KERALA STATE CONSUMER DISPUTES REDRESSAL COMMISSION
VAZHUTHACAUD THIRUVANANTHAPURAM
APPEAL NO.606/11
JUDGMENT DATED 12.3.2012
PRESENT
JUSTICE SHRI.K.R.UDAYABHANU -- PRESIDENT
West Fort Academy for Higher
Education, A unit of West Fort
Higher Education Trust
Reptd. by Managing Trustee -- APPELLANT
K.M.Mohandas, Pattore
M.G.Kavu P.O, Thrissur.
(By Adv.Manish)
Vs.
1. Asst.Engineer,
Electrical Section, KSEB
Mulamkunnathukavu. -- RESPONDENTS
2. KSEB, reptd. by Secretary,
Thiruvananthapuram.
(By Adv.B.Sakthidharan Nair)
JUDGMENT
JUSTICE SHRI.K.R.UDAYABHANU,PRESIDENT
The appellant is the complainant in OP.583/04 in the file of CDRF, Thrissur. The complaint stands dismissed.
2. The complainant has disputed the bills issued by the opposite parties dated 24.4.04 for Rs.73,122/- and the bill dated 29.4.04 for Rs.21054/-. According to the complainant, the bills issued are illegal and it is not evident from the bills as to on what basis the bills has been issued. He has sought for setting aside the said bills.
3. The opposite parties have filed version pointing out that the connection was taken for construction purpose under VII A tariff. On 16.4.04, an investigation was conducted and it was found that one of the phases of 3 phase meter from which the power is taken by the complainant was not working. The site mahazer was prepared by board officials and the matter was brought to the attention of Sri.Mohandas, Electrical Engineer of the complainant Institution who has signed in the mahazer. The three phase energy meter was replaced. The initial reading of new meter was 10 and the final reading of faulty meter was 16299. The reading of the old meter was 11692 and the reading of the old meter in February to 16.4.04 was 11692 and that reading in the new meter on 24.4.04 was 1064. The difference in reading in the old meter during February to 24.4.04 was 4607 units which is the consumption of 2 phases as the third phase was not recording energy. Hence the consumption for the period would work out to 4607 x 1.5 ie; 6911. The consumption from 16.4.04 to 24.4.04 was 1064 – 10 ie; 1054 units. Hence the total consumption for 2 months comes to 6911 + 1054 which would be 7965 units. It is for the same the bill is issued for Rs.73122/-. In the previous 4 months ie; 10/03 to 2/04, 4639 units were recorded in the meter and 2320 units were left unrecorded. It is for the same bill for Rs.21,054/- has been issued. No penalty has been imposed.
4. The evidence adduced consisted of the testimony of PW1, Exts. P1 to P4 and R1 to R3.
5. We find that the site mahazer has been produced along with the version. But the same has been omitted to be marked by the opposite party. It is seen that one Mohandas as has been mentioned in the version has signed in the mahazer. The above Mohandas was not examined by the complainant. As per the above site mahazer it is noted that on inspection one phase of the meter was not working. Hence, the meter was replaced it is for the escaped energy that the bill has been issued. Ext.R1 contains the details as to how the amount has been arrived at with respect to Ext.P1 bill ie; Rs.73,122/- along with the units consumed. Half of the units consumed is added so as to incorporate the energy consumed through the missing phase. Ext.P2 bill is with respect to the escaped energy for the period from 10/2003 to 2/2004. For the above period regular charges has been paid and hence the same is only with respect to the escaped energy due to non recording of one phase.
6. It is the contention of the counsel for the appellant that it is Regulation 42 (3) of the Conditions of Supply 2005 that applies. As per the above provision in case of faulty meter average of 6 months after replacement of the meter is to be taken. It is pointed out by the counsel for the KSEB that the above regulations came in to effect subsequently. In the instant case, the dispute is not with respect to the faulty meter but regarding the non recording of one phase which is on account of some mistake in connecting the phase to the meter. It is pointed out that the opposite parties have just changed the meter as well as a matter of abundant caution. There is no case that the calculation has been done erroneously or that the reading shown is incorrect. The genuineness of the site mahazer has not been disputed. In the circumstances we find that no interference in the order of the Forum is called for. The appeal is dismissed.
The office will forward the LCR to the Forum along with the copy of this order.
JUSTICE K.R.UDAYABHANU : PRESIDENT