ORDER

STATE CONSUMER DISPUTES REDRESSAL COMMISSION
WEST BENGAL
11A, Mirza Ghalib Street, Kolkata - 700087
 
Revision Petition No. RP/166/2016
(Arisen out of Order Dated 08/09/2016 in Case No. Complaint Case No. CC/78/2016 of District Hooghly)
 
1. Station Manager, WBSEDCL
Bally More, C.C.C., Kalitala near Bandel Church, Dist. Hooghly, Pin- 712 103.
...........Appellant(s)
Versus
1. Dr. Chandra Chatterjee
D/o Lt. Abani Kumar Chatterjee, 28, Tewari Para Lane, P.O. & Dist. Hooghly, P.S. - Chinsurah, Pin - 712 014.
...........Respondent(s)
 
BEFORE: 
 HON'BLE MR. SAMARESH PRASAD CHOWDHURY PRESIDING MEMBER
 HON'BLE MRS. MRIDULA ROY MEMBER
 
For the Petitioner:Mr. Srijan Nayak, Mr. Alok Mukhopadhyay, , Advocate
For the Respondent:
Dated : 05 Oct 2016
Final Order / Judgement

Date of filing: 29.08.2016

Date of hearing: 29.09.2016

PER HON’BLE SAMARESH PRASAD CHOWDHURY, PRESIDING MEMBER

     The instant Revisional Application under Section 17(1)(b) of the Consumer Protection Act, 1986(hereinafter referred to as ‘the Act’ ) is at the behest of Opposite Party to impeach the Order no.08 dated 08.09.2016 passed by the Ld. District Consumer Disputes Redressal Forum, Hooghly (for short, Ld. District Forum) in Consumer Complaint No.78 of 2016 thereby the Ld. District Forum directed the Inspector-in-charge, Chinsurah P.S. to execute the Warrant against the Station Manager, West Bengal Distribution Company Ltd.(WBSEDCL), by 14.09.2016.

     The Opposite Party herein Smt. Chandra Chatterjee approached the Ld. District Forum with the instant consumer complaint with prayer for certain reliefs, viz – (a) a direction upon the Station Manager, WBSEDCL to reconnect the electric connection immediately; (b) a direction to pay an amount of Rs.10,00,000/- as compensation for harassment and mental agony; (c) a sum of Rs.35,000/- as litigation cost etc.  

     Upon hearing the Ld. Advocates appearing for the parties and on going through the materials on record, it would reveal that the prayer for reconnection has been made in respect of a deceased person named Prafulla Kumar Mukherjee at Tewaripara, Ballymore, Hooghly.  The said Prafulla Kumar Mukherjee passed away on 11.11.1976 leaving behind him his wife - Prabhavati Mukherjee, son – Sunil Mukherjee, since deceased and one daughter – Ira Chatterjee, since deceased.  The Complainant claimed herself as the granddaughter of said deceased Prafulla Kumar Mukherjee.  Prafulla Kumar installed electric connection on 23.11.1994.  It was a three phase connection with three single phase meter having contractual demand being 0.76 KW.  Those meters were installed without PP Box and all the three meteres were found defective on 25.02.2013.  Accordingly, those three defective meters were replaced by good static meters with PP Box on 28.06.2013.  Therefore, average bills were raised based on connected load and consumption for two quarters in the year 2013. 

     After installation of new meter, the bill was raised and on 22.09.2014, it was showing consumption units of 1754 units for the period from September to November, 2013 amounting to Rs.13,498/-.  The OP herein initiated a Misc. Petition being MP no.1062/2013 on 27.10.2013 before the First Court of Ld. Executive Magistrate, Hooghly alleging against the Station Manager and its staff.  The said Misc. Petition was dropped on 05.12.2014 and the line was disconnected on 10.12.2014.  The OP herein, thereafter, filed one consumer complaint being CC/265/2014 before the Ld. District Forum.  On 07.01.2015, the Ld. District Forum was pleased to direct the Station Manager to reconnect the line within three days after receipt of Rs.6,000/-.  The Station Manager of WBSEDCL duly obeyed such order and reconnection was done on 24.01.2015.  After such reconnection, the bills amounting to Rs.18,185/- was sent, but the Complainant did not deposit the same.  On 16.06.2105 the CC/265/2014 was dismissed for default.  Ultimately, on 30.09.2015 the line was disconnected due to non-payment of outstanding amount of electric bill. 

     In this backdrop, on 01.06.2016, after a long delay of eight months from the date of disconnection, the instant consumer complaint has been filed.  The petition of complaint was defective one and as such on 30.06.2016 the prayer for amendment of petition of complaint was allowed.  On that date, the Complainant moved an application with a prayer for interim relief by way of direction upon the OP/WBSEDCL to restore electric connection.  The order itself speaks – “considering all aspects, we are of the view that the matter is to be considered with humanitarian aspects.  In the scheduled property only two lady members reside and any prudent man can presume the sufferings of those two lady members without electricity”.  The said order goes to show that an amount of Rs.98,000/- was due and payable by the Complainant and as out of the said amount Rs.6,000/- was deposited, the OP/WBSEDCL shall restore electric connection within three days. 

     We are afraid that in passing the order impugned, Ld. District Forum did not consider the merit of the case but swayed by emotions.  Such a thing is beyond the scope of a judicial authority.  There was no urgency at all in the matter because the line was disconnected on 30.09.2015 for non-payment of electric bills and the Complainant approached the Ld. District Forum on 01.06.2016.  Even on the date of filing of the complaint, the prayer for interim relief was not moved and after rectification of defects on 30.06.2016, prayer for restoration of electric connection was made and the Ld. District Forum did not consider it wise to issue notice upon the OP to ascertain the actual state of affairs.

     Needless to say, a Court of law cannot pass any order on equitable grounds.  At the time of consideration of prayer, Ld. District Forum should have considered that the bill raised by the OP/WBSEDCL is a public money.  The Complainant raising the billing dispute never approached the Central Grievance Redressal Officer (CGRO) or has not made any prayer before the Ld. District Forum for appointment of a technical person to ascertain whether the meter reading was defective or not.

     We must not be obsessed with the fact that a Consumer Forum cannot be a subject for unjust enrichment.  The Ld. District Forum has passed the order without giving any opportunity to the OP and as such could not understand the real fact behind the episode.  The Ld. District Forum has not assigned any reason under what basis, it has asked the Complainant to deposit Rs.6,000/- when according to the statement of Complainant herself in their brief note of argument that at least a sum of Rs.15,000/- and odd should have been deposited.  It is true that having regard to the laudable object behind the legislation of the Act to protect the interest of consumers, liberal interpretation has to be placed on the scheme of the Act avoiding hyper technical approach.  At the same time, fair procedure is the hall mark of every legal proceeding and an affected party is entitled to be put to notice of the claim which such affected party has to meet.

     We are not unmindful to the provisions of Section 17(1)(b) of the Act which authorises this Commission to invoke its revisional power for a limited purpose only on the ground of jurisdictional error or material irregularity.  Unless the material irregularity is patent, this Commission being a Revisional Forum do not usually interfere into the order passed by the Ld. District Forum.  In the instant case, the irregularity is so apparent that unless this Commission exercises its revisional power, then it would cause miscarriage of justice.

     In view of the above, the instant revision petition is allowed on contest.  Considering the facts and circumstances of the case, however, we do not make any order as to costs.

   Consequently, the order no.08 dated 08.09.2016 which emanates from Order no.3 dated 30.06.2016 in connection with CC/78/2016 passed by the Ld. District Forum is hereby set aside.

    MA/905/2016 is, thus, rejected on contest and stands disposed of.

    The W.A. already issued against the Station Manager of WBSEDCL, Ballymore C.C.C. be recalled.

    The Registrar of this Commission is directed to send a copy of this order to the Ld. District Consumer Disputes Redressal Forum, Hooghly at Chinsurah for information.

          

 
 
[HON'BLE MR. SAMARESH PRASAD CHOWDHURY]
PRESIDING MEMBER
 
[HON'BLE MRS. MRIDULA ROY]
MEMBER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.