Delhi

South Delhi

CC/698/2009

NARENDER KUMAR PARTI - Complainant(s)

Versus

BSES RAJDHANI POWER LTD - Opp.Party(s)

18 Aug 2022

ORDER

DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION-II UDYOG SADAN C 22 23
QUTUB INSTITUTIONNAL AREA BEHIND QUTUB HOTEL NEW DELHI 110016
 
Complaint Case No. CC/698/2009
( Date of Filing : 14 Sep 2009 )
 
1. NARENDER KUMAR PARTI
B-1/38 FF & SF B BLOCK BETWEEN G BLOCK HAUZ KHAS NEAR CITI BANK ATM NEW DELHI 110016
...........Complainant(s)
Versus
1. BSES RAJDHANI POWER LTD
BSES BIDG ROOM NO. 206-207 ADHCHINI NEAR IIT GATE NEW DELHI 110029
............Opp.Party(s)
 
BEFORE: 
  MONIKA A. SRIVASTAVA PRESIDENT
  KIRAN KAUSHAL MEMBER
 
PRESENT:
 
Dated : 18 Aug 2022
Final Order / Judgement

DISTRICT CONSUMER DISPUTES REDRESSAL FORUM-II

Udyog Sadan, C-22 & 23, Qutub Institutional Area

(Behind Qutub Hotel), New Delhi- 110016

Case No.698/09

 

 

Shri Narender Kumar Parti

S/o Shri Yashwant Rai Parti

R/o B-1/38, (FF & SF)

B- Block between G Block

Hauz Khas

Near Citi Bank ATM

New Delhi-110016.                                                         ….Complainant

Versus

BSES Rajdhani Power Limited

Through its Business Manager –

Commercial Officer

BSES Bldg, Room No.206-207

Adhchini, Near IIT Gate

New Delhi-110029

 

ALSO AT:

Legal Department

BSES Rajdhani Power Limited

Andrews Ganj

New Delhi.                                                              ….Opposite Party

 

Date of Institution    :          14.09.2009                        

                           Date of Order        :          18.08.2022

 

 

Coram:

Ms. Monika A Srivastava, President

Ms. Kiran Kaushal, Member

ORDER

 

Member: Ms. Monika A. Srivastava

 

The present complaint has been filed for restraining the OP from adopting unfair trade practice, restraining demand raised by the OP for Rs.2,69,144/-.  It is further prayed to restrain the OP from disconnecting the electric supply to the complainant CR No.2550042972 and connection No.2550096343 in the premises of the complainant and compensation of Rs. 1 Lakh and costs.

It is the case of the complainant that the father of the complainant entered into collaboration agreement with the builder for constructing their property and in terms of the said agreement the first and second floor of the property came to the share of the father of the complainant and the remaining portion was taken over by the builder.  After the construction was completed separate electricity connections were required for each floor applications for the same were made to Delhi Vidyut Board (DVB).  The DVB prepared final payable bill by 23.04.2002 demanding a sum or Rs.8590/- and it was stated that before sanction of new electricity connections, the entire outstanding bills pertaining to the said property were required to paid.  Thereafter, the DVB after receiving the entire outstanding sanction four electricity connections and asked to make security deposits, connection charges etc.

After payment of the entire outstanding dues, the then Delhi Vidyut Board sanctioned four electricity connection and asked to make payment of security deposit, connection charges etc. and the same were paid by four different receipts as per details given below:

Receipt No.         

22664        Dated 09.05.2002                 Rs.7,795/-

                   22665        Dated 09.05.2002                 Rs.21,485/-

                   22666        Dated  09.05.2002                Rs.9,375/-

                   22667        Dated  09.05.2002                Rs.21,485/-

It is the case of the complainant that after passing of seven years complainant got a notice dated 24.07.2009 wherein it was stated that an amount of Rs.2,69,144/- is outstanding against the above referred temporary K. No. 2551L 3510414 and it was stated that though permanent domestic connections were provided to them, the temporary bill has still not been cleared. Therefore the outstanding amount would be transferred to their present connection K. No. 25510B081764 without any further notice.  The letter is annexed with the complaint as Annexure C-9.

It is stated by the complainant that as per policy of the OP, new connection is sanctioned only when the entire outstanding is paid which in this case stood paid on 17.02.2002.  It is also stated that OP cannot raise a demand after a period of seven years from the date of sanctioning of electricity connection and their demand is barred by time. It is further stated that this demand of Rs.2,69,144/- is arbitrary, illegal, unjustified and in addition, the threat was given to the complainant to comply with the demand failing which their electricity connection would be disconnected.

In their reply, the OP states that it came to their notice that the complainant had a temporary connection vide K No. 2551L3510414 and the consumer had not paid the bill.  It is also stated that there was no threat given by them to the complainant and the OP was ready to settle the case.  This reply has been filed by the BSES Rajdhani which came into existence after DVB being taken over by Govt of NCT of Delhi in collaboration with BSES Rajdhani. 

Evidence of both the parties as well as written arguments are on record. 

It is seen from the records that an evasive reply has been filed by the OP wherein they have not given any reason for raising a demand of Rs.2,69,144/- after a period of seven years.  However, in their written arguments they have reproduced Section 44 of Delhi Electricity Supply Code which does not pertain to the disputed subject.  The said section pertains to a complaint being entertained by OP and their response time.

In an application filed by the complainant, the complainant has placed on record order No.16/19 May 2008 passed by the Govt. of NCT of Delhi which is applicable to the said case. It is reproduced here:

  1. Direct the discoms to write off the principal dues against sale of power during DESU/DVB period in respect of the private electricity consumers and to waive off their late payment surcharge as well pertaining to that period only, except the cases under litigation at any forum at any level.
  2. ……..
  3. ……..

 

After perusing the record it is evident that the OP has no locus to raise the illegal demand of Rs. 2,69,144 in view of the order passed by the Govt. of NCT of Delhi dated 16/19 May  2008.  This demand could not have been raised and the OP is therefore found guilty of indulging in unfair trade practice by raising a demand which is not legally permitted.  The complaint is allowed and the OP is directed to pay a sum of Rs.50,000/- to the complainant for causing mental harassment to the complainant.  This amount shall be paid by the OP to the complainant within a period of three months from the date of this order failing which the amount shall be paid with interest @ of 5 % per annum till the date the said amount is paid.

File be consigned to the record room after giving copy of the order to the parties, on their application. Order be uploaded on the website.

                                                     

 

 
 
[ MONIKA A. SRIVASTAVA]
PRESIDENT
 
 
[ KIRAN KAUSHAL]
MEMBER
 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.