappellantisindependentlyliabletoreturnthemoney.
13. UnderSection-14(a),institutionofsuitetc.againstcorporatedebtorcanbeprohibitedwhileunderSection-14(b)prohibitioncanbeimposeduponthecorporatedebtorfromtransferringetc.itsassets.SupremeCourtinChitraSharmaandothersVs.UnionofIndiaandothers,(2018)18SCC575andJaypeeKensingtonBoulevardApartmentWelfareAssociationandothersVs.NBCC(India)Ltd.andors.,(2021)SCCOnLineSC253.,didnotheldthattheproceedingagainsttheappellantforrefundofmoneyisliabletobeabated/stayedduetopendencyofproceedingundertheCode,2016,againstJaypeeInfratechLimited.Innoneofthecases,relieduponbytheappellant,ithasbeenheldthattheproceedingagainstapromoterorco-promisorforrefundisliabletobeabated/stayedduetopendencyofproceedingundertheCode,2016,againstJaypeeInfratechLimited.AforesaidprovisionsoftheCode,2016barsuitetc.againstcorporatedebtoronlynotagainsttheappellant,whowasnotacorporatedebtor.
15. Section43oftheContractAct,1872andtherelevantprovisionsoftheRealEstate(RegulationandDevelopment)Act,2016arequotedblow:-.
“Section43.Anyoneofjointpromisorsmaybecompelledtoperform-Whentwoormorepersonsmakeajointpromise,thepromisemay,intheabsenceofexpressagreementtothecontrary,compelany[oneormore]ofsuchjointpromisorstoperformthewholeofthepromise.
Eachpromisormaycompelcontribution.-Eachoftwoormorejointpromisorsmaycompeleveryotherjointpromisortocontributeequallywithhimselftotheperformanceofthepromise,unlessacontraryintentionappearsfromthecontract.
Sharing of loss by default in contributions.-if any one of two or more joint promisors makesdefault in such contribution, the remaining joint promisors must bear the loss arising from suchdefaultinequalshares.
Explanation-Nothinginthissectionshallpreventasuretyfromrecovering,fromhisprincipal,paymentsmadebythesuretyonbehalfoftheprincipal,orentitletheprincipaltorecoveranythingfromthesuretyonaccountofpaymentmadebytheprincipal.
TheRealEstate(RegulationandDevelopment)Act,2016
Section:2(zk)“promoter”means,—
- apersonwhoconstructsorcausestobeconstructedanindependentbuildingorabuildingconsistingofapartments,orconvertsanexistingbuildingorapartthereofintoapartments,forthepurposeofsellingallorsomeoftheapartmentstootherpersonsandincludeshisassignees;or
- apersonwhodevelopslandintoaproject,whetherornotthepersonalsoconstructsstructuresonanyoftheplots,forthepurposeofsellingtootherpersonsallorsomeoftheplotsinthesaidproject,whetherwithorwithoutstructuresthereon;or
- anydevelopmentauthorityoranyotherpublicbodyinrespectofallotteesof—(a)buildingsorapartments,asthecasemaybe,constructedbysuchauthorityorbodyonlandsownedbythemorplacedattheirdisposalbytheGovernment;or
(b)plotsownedbysuchauthorityorbodyorplacedattheirdisposalbytheGovernment,
forthepurposeofsellingallorsomeoftheapartmentsorplots;or(iv)anapexStatelevelco-operativehousingfinancesocietyandaprimaryco-operativehousingsocietywhichconstructsapartmentsorbuildingsforitsMembersorinrespectoftheallotteesofsuchapartmentsorbuildings;or
- anyotherpersonwhoactshimselfasabuilder,coloniser,contractor,developer,estatedeveloperorbyanyothernameorclaimstobeactingastheholderofapowerofattorneyfromtheownerofthelandonwhichthebuildingorapartmentisconstructedorplotisdevelopedforsale;or
- suchotherpersonwhoconstructsanybuildingorapartmentforsaletothegeneralpublic.
Explanation.—Forthepurposesofthisclause,wherethepersonwhoconstructsorconvertsabuildingintoapartmentsordevelopsaplotforsaleandthepersonwhosellsapartmentsorplots
aredifferentperson,bothofthemshallbedeemedtobethepromotersandshallbejointlyliableassuchforthefunctionsandresponsibilitiesspecifiedunderthisActortherulesandregulationsmadethereunder;”
Section19.Rightsanddutiesofallottees;(1)…………
(2)………………..
(3)…………………
(4)TheallotteeshallbeentitledtoclaimtherefundofamountpaidalongwithinterestatsuchrateasmaybeprescribedandcompensationinthemannerasprovidedunderthisAct,fromthepromoter,ifthepromoterfailstocomplyorisunabletogivepossessionoftheapartment,plotorbuilding,asthecasemaybe,inaccordancewiththetermsofagreementforsaleorduetodiscontinuanceofhisbusinessasadeveloperonaccountofsuspensionorrevocationofhisregistrationundertheprovisionsofthisActortherulesorregulationsmadethereunder.
- . UnderDevelopmentAgreementdated01.05.2009,taskofdevelopment,construction,marketing,saleetc.ofthevariousprojectsofJaypeeInfratechLimitedwereassignedtoJaiprakashAssociatesLimited,whowasalsosharingtheprofitoncostplusbasis.UnderProvisionalallotmentletterandStandardTermsandConditions,JaiprakashAssociatesLimitedhaspowertocancelallotmentofthehomebuyer.Inparagraph-8(ii)ofthewrittenreply,theappellanthasstatedthatJaypeeInfratechLimitedwasitssubsidiarycompany.Inparagraph-2ofmemorandumofappeal,theappellantclaimedtobeholdingcompanyofJaypeeInfratechLimited.However,theappellantarguedthatitwasanagentofJaypeeInfratechLimitedunderDevelopmentAgreement.
- TheRealEstate(RegulationandDevelopment)Act,2016,hasbeenenactedtoprovidebetterprotectiontothehomebuyersinefficientandtransparentmanner.TheappellantfallswithinthedefinitionofthepromoterunderthisAct.ThehomebuyerisentitledtoclaimrefundofmoneywithinterestfromtheappellantunderSection-19(4)oftheRealEstate(RegulationandDevelopment)Act,2016.TheprovisionsoftheCode,2016donotbarinitiationofproceedinganditscontinuationforrefundagainstthepromoter.RealEstate(RegulationandDevelopment)Act,2016isaspeciallaw.Evenif,forthesakeofarguments,itistakenthattheappellantwasanagentofJaypeeInfratechLimitedundertheDevelopmentAgreement,thenalsotheappellantisfallingwithinthedefinitionof“promoter”asgivenunderRealEstate(RegulationandDevelopment)Act,2016.SpecialLawwillprevailovergenerallawasheldbySupremeCourtinVodaphoneIdeaCellularLtd.Vs.AjayKumarAgrawal,(2022)6SCC496.ThepositionoftheappellantaspromoterandliabilitytorefundSection-19(6)ofRealEstate(RegulationandDevelopment)Act,2016willoverrideoveritspositionasanagentofJaiprakashInfratechLimited.Theappellantbeingaco-promisorisjointlyandseverallyliabletorefundthemoneytothehomebuyerunderSection43oftheContractAct,1872.InPioneerUrbanLandandInfrastructureLtd.andOrs.Vs.UnionofIndia,(2019)8SCC416,heldthatRERAandIBCareparallelremedy.
- SupremeCourtinBankofIndiaVs.KetanParekh,(2008)8SCC148andS.VanithaVs.DeputyCommissioner,Bengaluru,2020SCCOnLineSC1023,heldthatthecasesmightarise,
whereboththeenactmentshavethenon-obstanteclause,theninthatcase,properperspectivewouldbethatonehastoseethesubjectandthedominantpurposeforwhichthespecialenactmentwasmadeandincasethedominantpurposeiscoveredbythatcontingencythennotwithstandingthattheActmighthavecomeatalaterpointoftime,stilltheintensioncanbeascertainbylookingtotheobjectsandreasons.
- RelyinguponthejudgmentsofthisCommissioninCC/3879-3880/2017DeepakAgrawalandOrs.Vs.ThreeCShelters(decidedon21.01.2020)andCC/1702/2016ShalabhNigamVs.OrrisInfrastructurePvt.Ltd.andOrs.(decidedon06.05.2019),thecounselfortheappellantsubmittedthatthepersonwhohadreceivedthemoneywouldbeliabletorefund.Werespectfullydisagreewithit,inasmuchasithasnottakennoticeofSection43oftheContractAct,1872,whereco-promisorisjointlyandseverallyliable,Section-19ofRealEstate(RegulationandDevelopment)Act,2016,wherethepromoterisindividuallyliableandwellsettledprincipleoflawoftortrelatingtovicariousliability.(SeeCanaraBankVs.CanaraSalesCorporation,(1987)2SCC666andPradeepKumarVs.PostMasterGeneral,(2022)6SCC351.)Assuchthesecasesareperincurium.
- SurakshaRealtyLimitedinitsPlandated09.07.2021proposedthecompletetheprojectwithin40monthsandthehomebuyerswouldbegivenpossessionoftheirflatswithoutanydelayedcompensation.Duedateofpossessionwas16.05.2016asperallotmentletterdated16.05.2012.SupremeCourtinBangloreDevelopmentAuthorityVs.SyndicateBank,(2007)6SCC442,FortuneInfrastructureVs.TrevorD’Lima,(2018)5SCC442,KolkataWestInternationalCityPvt.Ltd.Vs.DevasisRudra,2019SCCOnLineSC438andPioneerUrbanLand&InfrastructureLtd.Vs.GovindRaghavan,(2019)5SCC725,heldthatahomebuyercannotbemadetowaitforpossessionoftheflatforindefiniteperiod.
- InviewoflawlaiddownbySupremeCourt,thehomebuyerisentitledtoclaimrefundofhismoneyalongwithinterestincaseofunreasonabledelayinhandingoverpossession.However,StateCommissionhasawardedinterest@18%perannum,whichisonhigherside.CompensationofRs.20000/-formentalagonywasalsonotpayable.SupremeCourtinBangloreDevelopmentAuthorityVs.SyndicateBank,(2007)6SCC442,heldthatinthematterofcontractualobligation,thereisnoscopeforcompensationformentalagonyandharassment.InDLFHomesPanchkulaPvt.Ltd.Vs.D.S.Dhanda,II(2019)CPJ117(SC)heldwheninterestisawardedascompensationinthecasesofrefundofmoney,thenawardingadditionalcompensationwasnotjustified.NowSupremeCourtinthecasesofIreaoGraceRealteck(P)Ltd.Vs.AbhishekKhanna,(2021)3SCC241andCivilappealNo.2324of2021M/s.BarnalaBuildersandPropertyConsultantsVs.Lt.Col.SameerBalodi(decidedon06.06.2021),fixedtheinterest@9%perannuminthecasesofrefund.
ORDER
Inviewoftheaforesaiddiscussions,theappealispartlyallowed.TheorderofStateCommissiondated24.10.2018ismodified.Theappellantisdirectedtorefundentireamountdepositedbythecomplainantwithinterest@9%perannumfromthedateofrespectivedeposittillthedateofactualpayment,withinaperiodoftwomonthsfromthedateofthisjudgment.Respondent-1wouldalsobeentitledforaconsolidatedcostofRs.20000/-.Whilemakingpayment,loanofAxis BankLimitedshallbeadjustedfirst.”
Now it has been held that the opposite parties are liable for the compensation and damages. The opposite parties totally failed to carry out their promise and the complainant cannot be left /for long period. There is clear deficiency of service on the part of the opposite parties and it is a matter of unfair trade practice and unfair contract. What should be the amount of compensation and what should be the rate of interest, will depend on the facts and circumstances of each case as held by on the Supreme Court in the following judgement,
Hon’ble Supreme Court has held in Ghaziabad Development Authority Vs Balbir Singh (2004) 4 SCC 65-
“The Supreme Court, at the outset, reiterated the position taken in the case of Lucknow Development Authority v. M.K. Gupta, and held that “the Consumer Protection Act has a wide reach and the Commission has jurisdiction even in cases of service rendered by statutory and public authorities”. It further held that the power of the NCDRC extends to awarding compensation to consumers for misfeasance in the public office i.e. an act which is oppressive or capricious or arbitrary or negligent provided loss or injury is suffered by a citizen. Therefore, it upheld the appeals filed before it to the extent that it confirmed the jurisdiction of the NCDRC to award compensation in cases of service rendered by statutory & public authorities (the land development authorities in the present case).
As to the issue of whether the grant of interest at the rate of 18% per annum by the NCDRC in all cases is justifiable, the Supreme Court held in the negative. It stated that “the power to and duty to award compensation does not mean that irrespective of facts of the case compensation can be awarded in all matters at a uniform rate of 18% per annum.” It held it to be unsustainable. The Court further stated that the “Award of compensation must be under different separate heads and must vary from case to case depending on the facts of each case.” The purpose of awarding compensation is to recompense for a loss or injury suffered and such compensation would therefore be proportional to the amount of loss and injury.
While considering the compensation to be awarded to the consumers in cases of deficiency of service by Development Authorities, the Court laid down a range of principles for the determination of the amount of compensation, summarised below:
- To award compensation, the Forum or the Commission must determine that service has been deficient and/or misfeasance in public office which has resulted in loss or injury. While no hard and fast rule can be laid down, the Court gave a few instances where the award of compensation would be justifiable, including where possession is not handed over within the intimated period even though allotment is made and the price is paid. In such cases, the loss could be determined based on loss of rent which could have been earned if possession was given. Compensation could also be the scheme has been canceled without any justifiable cause, after the allotment.
- Compensation cannot be uniform and to illustrate this, the Court lays down the principle to be followed for the determination of compensation in two cases- – (a) where the delivery of possession is being directed, and (b) where only the monies are directed to be returned or refunded by the Court. In case (a), the compensation for harassment will necessarily have to be less since in a way the aggrieved party is being compensated by an increase in the value of the property he is getting. In case (b) however, the party is suffering a greater loss since he has been deprived of the flat/plot, and his expectation of delivery of possession. He would also be denied the benefit of an increase in the value of land and the compensation thereof. Therefore, the compensation to be awarded in such cases would have to be higher than in case (a).
The Court held that “such compensation has to be worked out after looking into the facts of each case and after determining what is the amount of harassment/loss which has been caused to the consumer.”
- Compensation would include compensation for physical, mental, or even emotional suffering, insult, or injury or loss.”
“The consumer protection laws have a wide reach and the consumers are entitled to receive compensation for deficiency in services rendered by statutory and public authorities. The Consumer Commissions have been vested with the jurisdiction to award the value of goods or services and compensation. On being satisfied that a complainant is entitled to compensation for loss or injury or harassment or mental agony or oppression, it must direct the authority to pay compensation. A wide discretion has been given to determine the quantum of compensation for any loss or damage suffered by a consumer, to redress any injustice. However, it is a well-established principle that the computation of compensation has to be fair, reasonable, and must reconcile with the loss or injury suffered. The Consumer Forum is cast with the duty to take into account all relevant factors for arriving at the compensation to be paid.
This landmark decision has set a precedent on the matter of compensation to be awarded in matters relating to allotment of land by development authorities and has been relied upon in many subsequent cases of the Supreme Court. In the case of H. P. Housing Board v Varinder Kumar Garg] and Haryana Urban Development Authority vs Darsh Kumar, the Supreme Court directed the Commission to follow the principles laid down in the case of Ghaziabad Development Authority vs. Balbir Singh in future cases.”
Hon’ble Supreme Court in the case of Haryana Urban Development ... vs Darsh Kumar, Etc. Etc , Civil Appeal no 5796 of 2002 decided on on 28 July, 2004 has held ;
“This Court has, in the case of Ghaziabad Development Authority vs. Balbir Singh reported in (2004) 5 SCC 65, deprecated this practice. This Court has held that interest at the rate of 18% cannot be granted in all cases irrespective of the facts of the case. This Court has held that the Consumer Forums could grant damages/compensation for mental agony/harassment where it finds misfeasance in public office. This Court has held that such compensation is a recompense for the loss or injury and it necessarily has to be based on a finding of loss or injury and must co-relate with the amount of loss or injury. This Court has held that the Forum or the Commission thus had to determine that there was deficiency in service and/or misfeasance in public office and that it has resulted in loss or injury. This Court has also laid down certain other guidelines which the Forum or the Commission has to follow in future cases.
We are informed that in spite of there being no stay, to payment of interest beyond 12% and in spite of clarification given by this Court's order (reported in (2004) 5 SCC 65), the amounts have still not been paid. We feel that for the lapse Appellants must pay interest at the rate of 15% from 17th March, 2004 till payment. Appellants shall also pay costs fixed at Rs.500/- in each case to the Legal Aid Society of the Supreme Court. The Appellants must recover the amount paid towards costs personally from the officer/s, who were responsible for not paying even after clarification by this Court. We clarify that this Order shall not be taken as a precedent in any other matter as the order has been passed taking special features of the case into account. The Forum/Commission will follow the principles laid down by this Court in the case of Ghaziabad Development Authority vs. Balbir Singh (supra) in future cases. The Appeals are disposed off in above terms. There will be no order as to costs.”
So it is clear that the compensation and rate of interest shall depend on the facts and circumstances of each case and no hard and fast rule can be framed. In this connection some of the judgement of the Supreme Court and Hon’ble NCDRC should be taken into account.
In the case of PRIYANKA MITTAL & ANR. V. PARSVNATH DEVELOPERS LTD. & ANR. (NCDRC).These appeals arise out of single order of State Commission, hence, decided by common order. These appeals have been filed against the order dated 25.2.2015 in Complaint Nos. 18 of 2013- Nalin Bhargava &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 34 of 2013- Jasleen Viswanathan &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 58 of 2011- Janmejai Mani Tiwari Vs. Parsvnath Developers Ltd. &Anr.; 68 of 2013- Indu Singh Vs. Parsvnath Developers Ltd. &Anr.; 69 of 2013- Poonam Sagar Vs. Parsvnath Developers Ltd. &Anr.; 86 of 2010- Priyanka Mittal &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 101 of 2011- Mohd. Aslam Khan &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 130 of 2012- Dr. Sunil Kr. Singh &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 49 of 2012- Neera Mittal &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 74 of 2011- Deepak Bhalla Vs. Parsvnath Developers Ltd. &Anr.; 87 of 2010- Syed Gufran Ali Alvi&Anr. Vs. Parsvnath Developers Ltd. &Anr.; 96 of 2011- Uppasana Malik Vs. Parsvnath Developers Ltd. &Anr.; 175 of 20130- Umesh Chandra Dixit &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 97 of 2011- Pravin Kumar Goel &Anr. Vs. Parsvnath Developers Ltd. &Anr. which complaints were partly allowed.
The Hon’ble NCDRC held that:
“Brief facts of the cases are that opposite parties/respondents are engaged in the activity of housing construction and accordingly they have launched a project named as Parsvnath Planet situated in Gomti Nagar, Lucknow. The project was demonstrated to be very lucrative and made attractive to the vendees, in order to procure/collect money from the needy persons demonstrating themselves to be excellence in the field of construction activity as compared to other builders and assured the buyers/complainants that it has been duly approved by the Lucknow Development Authority and necessary permission has also been obtained from them. The emphasis was made by the opposite parties that the possession of the Unit shall be given within a scheduled period of 36+6=42 months stipulated in agreements executed in between the parties for the project launched in the year 2006. The complainants/appellants attracted by the promise and assurance of the opposite parties, somehow managed and arranged the money from their personal sources as well as on loan at attractive rate of interest and the hard earned money was paid by them to the opposite parties in a hope that the possession of the units shall be provided to them in the year 2009 and they can leave peacefully in their own houses, since the complainants are living in rented houses.
The complainants visited the construction site of the opposite parties after depositing the entire amount, where it was revealed that the construction activities were on halt and the persons available on the site told the complainants that the apartments are likely to be completed till 2015. Even the partial construction done by the opposite parties was defective and did not match the specifications provided in the agreement. The complainants were shocked on hearing it and observing the site. The complainants immediately contacted the Area Manager, who told the complainants that there is some delay in the construction of the apartment and the apartments shall be ready till June, 2010. The complainants have to repay the amount taken on loan alongwith interest without getting the possession of the allotted units causing irreparable loss and injury to them. The complainants have come to know that the opposite parties have invested the funds earmarked for this project into their other projects in other city due to which they have not been able to complete the project in time. Besides this, it has also come to the light that although the opposite parties had collected huge funds from the buyers but in spite of that the opposite parties have miserably failed to pay the dues of Lucknow Development Authority which forced the Lucknow Development Authority to issue coercive measures against the opposite parties for the recovery of their dues. Alleging deficiency on the part of opposite parties/ respondents, complainants filed separate complaints before State Commission. Aggrieved by the order of Hon’ble State Commission, these appeals preferred before Hon’ble National Consumer Disputes Redressal Commission.
Hon’ble NCDRC discussed various case laws and after hearing the parties held,
“Learned Counsel for appellants submitted that as complainants have been deprived of possession for a long period beyond agreed period, it amounts to restrictive trade practice under and complainants are entitled to get compensation. Section 2 (nnn) runs as under:- means a trade practice which tends to bring about restrictive trade practice manipulation of price or its conditions of delivery or to affect flow of supplies in the market relating to goods or services in such a manner as to impose on the consumers unjustified costs or restrictions and shall include- Delay beyond the period agreed to by a trader in supply of such goods or in providing the services which has led or is likely to lead to rise in the price; Any trade practice which requires a consumer to buy, hire or avail of any goods, or, as the case may be, services as condition precedent to buying, hiring or availing of other goods or services; Perusal of aforesaid provision reveals that when opposite party delays in delivery of goods which leads to rise in the price of goods meaning thereby, more price is charged from complainant, it amounts to restrictive trade practice. In the case in hand, opposite party on account of delayed delivery of possession is not charging higher rate than the agreed rate for delivery of possession of flat, so, it does not fall within the purview of restrictive trade practice under ”
“Admittedly, agreements were executed in 2006 and as per agreements, possession of flats was to be delivered within 42 months, meaning thereby, possession was to be given in the year 2009-2010 and possession has not been handed over so far though year 2016 has started. No doubt, complainants are entitled to get penalty amount for delayed delivery of possession as per clause 10 ( c) of the agreement but opposite party cannot be permitted to avail benefit of aforesaid clause for indefinite period. This penalty clause should be allowed for the benefit of parties for a limited period and in the cases in hand, I deem it appropriate to extend applicability of aforesaid clause for a period of one year beyond 42 months and after that, complainants are certainly entitled to compensation. Opposite party cannot be allowed to avail huge funds of complainants by paying merely Rs. 5/- per sq. ft. for example, complainants who have purchased flat measuring 164.901 sq. mtr., they have made payment of about Rs. 31.00 to 32 lakhs and in the garb of clause 10 (c), opposite party is paying penalty @ approximately Rs. 9,000/- per month against enjoying funds more than Rs. 30.00 lakhs. As complainants have been deprived to shift to their flats for a long period which would not only have given them satisfaction of living in their own house but also have raised their social status and opposite party has enjoyed funds of complainants for a long period, I deem it appropriate to allow compensation @ Rs. 15,000/- p.m. to the complainants who have applied for flats upto 175 sq. mtr and Rs. 20,000/- per month to complainants who have applied for flats above 175 sq. after 54 months of execution of agreement till delivery of possession. ”
Against this judgment, parties went to Hon’ble Supreme Court. The judgment of Hon’ble Supreme Court is:-
In Nalin Bhargava vs. Parsvnath Developers Ltd. CA 6662/2018 @ SLP(C) 7596/2016 etc and other related civil appeals on 13 July, 2018, Hon’ble Supreme Court held:-
“Leave granted in all the special leave petitions.CA 6662/2018 @ SLP(C) 7596/2016 etc.
It is submitted by Mr. M.L. Lahoty, learned counsel appearing for the appellants in all the appeals that the possession has been handed over and the deficiencies have been removed and, therefore, he has no grievance. However, Mr. Lahoty would insist that there should be imposition of costs as compensation.
Mr. Sachin Datta, learned senior counsel appearing for the developer has raised objections with regard to imposition of costs.
Having heard learned counsel for the parties, we are of the considered opinion that the cause of justice would be best subserved if each of the appellants in the present appeals are given Rs.1,50,000/- (Rupees one lakh fifty thousand only) per flat, towards costs. When we say “cost”, we mean costs alone and nothing else.”
These builders are just earning money from the consumers to whom they issued allotment letters and got a huge amount. They keep this amount for a long time and earn interest on it. Property dealing is that part of business where they never pay a penny to the consumers on their amounts deposited for a long-term or if they pay, they pay a meagre interest of about 5% or so but they charge 18 to 24% or more if the consumers default in depositing any instalment. It reminds us the story of “The Merchant of Venice” The Merchant of Venice is the story of a Jewish money lender Shylock who demands that an antisemitic Christian offer “a pound of flesh” as collateral against a loan. These acts of builders also remind us the age of Sahukari during ancient India and also during British Raj. Whether these builders have power to frame their own law? They put their terms and conditions in such a way that the sufferer will always be the consumer. The Consumer Protection Act 1986 has been enacted for the benefits of consumers, so the courts dealing with Consumer Protection Act 1986 should come forward for their rescue. The courts are not governed by the builders but they are governed by the law, Custom and Usages. Now in the background of all the facts and also the facts of the present case, we will also discuss something more.
After taking account the main objects of the Consumer Protection Act, the facts and circumstances of the present case ,we will decide the amount of compensation and damages for the complainant. The opposite parties have objected that this flat has been taken by the complainant for the commercial use. The opposite parties have stated that the complainant did not ask for the possession of the flat but he prayed for the refund of his amount which shows that the flat was booked for commercial purposes and not for personal living . If a person who trusted the opposite parties and applied for a unit in the year 2012 and he did not get the flat or he was not given any flat by the opposite parties even after 10 years of the booking of the flat ,in such circumstances he may think better option to get refund otherwise that may also be not refunded to him. The allottees know that the builders have higher links that’s why they are going and collecting huge amount of money from the innocent allottees. If the complainant has asked for refund of his money, this will not show that he does not want the flat. Maybe he has purchased a flat somewhere else and therefore he is requesting for the refund of his money. If the opposite parties think so, we are inclined to see clause 6 of the relief which is “any other order which this Hon’ble commission may deem fit and proper in the circumstances of the case may also be passed”. So taking into consideration this relief clause now we are of the opinion that there should be an order for the delivery of possession of the flat with completion and occupancy certificate and also an order to execute the registry of the flat with completion certificate, occupancy certificate and NOCs of fire department, civil aviation department, pollution control Department etc and it should be done within eight weeks from the date of judgement of this complaint case otherwise after eight weeks the opposite parties shall jointly and severally liable to pay damages at a rate of ₹ 2 lakhs per month till the actual delivery of possession and execution of sale deed with all the relevant documents as mentioned above. Seeking refund of money deposited does not prove that this flat has been applied for commercial use or for reselling.
Now we take the facts and circumstances of the present case. In this case the complainant paid ₹ 35,14,033/– against the total price of ₹ 51,07,355/, so about 70% of the basic cost has already been paid by the complainant and he did not get the possession of the flat as promised by the opposite party within the time limit framed by the opposite parties which was 42 months. After considering all the above-mentioned judgements of the Hon’ble Supreme Court and Hon’ble NCDRC we are of the opinion that the complainant is entitled for the following reliefs:-
The complainant is entitled to get possession of the flat as allotted provisionally bearing unit reference number GDI 0240104 situated in“Garden Isles” at Jaypee Greens Noida within eight weeks from the date of judgement of this complaint case on depositing the rest amount of ₹ 51,07,355 / without any interest and if the possession was not delivered to him with completion and occupancy certificate and NOC’s of fire department, civil aviation department, pollution control Department etc , complainant will be entitled to get ₹ 2 lakhsper month after eight weeks from the date of judgement of this complaint case..
In Alternative
The complainant is entitled to get the present market value of the flat that exist today as per valuer report with interest at a rate of 9% on this amount from 15.10.2015 till the date of actual payment.
The complainant is entitled to get ₹ 15,000 per month starting from 15.10.2015 till the date of actual payment with interest at a rate of 10% per annum and it should be paid within eight weeks from the date of judgement of this complaint case and if not paid within eight weeks from the date of judgement of this complaint case, the complainant will be entitled for interest at a rate of 15% from 15.10.2015 till the date of actual payment.
The complainant is entitled to damages of ₹ 1.5 lakhs as per judgement of the Hon’ble Supreme Court.
For relief number three we are of the opinion that the complainant is entitled to get ₹ 40 lakhs from the opposite parties within eight weeks from the date of judgement of this complaint case towards the mental torture, agony, harassment and depression and this amount if not paid within eight weeks from the date of judgement, the complainant will be entitled to receive interest at a rate of 10% on this amount after eight weeks from the date of judgement of the complaint case.
The complainant is entitled to get ₹ 1 lakh towards cost of the case and it shall be paid within eight weeks from the date of judgement, the complainant will be entitled to receive interest at a rate of 10% on this amount after eight weeks from the date of judgement of the complaint case till the actual payment.
Therefore the complaint case is allowed accordingly and the following order is being passed .
ORDER
- The opposite parties are directed jointly and severally to hand over the possession of the flat as allotted provisionally bearing unit reference number GDI 0240104 situated in “Garden Isles” at Jaypee Greens Noida within eight weeks from the date of judgement of this complaint case on depositing the rest amount of ₹ 51,07,355 / without any interest and if the possession was not delivered to him within eight weeks along with completion and occupancy certificate and NOC’s of fire department, civil aviation department, pollution control Department etc , complainant will be entitled to get ₹ 2 lakhs per month after eight weeks from the date of judgement of this complaint case.
In Alternative
The opposite parties are jointly and severally to pay the amount of the flat at market rate as exist today on the basis of a valuer report within eight weeks from the date of judgement of this complaint case with interest at a rate of 9% on this amount from 15.10.2015 till actual payment.
- The opposite parties jointly and severally are directed to pay ₹ 15,000 per month starting from 15.10.2015 till the date of actual payment with interest at a rate of 10% per annum and it should be paid within eight weeks from the date of judgement of this complaint case and if not paid within eight weeks from the date of judgement of this complaint case, the opposite parties shall pay interest at a rate of 15% from 15.10.2015 till the date of actual payment.
- The opposite parties , jointly and severally , are directed to pay ₹ 1.5 lakhs as damages to the complainant which shall be paid within eight weeks from the date of judgement of this complaint case, and if not paid within eight weeks from the date of judgement of this complaint case, the opposite parties shall pay interest at a rate of 10% after eight weeks from the date of judgement of this complaint case till actual payment.
- The opposite parties , jointly and severally, are directed to pay ₹ 40 lakhs to the complainant towards mental agony, torture, harassment and depression which shall be paid within eight weeks from the date of judgement of this complaint case, and if not paid within eight weeks from the date of judgement of this complaint case, the opposite parties shall pay interest at a rate of 10% after eight weeks from the date of judgement of this complaint case till actual payment.
- The opposite parties , jointly and severally, are directed to pay ₹ 1 lakh to the complainant towards cost of the case which shall be paid within eight weeks from the date of judgement of this complaint case, and if not paid within eight weeks from the date of judgement of this complaint case, the opposite parties shall pay interest at a rate of 10% after eight weeks from the date of judgement of this complaint case till actual payment.
All the decretal amount shall be paid within eight weeks from the date of judgment of this complaint case, otherwise the opposite parties shall pay interest at the rate as mentioned in each direction of the judgement. If it is not paid within eight weeks from the date of judgment of this Complaint Case, the complainant shall be entitled to present Execution Proceedings before this court at the cost of the opposite parties.
The stenographer is requested to upload this order on the Website of this Commission today itself.
Certified copy of this judgment be provided to the parties as per rules.
(Vikas Saxena) (Rajendra Singh)
Member Presiding Member
Judgment dated/typed signed by us and pronounced in the open court.
Consign to the Record Room.
(Vikas Saxena) (Rajendra Singh)
Member Presiding Member
Dated October 07 , 2022
JafRi, PA II
C-2