View 963 Cases Against Ansal Properties
View 3633 Cases Against Properties
Major Kamaljeet Singh filed a consumer case on 22 Mar 2017 against Ansal Properties and Infrastructure Ltd. in the StateCommission Consumer Court. The case no is CC/31/2017 and the judgment uploaded on 23 Mar 2017.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 31 of 2017 |
Date of Institution | : | 11.01.2017 |
Date of Decision | : | 22.03.2017 |
Both residents of House No.88, Sector-A, Chandimandir,
Panchkula.
……Complainants
.... Opposite Parties
Complaint under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
MR. DEV RAJ, MEMBER.
MRS. PADMA PANDEY, MEMBER.
Argued by: Sh.Piyush Aggarwal, Advocate for the complainants.
None for the opposite parties (Defence struck of).
PER JUSTICE JASBIR SINGH (RETD.), PRESIDENT
The complainants who are husband and wife have filed this complaint seeking possession of the unit bearing no.904, first floor, measuring 1299 square feet, purchased by them, in the project of the opposite parties, namely “Exclusive Floors”, Golf Links, Sector 114, Kharar Landran Road, Mohali, Punjab. They purchased the said unit, to satisfy future needs of their family, as they were residing in a Govt. accommodation. They looked into various promises made by the opposite parties and agreed to purchase the said unit, for an amount of Rs.30,90,510/-, which included basic sale price plus additional charges. The amount was to be paid as per scheduled payment plan. The complainants paid an amount of Rs.3 lacs on 19.11.2010, vide receipt Annexure C-1, at the time of signing allotment letter. It is case of the complainants that they continued to make payment as per the payment schedule. Finally, allotment letter/agreement (in short the agreement) was issued to them on 05.02.2011. Before signing the said Agreement, they had paid an amount of Rs.5,69,538/-. It is their further case that as per Clause 12 of the Agreement, the opposite parties agreed to hand over possession of the constructed unit, within a period of 24 to 30 months of commencement of the construction after getting requisite approvals/clearances, from the Competent Authorities, subject to force majeure circumstances i.e. on or before 04.08.2013. Clause 12 of the Agreement reads thus:-
“The Construction of the said independent floor is likely to be completed within 24 to 30 months of commencement of work, which shall be tentatively the date of receipt of all requisite sanctions/approvals/ permissions/clearances subject however to force majeure circumstances, regular and timely payments by Allottee(s), availability of building material etc., change of policy by Government/Local Authorities etc. No claim by way of damages/compensation shall be raised against the Company in case of delay in handing over the possession on account of the said reasons or any other reasons beyond the control of the Company.”
As and when demands were raised, amount was deposited towards price of the said unit. Receipts have been placed on record as Annexure C-3 colly. By 22.06.2012, the complainants had paid an amount equal to 70% of the total price of the unit i.e. Rs.22,06,106/-. However, possession of the unit was not offered. The complainants patiently continued to wait, however, no assurance was given by the opposite parties to hand over possession of the unit, within a time bound manner. On 04.04.2015, the complainants sent a letter to the opposite parties seeking reasons of delay in handing over possession of the unit. They further said that for more than one and a half years, no update qua status of construction has been given to them, by the opposite parties. In response thereto, the complainants received letter dated 04.04.2015, from the opposite parties, assuring them that possession of the unit will be handed over tentatively in the month of October 2015 or November 2015. Relevant part of the said letter reads thus:-
“This is regarding your unit no.904FF in Exclusive Floors situated at Golf Link-I, Sector 114, Mohali, we would like to inform you that as on date External Plastering for said unit has already completed. Now Flooring and Final Finishing work is pending. To complete pending work, it will take tentatively 6 months with extended period of 3 months time. So possession for said unit will be offered tentatively in m/o October 2015 or November 2015.”
It was promised that possession of the unit will be offered in the month of October or November 2015. However, it was not so done. The opposite parties continued to put off the complainants, on one pretext or the other. It is positive case of the complainants that to make payment towards price of the said unit, they had raised loan from Army Group Insurance Fund, New Delhi and they had been repaying the same. However, on account of delay, as they failed to get possession of the unit, in question, they could not make payment, which led to receiving repeated demands by the above said party. It was alleged that the opposite parties have not performed, as per promise made, to offer possession of the constructed unit. By further alleging that the opposite parties have also adopted unfair trade practice, by selling the units without getting necessary approvals, a prayer has been made that let directions be issued to them (opposite parties) to hand over possession of the unit purchased, complete in all respects; pay compensation for the period of delay in handing over possession, by way of interest @12% p.a. on the amount deposited; compensation for mental agony and physical harassment; cost of litigation expenses etc.
“Called third time at the end of the entire list. Neither reply filed nor anybody had come present to assist this Commission on behalf of the Opposite Parties. It is clear from the record that on 25.01.2017, one representative of the Company had put in appearance on behalf of the Opposite Parties and placed on record Vakalatnama of Sh.Rachit Kaushal, Advocate. He sought time to file reply and evidence and on his request, the matter was adjourned to 14.02.2017. On the said date, Ms. Kashika Kaur, Advocate put in appearance on behalf of the Opposite Parties and she sought further time to file reply and evidence. To the prayer made, very graciously no objection was raised by the Counsel for the complainants. The matter was adjourned to today. Reply and evidence could have been filed by the Opposite Parties in the office of this Commission. However, it was not done. Today, none is present to give any explanation for not filing any reply and evidence. Hence, the defence of the Opposite Parties is struck of.
Arguments heard.
Reserved for orders.”
“We are unable to persuade ourselves to agree with the ld. counsel. While affirming the order passed by the District Forum and commenting and deprecating the conduct of the Opposite Parties in the complaint, in launching the project and selling the farmhouses, even without obtaining sanction/approval from the competent authority, the State Commission has observed as follows:-
If a marketing agency sells out a project, for which, no approvals/sanctions have been granted by the Govt. Authorities, the said agency has to face the music and consequences of duping the gullible buyers, of their hard-earned money. In the public notice, it has specifically been mentioned by the GMADA that respondent no.2 and appellant no.1 are the sister concern. It is also apparent on record that before appellant no.1 started marketing the project, not even an application has been filed by respondent no.2, to get approval/sanction from the competent authorities, to launch the project. The information supplied vide letter dated 26.08.2014, referred to above, clearly states that not even a single application qua granting sanction to the project, has been received and dealt with, by the Competent Authority. In connivance with each other, the appellants and respondent no.2 committed a criminal offence of cheating. As per established law, builder cannot sell its property, unless and until proper approvals/sanctions have been obtained by it, from the Competent Authorities. It appears from the reading of documents on record that instead of selling a unit in a project, respondent no.2 in a very arbitrary manner, sold its share in a joint land measuring approx. 3807 acres, bearing hadbast No.326, Khewat No.92, Khatauni no.254-352, at Village Mirzapur, District Mohali, Punjab. There is nothing on record that said land was ever partitioned.
6. We are in complete agreement with the view taken by the State Commission. ”
The principle of law, laid down in the aforesaid case, is fully applicable to the present case. In view of above, it can safely be said that by adopting unfair trade practice, the project was sold/launched.
“What relief can be granted to a consumer, in case of delay, in offering possession, came up for consideration before the Hon’ble National Commission, in a case titled as Parsvnath Exotica Ghaziabad Resident's Association Vs. Parsvnath Buildwell Pvt. Ltd. & Anr., consumer complaint no.45/2015, decided by the Hon’ble National Commission, on 06.05.2016, wherein, it was argued by the project proponent that at the maximum, as provided in the Agreement, the consumer will be entitled to claim penalty for delayed compensation @Rs.5/- per square feet, per month. Noting that in case of delay in making payment, the project proponent was charging heavy penal interest, instead of penal amount, the interest on the deposited amount, for the period of delay was granted, by holding as under:-
“Though, the Agreement between the developer and the flat buyers provides for payment of compensation in case of delay @ Rs.5/- per square feet of the super area per month, such clauses have been found to be unfair trade practice and have been consistently rejected by this Commission in several decision, including Consumer Complaint No. 427 of 2014 Satish Kumar Pandey & Ors. Vs. Unitech Ltd. and connected matters decided on 08.6.2015. Therefore, the aforesaid clauses cannot be taken into consideration, while determining the compensation payable to the members of the complainant association for the aforesaid delay in completion of construction.”
Not only this, in another case, titled as Capt. Gurtaj Singh Sahni & anr. Vs Manager, Unitech Limited & anr., consumer complaint bearing no.603/2014, decided on 02.05.2016, the Hon'ble National Commission, directed the opposite party/builder to pay interest on the deposited amount, for the period of delay, till delivery of possession of the unit. Relevant contents of the said order reads thus:-
“8. If the compensation for the delay in construction is restricted to what is stipulated in the Buyers Agreement, there will be no pressure upon the builder to complete the construction since he will be more than happy to keep on paying paltry compensation of about 3% per annum of the capital investment, instead of arranging funds at much higher cost, to complete the construction.
9. xxxxxxxxxxxxx
10. For the reasons stated hereinabove, the complaints are disposed of with the following directions:
(1) xxxxxxxxxxxxxx
(2) The opposite party shall pay compensation in the form of simple interest @ 12% per annum from the expected date of possession till the date on which the possession is actually offered to the complainants after completing the construction in all respects and obtaining the requisite completion certificate.”
Thus, keeping in view the principle of law laid down by the Hon'ble National Commission, in the cases, referred to above, if interest @12% on the deposited amount for the period of delay, till delivery of possession of the unit, is awarded, that would meet the ends of justice.”
Not only this, in H.P. Housing Board Vs. Janak Gupta [2009] INSC 627 (26 March 2009) (Civil Appeal No. 6346 of 2002), it was clearly held by the Hon’ble Supreme Court of India that in the cases of delay, in delivery of possession, award of interest @ 12% per annum, on the deposited amount, for the period of delay, would meet the ends of justice.
Taking note of above said proposition of law, ends of justice would meet, if interest is granted for delayed period, to the complainants whereof 04.08.2013. However, in the instant case, if interest @11% p.a. for the period of delay, on the deposited amount is granted, that would meet the ends of justice.
Pronounced.
22.03.2017
Sd/-
[JUSTICE JASBIR SINGH (RETD.)]
PRESIDENT
Sd/-
(DEV RAJ)
MEMBER
Sd/-
(PADMA PANDEY)
MEMBER
Rg.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.