Tummalapalli Subhadradevi filed a consumer case on 10 Jun 2015 against Bhagavatula Sankara Rao in the Visakhapatnam-II Consumer Court. The case no is CC/466/2011 and the judgment uploaded on 14 Jul 2015.
Reg. of the Complaint:28-11-2012 Date of Order:10-06-2015
BEFORE THE DISTRICT CONSUMERS FORUM-II
AT VISAKHAPATNAM
Present:
1.Sri H.ANANDHA RAO, M.A., L.L.B.,
President
2.Sri C.V.RAO, M.A., B.L.,
Male Member
3.Smt.K.SAROJA, M.A., B.L.,
Lady Member
WEDNESDAY, THE 10TH DAY OF JUNE, 2015
CONSUMER CASE NO.466/2011
BETWEEN:
Tummalapalli Subhadradevi, W/o late Chalapathi Rao,
Hindu, aged 76 years, R/at D.No.53-22-27,
Chaitanya Nagar, Maddilapalem, Visakhapatnam.
…Complainant
AND:
Hindu, aged 35 years, Partners M/s Shivam Constructions,
R/a H.No.53-23-32/39, Chaitanyanagar,
Maddilapalem, Visakhapatnam.
Hindu, aged 49 years, r/o H.No.53-23-32/39,
Chaitanyanagar, Maddilapalem, Visakhapatnam.
…Opposite Parties
This case coming on 29-05-2015 for final hearing before us in the presence of SMT.Y.R.S.PRAKASA RAO, Advocate for the Complainant, and of SRI K.V.RAMA MURTHY, Advocate for the Opposite Parties, and having stood over till this date for consideration, this Forum made the following.
ORDER
(As per the Honourable President on behalf of the Bench)
11. The allegations that they have not provided even minimum amenities like water, power, main gate, lift etc., is incorrect. All facilities were provided and the complainant is not the sole purchaser of the entire apartment flats. They have not deviated the approved plan and the entire parking was divided into 12 parking areas each contains 80sft and 3 car parking areas were registered in the name of the complainant by way of construction agreement. For these reasons, the complaint filed by the complainant is liable to be dismissed.
12. To prove the case on behalf of the complainant, Exhibits A1 to A11 are suomoto marked. On behalf of the OPs, they filed their Evidence affidavit and got marked Exhibits B1 to B19.
13. Exhibit A1 is the Development Agreement, dated 01-02-2007, Exhibit A2 is the Development Agreement, dated 07-05-2008, Exhibit A3 is the Revised Agreement, dated 04-10-2008, Exhibit A4 is the GPA with sale agreement, dated 06-10-2009, Exhibit A5 is the Construction Agreement, dated 06-10-2009, Exhibit A6 is the Construction Agreement dated 06-10-2009, Exhibit A7 is the Construction agreement, dated 06-10-2009, Exhibit A8 is the indemnity bond, dated 06-10-2009, Exhibit A9 is the Registered Lawyer notice, dated 12-08-2011, Exhibit A10 is the Postal Receipts, Exhibit A11 is the Acknowledgement of OP2.
14. Exhibit B1 is the Unregistered Development Agreement, dated 1-2-2007, Exhibit B2 is the Unregistered Development Agreement, dated 07-05-2008, Exhibit B3 is the Revised Agreement dated 04-10-2008, Exhibit B4 is the Indemnity Bond, dated 06-10-2009, Exhibit B5 is the Approve building plan, dated 29-01-2007, Exhibit B6 is the Cash Receipt, dated 18-11-2008, Exhibit B7 is the letter addressed by the 1st OP to the complainant, dated 10-06-2009, Exhibit B8 is the Letter addressed to 1st P by Sri B.N.Prasad. dated 12-03-2009, Exhibit B9 is the Cheque of Rs.3,00,000/-, Exhibit B10 is the News Clipping of Eeenadu News Paper, dated 15-09-2007, Exhibit B11 is the letter addressed by the 1st OP to Sri B.N.Prasad, dated 26-11-2007, Exhibit B12 is the Notice and summons of Pr.Junior Civil Judge Court, Visakhapatnam, Exhibit b13 is the Letter of settlement, dated 03-06-2008, Exhibit B14 is the Letter of complaint of construction, Exhibit b15 is the structural stability certificate, Exhibit B16 is the Photographs in 3 nos. Exhibit B17 is the receipt of Rs.2,25,000/- issued by P.Venakta Rao, dated 10-06-2008, Exhibit B18 Construction agreements in 3 nos. dated 06-10-2009. Exhibit B19 is the Photograph 21 nos. showing the completion of apartment.
15. OPs filed their written arguments.
16. Heard oral arguments of OPs.
17. Now the point for determination to be determined in this case is;
Whether there is any deficiency of service on the part of the OPs and the Complainant is entitled to any reliefs asked for?
18. To prove the case of the complainant inspite of filing Exhibit A1 to A11, he has not filed his evidence affidavit, for the reasons best known to him in spite of sufficient opportunities are given. However in order to come to a just conclusion to decide the case on merits, it is relevant for us to discuss the documents relied upon by the complainant. Exhibits A1 & A2 are the Development Agreements dated 01-02-2007 and 07-05-2008, Exhibit A3 is the Revised Agreement dated 04-10-2008, Exhibit A4 is the agreement to sell with GPA dated 06-10-2009, Exhibit A5 and A6 is the construction agreement between the builder and the owner dated 06-10-2009, Exhibit A7 is the Construction agreement dated 06-10-2009, Exhibit A8 is the indemnity bond dated 06-10-2009, Exhibit A9 is the Registered Lawyer’s notice. It appears as seen from the counter averments and the affidavit filed by the OP, they have not disputed any of the Exhibit A1 to A8, therefore, much discussion not necessary in respect of these documents.
19. The 1st contention of the complainant is that as per Exhibit A1 Development Agreement, the OP has to complete the construction of the building within 18 months from 01-02-2007 but he failed, therefore, she is entitled for demurrages, loss etc., As seen from the record, it is evident in the starting of the project, 1st OP has taken only Subhadra Devi’s land with the mutual concern, the rest of sites 50sq.yds from Ramu and 100sq.yds from Uma Sundari has taken for convenient of both complainant and the OP. Apart from this Pothina Sanjeeva Rao filed a suit against OP and got injunction to stop the work. After settlement she has agreed to construct the entire building including 42 sq.yds of GPA of Pandia Appa Rao and therefore, it can be held this is one of the reason for delay of the construction. The record further shows again fresh permission and plan approvals have to be obtained in view of changing pattern of the Government in respect of the constructions rules. The record also shows at that time, in the foundation stage in the site in south side, there is a single sheet hard stone was hurdle for 8 column pits and the OP used Hydraulic compressor to remove the hard stone which took only about 5 months time on this work.
20. The affidavit averments of OP further go to show that they applied for new plan on 5-11-2007 and waited for nearly one month and after removing stones from the site, the work contract was given to P.Venkata Rao, Stone Works Contractor which is evident as seen from Exhibit B15. The affidavit averments also shows the GVMC, committee approved the plan and sent it to Assistant City Planner and the OP agreed and constructed the column upto slab level vide Exhibit B14, Exhibit B11 clearly go to show MOU was executed in between the complainant, first OP and another site owner Smt.Uma Sundari. After considering of both, the GVMC Authorities issued Revised Plan for total extent of 420 sq.yds which is applied on 28-06-2008 and the plan was approved by the authorities on 22-10-2008 and thereafter within 7 months, the 1st OP completed the total construction inside walls, pipelines, plastering and the remaining flats were completed on 1-3-2010 and handed over to the complainant. On a careful consideration of evidence affidavit of OP coupled with the aforesaid documents, it can be held that within 16 months, the 1st OP has completed the entire building work from the date of plan approval of revised plan. On scrutiny of all these facts and circumstances, it can be held that the OP has constructed the building within the time agreed.
21. The evidence of OP goes to show that the entire Electrical Material used in the building belongs to ISI Standard Material, Eminent Structural Engineer K.Kama Raju, has certified the stability of the building and issued both the Structural Stability Certificate Exhibit B15 and Completion Certificate vide Exhibit B14. Further as a 3rd party certification, an Eminent Structural Engineer MG Ravi Kanth also certified the building structure and issued a certificate vide Exhibit B13. His evidence affidavit also goes to show that the OPs has digged 3 borewells with 6.5 dia and also obtained 2 inch bulk water connection from GVMC and they have also erected 3 separate Electrical Meters, HT line was also erected and after getting 3 phase connection, the Lift was also installed and presently, it is in working condition vide Exhibit B17 and the entire parking was divided into 12 parking areas, each contains 80sft vide Exhibit B16. Thus, on a careful perusal reading of the evidence of the OP coupled with documents relied upon by them, it is held that there are no latches on the part of the OP. On the other hand, to prove the latches pointed out by the complainant he has not come forward with either his oral evidence or by way of expert evidence. For all these reasons, the complaint is liable to be dismissed.
22. In the result, this complaint is dismissed. No costs.
Dictated to the Stenographer, transcribed by him, corrected and pronounced by us in the open Forum, on this the 10th day of June, 2015.
Sd/- Sd/- Sd/-
LADY MEMBER MALE MEMBER PRESIDENT
APPENDIX OF EVIDENCE
Exhibits | Date | Description | Remarks |
A1 | 01-02-2007 | Development agreement | Photocopy |
A2 | 07-05-2008 | Development agreement | Photocopy |
A3 | 04-10-2008 | Revised agreement | Photocopy |
A4 | 06-10-2009 | GPA with sale agreement | Photocopy |
A5 | 06-10-2009 | Construction agreement | Photocopy |
A6 | 06-10-2009 | Construction agreement | Photocopy |
A7 | 06-10-2009 | Construction agreement | Photocopy |
A8 | 06-10-2009 | Indemnity Bond | Photocopy |
A9 | 12-08-2011 | Legal notice | Office copy |
A10 | 12-08-2011 | Posta Receipts | Originals |
A11 | 16-08-2011 | Acknowledgements of OP2 | Originals |
Exhibits | Date | Description | Remarks |
B1 | 01-02-2007 | Unregistered Development Agreement | Photocopy |
B2 | 07-05-2008 | Unregistered Development Agreement | Photocopy |
B3 | 04-10-2008 | Revised Agreement | Photocopy |
B4 | 06-10-2009 | Indemnity Bond | Photocopy |
B5 | 29-01-2007 | Approved Builidng Plan vide B.A.No.10244/2007 | Photocopy |
B6 | 18-11-2008 | Cash receipts | Original |
B7 | 10-06-2009 | Letter addressed by the 1st OP | Office copy |
B8 | 12-03-2009 | Letter addressed to 1st OP | Original |
B9 |
| Cheque of Rs.3,00,000/- drawn in favour of the complainant | Photocopy |
B10 | 15-09-2007 | News clipping of Eeanadu | Photostat copy |
B11 | 26-11-2007 | Letter addressed by the 1st OP | Office copy |
B12 |
| Suit Notice and summons of the Pr.Civil Judge Court, Visakhapatnam | Served coy |
B13 | 03-06-2008
| Letter of settlement | Original |
B14 |
| Letter of Completion of Construction | Office copy |
B15 |
| Structural Stability Certificate | Office copy |
B16 |
| 3 Nos. Photographs | Original |
B17 | 10-06-2008 | Receipt | Original |
B18 | 06-10-2009 | Construction agreement in 3 Nos. | Photocopy |
B19 |
| Photographs-21 nos. | Original |
Sd/- Sd/- Sd/-
LADY MEMBER MALE MEMBER PRESIDENT
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.