Shri. Pijush Kanti Dutta filed a consumer case on 09 Dec 2019 against Dr. Achintya Bhattacharya (Developer) in the StateCommission Consumer Court. The case no is A/25/2019 and the judgment uploaded on 10 Dec 2019.
Tripura State Consumer Disputes Redressal Commission, Agartala.
Case No.A.25.2019
S/o Late Adhinath Dutta,
43, Akhaura Road, P.O.-Agartala-799001,
P.S. West Agartala, District - West Tripura.
… … … … Appellant/Complainant.
Vs
S/o Late Sushil R. Bhattacharya,
Resident of Ramnagar Road No.5,
C/o Teresa Diagnostic Centre,
7 Hospital Road, P.O. Agartala - 799001,
P.S. West Agartala, District - West Tripura.
W/o Shri Ashish Sen,
Resident of Pragati Road, (Near Ice Factory),
P.O. Agartala - 799001, P.S. East Agartala,
District - West Tripura.
… … … … Respondent/Opposite Party No.1 and 2.
PRESENT
Hon’ble Mr. Justice U.B. Saha
President,
State Commission
Dr. Chhanda Bhattacharyya,
Member,
State Commission
For the Appellant: Mr. Jayanta Majumder, Adv.
For the Respondents: Mr. Kanu Lal Das, Adv.
Date of Delivery of Judgment: 09.12.2019.
J U D G M E N T
U.B. Saha, J,
The instant appeal is directed against the judgment dated 05.08.2019 passed by the learned District Consumer Disputes Redressal Forum (hereinafter referred to as District Forum), West Tripura, Agartala in Case No.C.C.135 of 2017 whereby and whereunder the learned District Forum dismissed the complaint petition. Hence, the appeal.
The complainant, Sri Pijush Kanti Dutta, being the land owner entered into an agreement on 28.03.2014 with the opposite party-Developers, Dr. Achintya Bhattacharya and Mrs. Lili Sen for development of the land by demolishing the old structure for construction of G+3 storied building on the land of the complainant. As per clause-1.10 of the Agreement, the complainant shall be entitled to get the entire second floor of the newly constructed building consisting of two flats having 800 sq. feet carpet area each, one number of garage at the ground floor and 50% of the roof of the top floor and also Rs.30,00,000/- which shall not be adjusted from the owner's share. As per clause-12.1 of the Agreement, the Developers will get maximum time for getting the plan sanctioned by the appropriate authority within a period of six months from the date of execution of the Agreement and that if the Developers do not succeed in getting the plan sanctioned, the complainant shall extend the period by another two months. Thus, the Developers under the agreement shall have to complete the construction work within 26 months (18+8). In clause-12.3 of the said Agreement, it has been incorporated that in case the construction is not completed within 26 months, then the Developers shall be liable to pay compensation to the complainant @ Rs.24,000/- per month towards rent for the time taken beyond 26 months till the date of handing over the possession of the flats.
The complainant alleged in the complaint petition that the total period of completion of building and handing over the same to the complainant took 38 months by the opposite parties. As a result of which, as per the agreement, the Developers are liable to pay an amount of Rs.2,88,000/- (Rs.24,000/- X 12) to the complainant. As per clause-9.1, the Developers shall be solely responsible for construction of the building as per sanctioned plan including other amenities as required for habitation in the building.
The complainant also alleged in his complaint petition that at the time of taking over possession of his flats, he found that one permanent structure measuring 1100 sq. feet more or less having brick wall with cement plastering with doors and windows affixed thereon has been constructed at the northern side on the ground floor by the Developers for utilizing the same as go-down by them and that was done without the consent of the complainant and beyond the approved plan of the Agartala Municipal Corporation (AMC). The complainant raised strong objection to the said illegal construction. The Developers had assured him to demolish the additional construction, but they did not demolish it, rather they have got benefit out of the aforesaid constructed place. According to the complainant, by constructing such a permanent structure on the ground floor, the purpose of keeping the ground floor open for parking has totally been frustrated and this also caused great inconvenience to the complainant as well as the inhabitants of the building. The complainant had sent three letters dated 21.09.2017, 27.10.2017 and 25.11.2017 requesting the Developers to demolish the additional construction which had been raised in the ground floor.
The complainant further alleged in his complaint petition that instead of demolishing it, the Developers sold the premises to Sri Gautam Saha and other on 08.12.2017 at the cost of Rs.20 lac showing the constructed place as a covered garage. According to the complainant, the Developers sold it behind his back and deprived him of getting due amount from it. The complainant in his complaint petition also stated that the developers failed to furnish completion/occupancy certificate to him from the AMC.
Being aggrieved by the action of the Developers, the complainant filed an application under Section 12 of the Consumer Protection Act, 1986 before the learned District Forum alleging deficiency of service by the opposite parties and prayed for compensation of Rs.18,45,056/- including cost of litigation.
“5. DECISION AND REASONS FOR DECISION:
We have heard arguments from both sides' Advocates. Both sides Advocates have also submitted written arguments. Learned Advocate for the O.Ps. in support of his arguments has also referred to a decision of our Hon'ble State Commission reported in (2011) 4 CPJ at page 63 (in case no. F.A.27 of 2011, between Binay K. Bhattacharya – Appellant Vs Agartala Municipal Council – Respondent).
It was argued by Learned Advocate for the Complainant that the O.P. Developers had taken extra time of 12 months beyond the stipulated period of 26 months for completion of building and handing over the same to the Complainant and as such as per clause 9 of the Development Agreement, the O.P. Developers are liable to pay an amount of Rs.2,88,000/- (24,000/- x 12 months) as compensation to the Complainant.
Secondly, it was argued that the O.P. Developers without the consent of the Complainant raised a permanent structure measuring 1100 sq. feet more or less having brick wall with cement plastering, doors and windows affixed thereon at the Northern side of the ground floor which is parking space and that the said construction had been done beyond the approved plan of the AMC. The O.Ps also sold out the aforesaid construction area to Sri Gautam Saha & Sri Tapan Debnath on consideration of an amount Rs. 6,36,000/- depriving due share of the complainant. It was also argued that in spite of objection of the Complainant, the O.P. Developers raised the said illegal construction. Though the O.Ps. had promised to the Complainant to demolish it but they did not keep their promise. It was further argued that due to the illegal construction raised on the Northern side, the parking space became congested on account of hindrance to the movement of air in the parking space. This causes much inconvenience to the Complainant as well as to the inhabitants of the building.
Lastly, it was argued by Learned Advocate for the complainant that the Developers have failed to hand over final occupancy certificate to the complainant as required under the Building Rules. Learned Advocate has thus concluded his argument with the submission that the Complainant was entitled to get Rs.18,45,056/- in total as compensation including cost of litigation from the O.Ps. Developers.
Per-contra, Learned Advocate appearing for the O.Ps. argued that the O.Ps. have handed over the possession of flats including Complainant's allocated entire share to the Complainant in time in compliance with the clause V and clause 12.3 of the Development Agreement dated 28/03/2014. According to the Learned Advocate, the period of time for handing over of the constructed building to the complainant is to be reckoned from the date on which the plan was sanctioned or handing over the peaceful vacant position of the land to the Developers whichever is later. Moreover, as per clause 12.3 of the Agreement, the O.P. Developers are also entitled to get extra period which was necessitated for the grounds/reasons beyond their reasonable control.
Learned Advocate submitted that the AMC had approved the building plan on 16/10/2015 and handing over the possession of the building to the Complainant was done on 28/05/2017. So it took only 19 months 13 days time in place of 18 months for completing handing over of the building to the Complainant. According to the Learned Advocate the extra time of one month thirteen days was spent due to the grounds / reasons beyond the control of the O.P. Developers. The O.Ps. are entitled to take such benefit under clause 12.3 of the Development Agreement. With this submission Learned Advocate has contended that the Complainant is not entitled to get any compensation on this count.
Regarding the plea of the complainant as to the additional construction measuring 1100 sq feet on the Northern side in the ground floor, Learned Advocate argued that the alleged area in the ground floor is one of the garage spaces which had to be blocked by erecting brick wall for security purpose and that it was done in order to prevent incident of theft. Moreover, the construction was done by the O.Ps. in parity with the approved plan of the AMC. Learned Advocate further argued that the plea of the Complainant that he & other inhabitants were suffering inconvenience due to the construction raised on the Northern side in the ground floor has not been substantiated by the complainant as none of the inhabitants of the building came forward to support such plea of the Complainant before the Forum. Learned Advocate in support of this argument has refereed to a decision rendered by our Hon'ble State Commission reported in (2011)4 CPJ at page 63 (in case no. F.A.27of 2011, between Binay K. Bhattacharya – Appellant Vs. Agartala Municipal Council – Respondent).
Learned Advocate appearing for the O.Ps., has lastly argued that the Complainant has been given Provisional Occupancy Certificate by the AMC on 20/04/2017 and the same is still continuing.
According to the Learned Advocate the Complainant has failed to produce cogent evidence to prove his case. He has thus prayed for rejection of the complaint with costs.
We have considered the submissions of both sides' Advocates.
We have gone through the pleadings of the both sides, oral and documentary evidence of the Complainant and that of one of the O.P. Developers, materials on record and the written arguments furnished by both sides.
We find that the contention of the complainant that O.P. Developers took extra 12 months beyond the provisions of the Development Agreement does not appear to us having any substance. We find that as per Article V of the Development Agreement, the Developers have to complete the construction of the building within 18 months from the date of obtaining sanctioned plan and / or handing over the peaceful vacant possession of the land whichever is later. In the instant case the Developers got the building plan sanctioned by the AMC on 16/10/2015 and the Developers after completing the construction have handed over possession of the building to the Complainant on 28/05/2017. So it took 19 months and 13 days for the Developers to get the building construction work completed and also handing over the possession of it to the Complainant. The O.Ps. in their W.O. as well as in the statement on affidavit have clearly explained the reasons for one month and thirteen days delay in handing over the possession of the building. The delay explained by the O.P. Developers has not been controverted by the Complainant. We also find that as per Article 12.3 of the Development Agreement, the Developers can be exempted from paying compensation if the delay was caused due to Force MeaJeura or circumstances which were beyond the control of the O.P. Developers. The cause of delay explained by the O.Ps. according to us is reasonable and we have accordingly accepted it.
The allegation of the Complainant about raising of additional structure on the Northern sides of the garage space in the ground floor, we find that the space where the construction was done it falls within the Developers' allocated portion as described under Article VIII of the Development Agreement and that for raising such construction and selling of it prior consent of the Owner of the land is not necessary. Moreover, the Complainant has failed to produce any iota of evidence to prove that the construction that had been raised contravenes the approved plan of the AMC. The Complainant also has failed to establish his another allegation that due to raising of such construction he and the inhabitants of the building are / were suffering inconvenience. We find that except the Complainant no other flat owners in the building came forward to support the plea of the Complainant. Hence, we are not inclined to accept that allegation of the Complainant. In arriving this decision we have relied upon the decision of the Hon'ble State Commission reported in (2011) 4 CPJ at page 63 (in case no. F.A.27of 2011, between Binay K. Bhattacharya–Appellant Vs. Agartala Municipal Council – Respondent) as referred to by Learned Advocate for the O.Ps.
We further find that the complainant has already been furnished Provisional Occupancy Certificate by the AMC on 20/04/2017 and the said Certificate is still in force. The Complainant did not disclose either in his complaint or in his Statement on Affidavit as to how has he been affected due to non furnishing of Final Occupancy Certificate.
Hence, we do not find any laches on the part of the O.P. Developers regarding the matter. We are thus unable to accept the contention of the Complainant.”
According to us, the learned District Forum did not commit any error while passing the impugned judgment and rightly held that the complainant has failed to establish his case before the learned District Forum and there was no deficiency in service on the part of the opposite parties Developers which would be evident from the aforesaid findings of the learned District Forum. Thus, no interference is called for.
In the result, the appeal is dismissed being devoid of merit. No order as to costs.
Send down the records to the learned District Forum, West Tripura, Agartala.
MEMBER State Commission Tripura |
| PRESIDENT State Commission Tripura |
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.