View 963 Cases Against Ansal Properties
View 3633 Cases Against Properties
Varinder Kumar filed a consumer case on 20 Feb 2018 against Ansal Properties & Infrastructure Ltd. in the StateCommission Consumer Court. The case no is CC/527/2017 and the judgment uploaded on 27 Feb 2018.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 527 of 2017 |
Date of Institution | : | 10.07.2017 |
Date of Decision | : | 20.02.2018 |
Both R/o H.No.36, Green Enclave, Village Daun, District S.A.S. Nagar (Mohali) (Pb.).
…… Complainants
Ansal Properties and Infrastructure Ltd., through its Chairman/Director, 1202-04, Antriksh Bhawan 22, Kasturba Gandhi Marg, New Delhi-110001
2nd Address:-
Ansal Properties and Infrastructure Ltd., through its Chairman/Director, Regional Office S.C.O. No.183-184, Sector 9-C, Madhya Marg, Chandigarh.
…..Opposite party
Argued by:- Sh.Gaurav Bhardwaj, Advocate, proxy for Sh.Paras Money Goyal, Advocate for the complainants.
Opposite party exparte.
====================================================
Complaint case No. | : | 556 of 2017 |
Date of Institution | : | 18.07.2017 |
Date of Decision | : | 20.02.2018 |
Brij Krishan Koul son of Late Shri Shambhoo Nath Koul, resident of B/4-503, NHPC Colony, Sector 41, Faridabad (Haryana).
…… Complainant
Ansal Properties and Infrastructure Ltd., 1202-1204, Antriksh Bhawan, 22, Kasturba Gandhi Marg, New Delhi-110001, through its MD.
2nd Address: -
Ansal Properties and Infrastructure Ltd., S.C.O. No.183, 184, Sector 9-C, Madhya Marg, Chandigarh, through its Sr. Executive (Sales and Marketing)/Branch Manager/Authorized Signatory.
…..Opposite party
Argued by:- Sh.Subhash Chand, Advocate for the complainant.
Opposite party exparte.
====================================================
Complaints under Section 17 of the Consumer Protection Act, 1986
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
MR. DEV RAJ, MEMBER.
MRS. PADMA PANDEY, MEMBER.
PER JUSTICE JASBIR SINGH (RETD.), PRESIDENT
By this order, we propose to dispose of the aforesaid two consumer complaints. Arguments were heard in common, in the above cases, as the issues involved therein, except minor variations, here and there, of law and facts are the same. In both the complaints aforesaid, the complainants have sought refund of the amount deposited with the opposite parties, towards price of their respective units, alongwith interest, compensation etc. At the time of arguments, on 29.01.2018, it was agreed by Counsel for the complainant(s), that, in view of above, both the complaints can be disposed of, by passing a consolidated order.
Under above circumstances, to dictate order, facts are being taken from consumer complaint bearing no. 527 of 2017, titled as Varinder Kumar and another Vs. Ansal Properties and Infrastructure Limited. The complainants are husband and wife respectively. It is their case that they purchased a flat bearing no.637, first floor, measuring 1120 square feet, consisting of 3 bedrooms and 2 bathrooms, from the opposite party, in a project launched by them, under the name and style ‘Happy Homez”, Golf Links, Sector 114, Kharar-Landran Road, Mohali, Punjab (in short the unit). Allotment letter Annexure C-1, in respect of the said unit was issued on 15.08.2010. It was stated that to purchase the said flat, the complainants paid an amount of Rs.2,50,000/- vide cheque dated 31.08.2010 and Rs.1,10,000/- (twice) vide cheques dated 16.09.2010, totaling Rs.4,70,000/- receipts whereof have been placed on record as Annexures C-2 to C-4. It was specifically stated that, it was assured by the opposite party to the complainants that they had to make payment of an amount of Rs.4,70,000/-, under subvention scheme and rest of the sale consideration will be demanded, at the time of handing over possession of the unit, but, later on, they refused to do so, and compelled the complainants to start making payment towards price of the unit, under threat of cancellation of allotment and applicability of forfeiture clause. The opposite party made the complainants to take home loan from the HDFC Bank to the extent of Rs.17 lacs, vide Tripartite Agreement dated 04.02.2012, Annexure C-5. The said bank disbursed an amount of Rs.14,40,000/- to the opposite party on 08.02.2012. It is further case of the complainants that they have been making payment of EMIs to the said bank, to repay the amount of loan raised by them. It is further stated by the complainants that as per Clause 12 of the Allotment Letter, the opposite party, committed to hand over possession of the said unit, within a period of 24 to 30 months. The said Clause reads thus:-
“The Construction of the said Independent Floor is likely to be completed within 24 to 30 months of commencement of work, which shall be tentatively the date of receipt of all requisite sanctions/approvals/permissions/clearances subject however to force majeure circumstances, regular and timely payments by Allottee(s), availability of building material etc. change of policy by Government/Local Authorities etc. No claim by way of damages/compensation shall be raised against the Company in case of delay in handing over possession on account of the said reasons or any other reason beyond the control of the Company.”
Time of 30 months period to hand over possession of the unit, came to an end on 14.02.2013. It is averred by the complainants that when they failed to get possession of the unit, in time, and also thereafter, they saw that there were no chances to get possession in the near future also, they bought a residential house in a project named Green Enclave, Mohali, for which they had to raise loan of Rs.18 lacs, from Andhra Bank, on higher rate of interest. It was stated that on 10.08.2015, the complainants received a letter from the opposite party, asking them to make payment of outstanding amount totaling to Rs.19,10,000/-, in respect of the unit, in dispute. By stating that they had already paid the said amount, the complainants asked the opposite party to withdraw its notice, however, nothing was done. Faced with the situation, they asked the opposite party to refund the amount paid, alongwith interest, however failed to get any response. It is specifically averred that facilities/basic amenities as promised by the opposite party, are not available at the project site. It was stated that the opposite party has received an amount of Rs.19,10,000/-, and used the same for its own purposes, as such, it is bound to refund the same alongwith interest, compensation etc. Hence this complaint.
Not only in the instant case, earlier also, we have noticed that in some other cases also, there is an attempt of the opposite party to delay the proceedings and that at the spot construction is not complete. In a similar project (Golf Links-II) of the opposite party, in the same area, in the case of Prem Kumar Kanwar and another Vs. Ansal Properties and Infrastructure Ltd., consumer complaint bearing no.612 of 2017 decided on 19.02.2018, it was observed by this Commission as under:-
“It is not in dispute that the opposite party has failed to deliver possession of the unit, in question, within the stipulated period as provided in the Agreement or even till date, for want of construction at the site and also necessary approvals, from the Competent Authorities. The complainants have sought refund of the amount paid, alongwith interest, compensation etc. It is to be analyzed as to whether, in view of facts noted above; pleadings on record and arguments raised, it is open to the complainants, to claim above said relief or not.
It is not in dispute that the complainants purchased the unit, in question, for which Floor Buyer’s Agreement was signed between the parties on 16.12.2011. Constructed unit was sold in favour of the complainants, for an amount of Rs.39 lacs, excluding external development charges. As per condition no. 5.1 of the Agreement, it was incumbent upon the opposite party, to hand over possession within a period of 30 months, with extended period of 6 months i.e. total 36 months from the date of execution of the said Agreement i.e. on or before 15.12.2014. The date of offer of possession of the unit i.e. 15.12.2014 already stood expired. Now it is February 2018. More than three years have lapsed.
Contention of Counsel for the complainants that construction at the spot is virtually stopped, needs acceptance. By the date, when arguments were addressed before us, possession has not been offered to the complainants. At the time of arguments, Counsel for the opposite party failed to give any positive date/time, as to when, construction, will be completed and possession of the constructed unit will be given. In the written reply also, no commitment was made, as to by which time and date, possession of the unit will be delivered, after construction. It is well settled law that the onus to prove that the project has been completed and the area/site, in question, is fully developed, is on the builder/opposite party. It was so said by the National Commission, in Emaar MGF Land Limited and another Vs. Krishan Chander Chandna, First Appeal No.873 of 2013 decided on 29.09.2014. In the present case, it is very strange that not even a single document has been placed on record, by the opposite party, in respect of the unit, in question, to prove that the construction is complete and it is actually ready for offer and delivery of possession. In case, all the development activities had been undertaken and construction of the flats is complete at the project site, then it was for the opposite party, which could be said to be in possession of the best evidence, to produce cogent and convincing documentary evidence, in the shape of the reports and affidavits of the Engineers/Architects, as they could be said to be the best persons, to testify, as to whether, all these development and construction activities, had been undertaken and completed at the site or not, but it failed to do so. At the same time, the opposite party was also required to produce on record, a copy of the occupation and partial/final Completion Certificates (if obtained), having been issued by the Competent Authorities, which could be said to be best evidence, to prove its case, but it miserably failed to do that also.
At the time of arguments, a very strange objection was raised by Counsel for the opposite party that construction of the units could not be completed, due to force majeure circumstances, faced by the opposite party i.e. non-approval of the project building plans, by the Officers of the Govt. Department concerned. It was stated that frivolous objections were raised by the Department, without any reasons. We have perused the reply filed. There is nothing on record, to show that any such alleged objections were ever raised by the Govt. Department, in respect of the project in question. Furthermore, no details in the reply have been given by the opposite party, as to at what stage and when, the alleged frivolous objections were raised by the Department, before granting approvals of the building plans etc. in respect of the project, in question. Such a plea taken by the opposite party, without any basis, needs rejection and is accordingly rejected.
Under above circumstances, it can be said that there is a material violation on the part of the opposite party, in not offering and delivering possession of the unit, in question, to the complainants, by the promised dated i.e. 15.12.2014 or even as on today, thereby leading material violation on its part, apart from deficiency in providing service and guilty of adoption of unfair trade practice. It is settled law that when there is a material violation on the part of the builder, in not handing over possession by the stipulated date, the purchaser is not bound to accept the offer, even if the same is made at a belated stage and on the other hand, can seek refund of amount paid. It was so said by the Hon’ble National Commission, in a case titled as Aashish Oberai Vs. Emaar MGF Land Limited, Consumer Case No. 70 of 2015, decided on 14 Sep 2016, wherein, under similar circumstances, while negating the plea taken by the builder, it was held as under:-
“I am in agreement with the learned senior counsel for the complainants that considering the default on the part of opposite parties no.1 and 2 in performing its contractual obligation, the complainants cannot be compelled to accept the offer of possession at this belated stage and therefore, is entitled to refund the entire amount paid by him along with reasonable compensation, in the form of interest.”
Not only as above, in a case titled as Brig Ajay Raina (Retd.) and another Vs. M/s Unitech Limited, Consumer Complaint No.59 of 2016, decided on 24.05.2016, wherein possession was offered after a long delay, this Commission, while relying upon the judgments rendered by the Hon’ble National Commission, ordered refund to the complainants, while holding as under:-
“Further, even if, it is assumed for the sake of arguments, that offer of possession, was made to the complainants, in July 2015 i.e. after a delay of about three years, from the stipulated date, even then, it is not obligatory upon the complainants to accept the same.
Furthermore, in another case titled as M/s. Emaar MGF Land Ltd. & Anr. Vs. Dr.Manuj Chhabra, First Appeal No.1028 of 2015, decided on 19.04.2016, the Hon’ble National Commission, under similar circumstances, held as under:-
“I am of the prima facie view that even if the said offer was genuine, yet, the complainants was not obliged to accept such an offer, made after a lapse of more than two years of committed date of delivery”.
However, in the present case, as stated above, the position is worst. It is not the case of the opposite party that construction could not be completed on account of some force majeure circumstances, actually encountered by them, as such, it be granted reasonable extension of time. Not even an iota of evidence has been placed on record to prove that the opposite party actually suffered any force majeure circumstances. Under these circumstances, the complainants are held entitled to get refund of amount deposited by them. In view of above facts of the case, the opposite party is also under an obligation to compensate the complainants, for inflicting mental agony and causing physical harassment to them, as also escalation in prices. .”
Under above circumstances, it can be said that there is a material violation on the part of the opposite party, in not offering and delivering possession of the unit, in question, to the complainants, by the promised dated i.e. 14.02.2013 or even as on today, thereby committing material violation on its part, apart from deficiency in providing service and guilty of adoption of unfair trade practice. It is settled law that when there is a material violation on the part of the builder, in not handing over possession by the stipulated date, the purchaser is not bound to accept the offer, even if the same is made at a belated stage and on the other hand, can seek refund of amount paid. It was so said by the Hon’ble National Commission, in a case titled as Aashish Oberai Vs. Emaar MGF Land Limited, Consumer Case No. 70 of 2015, decided on 14 Sep 2016, wherein, under similar circumstances, while negating the plea taken by the builder, it was held as under:-
“I am in agreement with the learned senior counsel for the complainants that considering the default on the part of opposite parties no.1 and 2 in performing its contractual obligation, the complainants cannot be compelled to accept the offer of possession at this belated stage and therefore, is entitled to refund the entire amount paid by him along with reasonable compensation, in the form of interest.”
Not only as above, in a case titled as Brig Ajay Raina (Retd.) and another Vs. M/s Unitech Limited, Consumer Complaint No.59 of 2016, decided on 24.05.2016, wherein possession was offered after a long delay, this Commission, while relying upon the judgments rendered by the Hon’ble National Commission, ordered refund to the complainants, while holding as under:-
“Further, even if, it is assumed for the sake of arguments, that offer of possession, was made to the complainants, in July 2015 i.e. after a delay of about three years, from the stipulated date, even then, it is not obligatory upon the complainants to accept the same.
Furthermore, in another case titled as M/s. Emaar MGF Land Ltd. & Anr. Vs. Dr.Manuj Chhabra, First Appeal No.1028 of 2015, decided on 19.04.2016, the Hon’ble National Commission, under similar circumstances, held as under:-
“I am of the prima facie view that even if the said offer was genuine, yet, the complainants was not obliged to accept such an offer, made after a lapse of more than two years of committed date of delivery”.
In the present case, there is nothing on record to show that the opposite party suffered any force majeure circumstances, on account of which, construction could not be completed. Non-filing of reply and evidence by the opposite party, is sufficient to prove the case of the complainants. Under these circumstances, the complainants are held entitled to get refund of amount deposited by them. In view of above facts of the case, the opposite party is also under an obligation to compensate the complainants, for inflicting mental agony and causing physical harassment to them, as also escalation in prices.
Consumer complaint bearing no.527 of 2017. The opposite party is directed as under:-
Consumer complaint bearing no.556 of 2017. The opposite party is directed as under:-
Pronounced.
20.02.2018
Sd/-
[JUSTICE JASBIR SINGH (RETD.)]
PRESIDENT
Sd/-
(DEV RAJ)
MEMBER
Sd/-
(PADMA PANDEY)
MEMBER
Rg.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.