West Bengal

Nadia

CC/165/2018

MAKBUL RAHAMAN - Complainant(s)

Versus

Franchisee Branch Manager Sahara Credit Cooperative Society Ltd. - Opp.Party(s)

19 Jul 2019

ORDER

DISTRICT CONSUMER DISPUTES REDRESSAL FORUM
NADIA
170,DON BOSCO ROAD, AUSTIN MEMORIAL BUILDING.
NADIA, KRISHNAGAR
 
Complaint Case No. CC/165/2018
( Date of Filing : 01 Oct 2018 )
 
1. MAKBUL RAHAMAN
S/o HABIBUR RAHAMAN Vill.- Saratpally P.O. Bethuadahari, P.S. Nakashipara PIN-741126
Nadia
West bengal
...........Complainant(s)
Versus
1. Franchisee Branch Manager Sahara Credit Cooperative Society Ltd.
Bethuadahari Branch, Sahara India Parivar, Vill.- Bethuadahari P.O. Bethuadahari, P.S.- Nakashipara PIN 741126
Nadia
West Bengal
2. Regional Manager, Sahara Credit Cooperative Society Ltd.
Sahara I ndia Parivar, 50/2 Karbala Rd., P.O.- Cossimbazar Raj, P.S. Berhampore, PIN 742102
Murshidabad
West bengal
3. Area Manager, Sahara Credit Cooperative Society Ltd.
Sahara I ndia Parivar, 3rd Floor, Sefali Sadan, Opposite L.I.C. Office S.F. Road, P.O. Siliguri, PIN 734005
Darjeeling
West Bengal
4. M.D. (Subrata Roy) Sahara Credit Cooperative Society Ltd.
Sahara Credit Cooperative Society Ltd. Sahara India Parivar, Sahara India Bhawan 1, Kapoortahla Complex Aliganj , Lucknow PIN 226024
LUCKNOW
U P
............Opp.Party(s)
 
BEFORE: 
 HON'BLE MR. SHYAMALENDU GHOSAL PRESIDENT
 HON'BLE MR. NARAYAN CHANDRA CHATTERJEE MEMBER
 HON'BLE MRS. SMT. ASHOKA GUHA ROY (BERA) MEMBER
 
For the Complainant:
For the Opp. Party:
Dated : 19 Jul 2019
Final Order / Judgement

Ld. Advocate(s)

          For Complainant   ..    Pramin Kr. Singh

          For OP/OPs     ..    Nabanita Kar and Golam Ashik

 

Date of Filing           : 01.10.2018

Date of Disposal      : 19.07.2019

 

:    JUDGMENT & ORDER  dtd. 19.07.2019   :        

 

Nonpayment of the maturity amount of two fixed deposits of the depositor herein, the complainant has obliged him to lodge this complaint u/s 12 of the C.P. Act 1986 for redressal.

The brief fact of the case is that the complainant had two F.D. certificates bearing numbers 705 001209214 and 705 001209215  for the amount of Rs.16,000/- + Rs.17,000/- = Rs. 33,000/- for the period from 15.07.2017 to 15.07.2018  ,i.e., for the period of  12 months with the OP No.1.  According to the condition of the F.D. Certificates, the complainant is entitled to get total deposited money of Rs. 17,440/- + Rs. 18,530/- = Rs.35,970/- + up to date interest as per norms of the OPs.  The complainant has made claim as per rule but no payment has been made by the OPs.  The complainant in his averment had prayed for directing the OPs to refund of Rs.35,970/- + up to date interest as per norms of the Ops, a compensation of Rs.25,000/- for harassment and mental agony and Rs. 10,000/- as litigation cost.

After receiving the notice, the Ld. Lawyer on behalf of the OPs Sahara India Parivar appeared before this Forum several times and filed a written version on the ground stated therein which is kept in the record.  Thereafter he never came to this Forum.  He also verbally submitted that the OPs are not in a position to make payment to the complainant.   

On argument the Ld. Lawyer for the complainant argued that she had submitted proper demand notice but the OPs gave no reply. 

On 16.07.19, the Ld. Lawyer for the complainant filed a petition stating that the OP had already paid Rs.18,530/- for one certificate being No. 705001209215 to the complainant out of Rs.35,970/-.  Now, the complainant is entitled to get the rest amount of Rs.35,970/- -  Rs.18,530/- = Rs.17,440/- + up to date interest as per norms of the OPs.

From the above discussion and as per original document which is in the record, it is clear that the complainant is entitled to get the rest amount of Rs.17,440/- only together with up-to-date interest as per norms of the OPs.  It is the deficiency in service on the part of the OPs not to make payment of the rest amount in time.  The complainant is not responsible for the internal disturbance of the OPs.

Hence, it is

O R D E R E D,

That the OPs are directed to refund of Rs.17,440/- + up-to-date interest to the complainant as per norms of the OPs within 30 days from the date of this order, failing which an interest @ 10% p.a. shall be imposed on the total amount up to the date of this order.  A compensation of Rs.3,000/- for harassment and mental agony and litigation cost of Rs. 2,000/- are to be paid to the complainant by the OPs within 30 days from the date of this order.

That the case be and the same succeeds on contest against the OPs.

            Let a plain copy of this order/judgment be supplied to the parties forthwith free of cost.

 
 
[HON'BLE MR. SHYAMALENDU GHOSAL]
PRESIDENT
 
[HON'BLE MR. NARAYAN CHANDRA CHATTERJEE]
MEMBER
 
[HON'BLE MRS. SMT. ASHOKA GUHA ROY (BERA)]
MEMBER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.