Perumal Apartments Resident filed a consumer case on 17 Oct 2017 against Anupam Foundation Ltd., in the South Chennai Consumer Court. The case no is CC/282/2006 and the judgment uploaded on 11 Dec 2017.
Date of Filing : 28.04.2006
Date of Order : 17.10.2017
DISTRICT CONSUMER DISPUTE REDRESSAL FORUM, CHENNAI (SOUTH)
2nd Floor, Frazer Bridge Road, V.O.C. Nagar, Park Town, Chennai-3
PRESENT: THIRU. M.MONY, B.Sc., L.L.B. M.L., : PRESIDENT
TMT. K.AMALA, M.A. L.L.B., : MEMBER I
DR. T.PAUL RAJASEKARAN, M.A ,D.Min.PGDHRDI, AIII,BCS : MEMBER II
C.C.NO.282/2006
TUESDAY THIS 17TH DAY OF OCTOBER 2017
Perumal Apartments Residents Welfare
Association, Rep. by its
Secretary V.Sivakumar,
Flat G-2, No.32, Mangadusamy Street,
Nungambakkam,
Chennai 600 034. .. Complainant
..Vs..
Anupam Foundations Limited,
Rep. by its Managing Director,
Shanthimull Nahar,
No.749, Anna Salai,
Chennai 600 002. .. Opposite party
Counsel for Complainant : M/s. C.S.K.Sathish
Counsel for opposite party : M/s. Ashok Menon & others
ORDER
THIRU. M. MONY, PRESIDENT
This complaint has been filed by the complainant against the opposite party under section 12 of the Consumer Protection Act 1986 seeking direction to rectify the deficiency in constructionand to pay a sum of Rs.2,00,000/- towards compensation for mental agony and to pay cost of the complaint.
The complainant submit that the complainant’s association entered into Development agreement on 12.12.2000 with the opposite party. As per the development agreement the opposite party obtained building permission on 12.3.2001. Thereafter the complainant association and the opposite party agreed to construct the ground floor and all the purchasers had agreed for the same. The complainant also state that the opposite party has not completed the building and handed over the building as per the terms of joint development agreement. Hence the complainant association appointed licensed surveyor for assessing the pending work and repair work involved in the building. The surveyor also visited the property and submitted his report. Accordingly the said surveyor by his report dated 29.3.2005 had quoted a sum of Rs.5,55,250/- would be required to make good the deficiency in construction. As such the act of the opposite party amounts to deficiency in service which caused mental agony and hardship to the complainant. Hence this complaint is filed.
2. The brief averments in Written Version of the opposite party is as follows:
This opposite party deny each and every allegations except those that are specifically admitted herein. The opposite party denies the averment that as per the construction agreement the opposite party had to paint the entire exterior walls of the flats, paint the grills of the stair case, make provisions for clearing rain water in all the sun shades, and had to attend the overhead tanks with regard to mark the pipelines connecting the individual flats, make good the leakages in the water tank, to fix water meter in the individual pipelines to enable the complainant association to fix water charges in the sense and spirit that the averment is made. The opposite party further denies that the complainant has availed the service of a licensed surveyor on 29.3.2005 to assess the work to be done and the expenses that were likely to be incurred in attending to them. This opposite party has not knowledged any inspection by any surveyor or any report filed and would most humbly like to submit that if indeed any surveyor had inspected, prior notice ought to have been given to the opposite party so that such inspection could have been done in the presence of this opposite party. This opposite party is unaware of any report of any surveyor dated 29.3.2005 and denies that a sum of Rs.5,55,250/- would be required to make good the deficiency in construction. Hence there is no deficiency in service on the part of the opposite party and the complaint is liable to be dismissed.
3. In order to prove the averments of the complaint, the complainant has filed proof affidavit as his evidence and documents Ex.A1 to Ex.A9 marked. Proof affidavit of opposite party filed and no documents marked on the side of the opposite party.
4. The points for the consideration is:
1. Whether the complainant is entitled to rectify the construction in alleged repairs as prayed for ?
2. Whether the complainant is entitled to pay compensation of Rs.2,00,000/- towards mental agony with cost as prayed for?
5. POINTS 1 & 2:
Both parties has not filed any written argument and not turned up to advance any oral argument for long time. Admittedly the complainant association entered into Development agreement Ex.A1 on 12.12.2000 with the opposite party. As per the development agreement the opposite party obtained building permission on 12.3.2001 also admitted. Thereafter the complainant association and the opposite party agreed to construct the ground floor and all the purchasers had agreed for the same and both parties aware of the consequences is not denied. The complainant pleaded in the complaint that the opposite party has not completed the building and handed over the building as per the terms of joint development agreement. Hence the complainant association appointed licensed surveyor for assessing the pending work and repair work involved in the building. The surveyor also visited the property and submitted his report which is marked as Ex.A2. As per Ex.A9 there is a pending work of Rs.5,55,250/-. But it is very unfortunate that neither the complainant association nor the licensed surveyor has not given any notice of such assessment related to pending work to the opposite party. The licensed surveyor had also not given the guidelines for such assessment. On a scrutiny of the report the surveyor prepared the report in consonance with the averment of deficiency in service alleged in the complaint without notice and guide lines. The complainant has not taken any steps to appoint Advocate commissioner to find out the actual deficiency in construction. The contention of the opposite party is that admittedly the complainant association and the opposite party agreed to construct additional 2nd and 3rd floor which leads several consequences related to approval and sharing of area spacing of excess amount etc. alleging deficiency in construction are imaginary. The opposite party constructed the building in such manner having no such deficiency. The allegation of pending leakages in water tank fixing of water meter and all other aspects has been duly attended by the opposite party, there is no deficiency of any kind exist. The report of the licensed surveyor is one sided. No notice of any information regarding the visit of the surveyor or assessment by the surveyor given to the opposite parties. Further the contention of the complainant is that due to the deficiency in construction; the complainant association are put to great mental agony and is claiming a sum of Rs.2,00,000/- towards compensation but no evidence.
6. The contention of the opposite party is that the allegation of mental agony is imaginary. All the defects have been rectified without any default. The alleged deficiency has not been proved by the complainant in a proper manner. Engaging a licensed surveyor of their whims and fancy and created a report shall not yield any purpose. Considering the facts and circumstances of the case this forum is of the considered view that the complainant is not entitled for any relief as prayed for in the complaint and the points 1 & 2 are answered accordingly.
In the result the complaint is dismissed. No cost.
Dictated by the President to the Assistant, taken down, transcribed and computerized by her, corrected by the President and pronounced by us in the open Forum on this the 17th day of October 2017.
MEMBER-I MEMBER-II PRESIDENT.
Complainant’s side documents:
Ex.A1- - - Copy of construction agreement.
Ex.A2- 4.7.2002 - Copy of implead application filed with CMDA.
Ex.A3- 1.10.2003 - Copy of Memorandum of Association of the complainant.
Ex.A4- 19.11.2003 - Copy of Certificate of Incorporation of complainant
Association.
Ex.A5- 10.6.2004 - Copy of payment made to TNEB.
Ex.A6- 11.6.2004 - Copy of payments made to TNEB.
Ex.A7- 6.9.2004 - Copy of letter to opposite party.
Ex.A8- 1.12.2004 - Copy of letter to opposite party.
Ex.A9- 29.3.2005 - Copy of work estimate and quotation given by Engineer.
Opposite party’s side document: - .. Nil..
MEMBER-I MEMBER-II PRESIDENT.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.