(Delivered on 19/12/2018)
PER SHRI B.A. SHAIKH, HON’BLE PRESIDING MEMBER.
1. We have heard advocate Mr. Aditya Joshi holding for advocate Mr. Sachin Jaiswal appearing for the appellant and advocate Mr. Vora appearing for the respondent No. 1 on the application made by the appellant for condonation of delay of 82 days that occurred in filing of the appeal. We have also perused the record and proceedings of the appeal. The respondent No. 2 is already proceeded exparte.
2. The learned advocate of the appellant explained the delay on the lines of the submission made in the said application. The explanation given in the application in short is that the copy of the impugned order dated 29/09/2016 was received by the appellant from the Forum below on 29/10/2016. The said copy was forwarded by the appellant’s advocate to the department along with his opinion for filing of appeal. The office of the appellant forwarded the said opinion along with copy of the impugned order to the Head Office at Jaipur for necessary guidance. The concerned officer of the appellant company after consultation of the Senior Executive Member decided to file the appeal before this Commission. The said decision was communicated to the Nagpur /local office of the appellant. The Nagpur office requested the counsel to take appropriate steps in the matter for filing of appeal. Thereafter appeal came to be filed. In that process the delay of 82 days has been occurred.
3. The learned advocate of the appellant submitted that as the delay is satisfactorily explained as above, it may be condoned. He also relied on the decision of the Hon’ble National Commission in the case of Dileep Kumar Vs. Jaipur Development Authority , in Revision Petition No. 3040/2016 decided by the Hon’ble National Commission as per order dated 27/04/2017.
In aforesaid case, the delay of 77 days that occurred in filing of appeal before the State Commission was condoned by the State Commission, Rajasthan. Thereafter, feeling aggrieved by that condonation of delay, the Revision Petition No. 3040/2016 was filed before the Hon’ble National Commission.The Hon’ble National Commission in that revision petition observed as follows.
“It is clear that the State Commission is well within its rights to condone the delay if it is satisfied. From the observations of the State Commission mentioned above it is clear that the State Commission was satisfied in the interest of justice to condone the delay. As per guidelines given by the Hon’ble Supreme Court in the case of Esha Bhattacharjee Vs. Managing Committee of Raghunathpur Nafar Academy and others and judgment of Hon’ble Supreme Court in case of N. Balakrishnan Vs. M. Krishnamurthy, the condonation of delay may be allowed on payment of cost to the other party. In both the cases cited by the learned counsel there are inordinate delays of 233 days and more than 1000 days, whereas in the instant case the delay is only of 77 days. The Forum has rightly condoned the delay in the interest of justice. Even otherwise also, by allowing the application for condonation of delay, the State Commission has decided to proceed with the appeals and expectedly these appeals will be decided on merits and both parties will get the opportunity to put forward their cases before the State Commission for adjudication of the appeals. Hence, no prejudice is caused to the petitioners if the appeals are decided on merit by the State Commission.”
Thus, learned advocate of the appellant submitted that the application may be granted by applying aforesaid observations made by the Hon’ble National Commission.
4. On the other hand, the learned advocate Mr. Vora appearing for the respondent No. 1 filed reply to the said application and strongly apposed the same. His submission in brief is that no date wise explanation is given by the appellant and stereo type grounds are raised in each of the appeal by the appellant without substance and without filing any documents. He also relied on the decisions of this Commission in two cases. He submitted that in those cases also identical grounds were raised by the petitioner for condonation of delay but this Commission after hearing both the parties, rejected the applications made in both cases by giving cogent reasons. He submitted that in the instant case also no cogent and satisfactorily explanation for delay is given and no document is filed to show that the impugned order with opinion was sent from one office to another office for approval. There is actual delay of 99 days that occurred in filing of appeal. He also submitted that signatory of the application is not an authorized person and he in its affidavit has not stated that he is authorized person. Advocate Mr. Vora further submitted that appellant has not filed any power of attorney or resolution of the Board of Directors to show that the appellant has duly authorized the aforesaid signatory for filing of the appeal. Hence, on these grounds he requested that application made for condonation of delay may be rejected.
5. The learned advocate Mr. Vora relied on the following two decisions of this Commission.
i. Iffco -Tokio General Insurance Co. Ltd. Vs. Bashir Khan Ajij Khan in First Appeal No. FA/12/467 decided by this Commission on 28/09/2016. In that case there was delay of 110 days that occurred in filing of appeal. It is observed by this Commission that no such long delay can be occurred simply for seeking administrative approval of higher authority for filing of appeal. Hence, this Commission rejected the application made for condonation of delay.
ii. Shriram General Insurance Co. Ltd. Vs. Gurlochansingh Harcharansingh Ghoitra in First Appeal No. A/17/72, decided by this Commission as per order dated 24/01/2018. In that appeal there was inordinate delay of 110 days for filing of an appeal. It is observed by this Commission that the said delay was occurred only because of inaction and gross negligence on the part of the appellant in taking immediate steps required for filing of appeal. It is also observed by this Commission that if such a long delay is condoned without sufficient explanation, then it would defeat the very object of expeditious disposal of the proceeding under the Consumer Protection Act, 1986. Hence, this Commission rejected the application made for condonation of delay.
6. It is seen that the copy of the impugned order was received by the appellant on 29/10/2016. Therefore, the appeal ought to have been filed on or before 28/11/2016. But appeal was filed on 08/03/2017. Thus there is actual delay of 99 days that occurred in filing of appeal.
7. No date wise explanation of the said delay of 99 days is given in the application. It is not stated in this application as to on which date the copy of the impugned order was forwarded by advocate of the appellant to the local office of the appellant and on which date the local office of the appellant forwarded the copy of the impugned order along with opinion of advocate to the Head Office of the appellant for necessary guidance. It is also not stated in this application as to on which date the Senior Executive Member decided to file the appeal and on which date said decision was communicated to Nagpur Office of appellant and on which date the counsel of Nagpur was instructed by appellant for filing of appeal. Moreover, no document is filed in support of the application about sending copy of the impugned order to the Head Office and about decision taken by the Head Office for the purpose of filing of appeal. Therefore, it is very difficult to accept that actually any such steps were taken by the appellant before filing of appeal. Even if it is assumed that said steps were taken for purpose of filing of appeal, then also we find that as no such long delay of 99 days can occur for taking such steps. Hence, the explanation given as above cannot be said to be satisfactorily or convincing, for the purpose of condonation of delay.
8. We also find that the aforesaid decisions of the Hon’ble National Commission as relied by the learned advocate of the appellant is not applicable to the facts and circumstances of the present case. In that case the delay of 77 days only had occurred in filing of appeal before the State Commission and it was condoned for the reasons mentioned in the said decision. However, in the instant case there is delay of 99 days and no satisfactorily explanation is given by the appellant for the said delay as discussed above. Thus, the facts and circumstances of the present case are totally different from the facts and circumstances of the said case. Hence, the said decision relied on the learned advocate of the respondent No. 1 is applicable to the present case.
9. We further find that if such a long delay of 99 that occurred in filing of appeal is condoned without any satisfactorily explanation then it will defeat the very object of expeditious disposal of appeal filed under the Consumer Protection Act, 1986. Thus, we are of the view that the 99 days delay has been occurred simply because of total inaction and gross negligence on the part of the appellant in taking prompt and diligent steps. Hence, the said delay cannot be condoned. Accordingly, the following order is passed.
ORDER
i. The application made for condonation of delay is rejected.
ii. Appeal is dismissed as time barred.
iii. No order as to cost in appeal.
iv. Copy of order be furnished to both parties, free of cost.