A. P. STATE CONSUMER DISPUTES REDRESSAL COMMISSION : AT HYDERABAD
FA 655 of 2012 against CC 31/2011 on the file of the District Consumer Forum II, Chittoor District at Tirupati.
Between :
1. The Chairman-cum-Managing Director
APSPDCL Kesevayanagunta
Tirupati.
2. The Superintendent Engineer ( Operation )
A. P. southern Power Distribution Company Ltd
Tirupati
3. The Divisional Engineer,
A.P. southern Power Distribution Company Ltd
Vijayapuram Post and Mandal
Chittoor Distrit.
4. The Asst. Divisional Engineer ( Operation )
APSPDCL, Vijayapuram Post and Mandal
Chittoor District.
5. The Assistant Engineer ( Operation )\
APSPDCL, Pannur
Vijayapuram Mandal, Chittoor District . Appellants/opp.parties
And
B. Balaji @ Balaji Naidu
s/o Ranganatha naidu
Resident of Gangamabapuram Village
Vijayapuram mandal
Chittoor District .. Respondent/complainant
Counsel for the Appellants : M/s. P. Vinod Kumar
Counsel for the Respondent : M/s. B.Siva Shanker Rao
Coram ;
Sri R. Lakshminarasimha Rao… Hon’ble Member
And
Sri T. Ashok Kumar .. Hon’ble Member
Tuesday, the Thirteenth Day of August
Two Thousand Thirteen
Oral Order : ( As per Sri T. Ashok Kumar , Hon’ble Member )
****
1. This is an appeal preferred by the opposite parties as against the orders dated 15.02.2012 in CC 31/2011 on the file of the District Consumer Forum II, Chittoor District at Tirupati . For convenience sake, the parties as arrayed in the complaint are referred to as under :
2. The brief facts of the complaint are that the complainant is the owner of Ac.4.04 cents of land at Nindra Mandal and he raised sugarcane crop by spending Rs.40,000/- for agricultural operations in the said land during relevant period. In spite of his objection, the opposite parties have installed a transformer of 220 KW in the fields of the complainant for distributing power to the surrounding ryots for running their agricultural pump sets. The sugarcane crop raised by the complainant was fully grown up and fit for harvesting. While the things thus stood, on 10.09.2010 there was sudden high voltage of 450 KW and as the supply being beyond the capacity of the transformer, there were flames/sparks from the transfer and the said flames/sparks fell on the sugarcane crop of the complainant and it resulted in damage to the entire crop on account of such fire accident. Immediately the fire department was informed about the fire accident but by the time they come and attended the entire sugarcane crop was subjected to fire and the complainant sustained loss of sugarcane in his fields weighing about 5oto 53 MTs and the then cost of the sugar cane per ton was Rs.200 to Rs.210 per M.T. and thus the complainant sustained Rs.6 lakhs and hence the complaint to direct the opposite parties to pay the said compensation, litigation costs of Rs.5000/- and also interest and compensation.
3. .OPs filed counter opposing the claim of the complainant and denying the allegations made in the complaint and the brief facts of the counter are as under : There was no such high voltage as contended by the complainant and that the transformer erected In the fields of the complainant is 25 KVA capacity but not 220 KVA. There was no such incident of heavy supply of 450 KVA to the transformer and in the existing system it was not possible. After the fire accident the fields of the complainant was inspected and found that the existing transformer and connected lines in the fields of the complainant are in good condition and there is no chance of short circuit at the transformer. The Fire accident in the sugarcane fields of the complainant may be due to various reasons like leaving burnt cigars, match stick, used by the people working in the nearest fields. There i s no gross negligence on the part of the opposite parties and the complainant did not sustain any loss and the question of payment of Rs. Six lakhs does not arise and thus prayed to dismiss the complaint with costs.
4. Both sides filed evidence affidavit reiterating their respective pleadings and Ex. A-1 to A15 were marked on behalf of the complainant and Ex. B -1 andB2 were marked for the OPs.
5. Having heard both sides and considering the evidence on record, the District Forum allowed the complaint in part vide impugned orders and directed OPs to pay a sum of Rs,4,04,000/- at 9% interest from 10.09.2010 till realization so also costs of Rs.5,000/-.
6. Feeling aggrieved with the said order the unsuccessful OPs filed this appeal on several grounds and mainly contended that the OPs have installed transformer with a capacity of 25 KA and not 220 KVA and there was no high voltage of 450 KVA on that date and at any other time and hence the question of loss on account of the alleged incident cannot be believed and that there was no possibility in the existing distribution to supply 450KVA to the transformer and that supply to the former transfer from the substation was only 11 KV and that the OP further enquired into the matter and unearthed the truth by obtaining a letter from the sugar factory wherein the complainant had sold 181.38 of sugarcane crop and got Rs.3,26,436/- for the year 2010-2011 and the said aspect clearly infers that the complainant had filed the complaint only to get illegal gains and that the accident was not due to short circuit but due to some other reasons and thus prayed to allow other appeal and set aside the impugned order.
7. IA 1297/2012 filed by the OP was allowed on 7.3.2013 to receive a letter issued by Prudential Sugar Corporation Limited, Prudential nagar, Uppedu to the effect that the complainant supplied sugarcane to it and realized Rs.3,26,436 as additional evidence and it is marked as Ex. B3.
8. Heard both sides with reference to their respective contentions in detail.
9. Now the point for consideration is whether the order of the District
Forum is sustainable ?
10. There is no dispute that the complainant is owning Ac.4.04 cents of land at Nindra Mandal in various survey numbers and during relevant time he raised sugarcane crop in it and also that a transformer was installed in the land of the complainant. However, the complainant contended that the said transformer was of 220 KV whereas the Ops contended that it was only 25 KVA and that question of high voltage of 450 KV passing through the transformer does not arise. The OPs did not file and prove any record in the said context in support of its contentions. The self-serving evidence of the ADE is not helpful for it. It is much more so, when he admitted in the cross examination that in Ex B2 reply notice there was no mention of the fact that there is no record to show the flow of high voltage was found to be released, as stated by him in chief examination. According to the Ops on receiving the complaint regarding fire accident the fields of the complainant was inspected and found that the existing transformer and connected lines in the fields of the complainant were in good condition and there was no chance of short circuit at the transformer. No report of the said inspecting authority has been filed and proved. Therefore the said plea could not be appreciated in their favour. In such circumstances, an inference is drawn that on account of high voltage whatever may be the KV capacity of the transformer there were sparks from the transformer and the said sparks fell on the sugarcane crop of the complainant and that said crop was subjected to fire. ExA1 to A7 documents also support the contention of the complainant that the sugarcane crop in his filed was subjected to fire on account of the said fire accident In such circumstances, the hypothetical contention of the opposite parties that it may be due to left over cigars and matchstick also could not be appreciated. Possibility of the complainant setting fire has been ruled out by the Forum assigning the reasons. At what height the transformer was erected has not been placed on record and therefore the contention that it was erected at about 10 to 15 feet and therefore question of sparks falling on the sugarcane from such a height was not possible could not be appreciated. The opposite party did not take any steps to fence the area in and around the transformer to prevent accident fire being spread to the sugar cane crop. They even did not educate the agircultu8rsts in the said context to prevent him loss. The said lapses on the part of Ops amount to negligence and deficiency in service.
11. In a decision reported in 2002 (2) ALD 4 (SC) between M.P. Electricity Board Vs. Shail Kumar the Hon’ble Supreme Court observed that :
“Even assuming that all such measures have been adopted, a person undertaking an activity involving hazardous or risk exposure to human life, is liable under law of torts to compensate for the injury suffered by any other person, irrespective of any negligence or carelessness on the part of the managers of such undertakings. The basis of such liability is the foreseeable risk inherent in the very nature of such activity. The liability case on such person is known, in law, as “strict liability”.
It differs from the liability which arises on account of the negligence or fault in this way i.e., the concept of negligence comprehends that the foreseeable hard could be avoided by taking reasonable precautions. If the defendant did all that which could be done for avoiding the harm he cannot be held liable when the action is based on any negligence attributed. But such consideration is not relevant in cases of strict liability where the defendant is held liable irrespective of whether he could have avoided the particular harm by taking precautions.”
On analogy the said decision is helpful for the complainant to sustain his claim for loss of sugarcane in his filed on account of negligence of Ops.
In view of the said decision of the Hon’ble Apex court, the OP department is certainly liable to compensate the complainant in connection with the fire accident to his fields because the Ops did not vigilant over the such supply of high voltage and its consequences nor prevented the same by taking recourse. In similar case, this Commission in FA No. 1003/2009 vide its orders dt. 30.08.2011 awarded compensation to the complainant therein. Regarding the quantum, the District Forum made exercise with reference to various documents ie Ex. A3, A12 and basing on the said documents and also the contention of the complainant that the expected yield was around 45 to 50 tons calculated the damage at Rs.4,44,400/- for 50 tons in Ac. 4.04 cents and Rs. .3,63,600/- for 45 tons at the rate of Rs.2000/- per ton in Ac.4.04 cents and arrived at Rs.4,04,000/- average damage and awarded the same and Rs.40,000/- claimed towards agricultural expenses were disallowed.
12. As already described supra Opposite party in this appeal, filed IA 1297/2012 which was allowed on 7.3.2013 and Ex.B3 letter issued by Prudential Sugar Corporation Limited, Prudential nagar, Uppedu was received as additional evidence wherein it is mentioned that the complainant supplied sugarcane to it and realized Rs.3,26,436/- It was so allowed as counsel for the respondent complainant reported ‘no objection’. It is not the case of the complainant that the said sugar cane crop was from other fields than that of the fields claimed by him.
13. In the said Ex. B3 document survey nos.125/1 and 126/10 are described as the lands of the complainant measuring Ac.3.17 cents from which the supplied sugarcane was raised. Admittedly as seen from Ex. A5 certificate, the said two survey numbers are also the lands of the complainants in which he raised sugarcane crop. In the second line from the top of the said Ex. B3 document it is mentioned that it was grower wise supply for the season 2011-12 and in the body of the letter dates of supply are shown from 29.11.2010 to 27.2.2011. In such circumstances, whether the sugarcane covered by the said document pertaining to the relevant season of fire accident or not has to be decided, so also whether the amount covered by the said document has to be deducted from and out of the amount payable to the complainant or not. Admittedly the complainant did not say that the said document is irrelevant and unconcerned still in the larger interest of justice additional evidence from both sides is required for effective adjudication of the said aspect and the material on record is not sufficient to decide the said aspect. Therefore we are of the opinion that this is a fit case to set aside the impugned order and remit back the case for fresh disposal. However, the amount deposited by the respondents shall remain in the Account as it is till disposal of the case afresh by the Forum.
14. In the result, the appeal is disposed of setting aside the order of the District Forum and the case is remitted back to the District Forum for fresh disposal according to law after giving opportunity to both sides with reference to the document received as additional evidence. Parties shall bear their own costs of the appeal.
MEMBER
MEMBER
DATED : 13.08.2013.