Uttar Pradesh

StateCommission

CC/46/2022

Krishna Nandan Singh - Complainant(s)

Versus

Ansal Properties and Infrastructure Ltd And Another - Opp.Party(s)

Piyush Mani Tripathi

26 Jul 2023

ORDER

STATE CONSUMER DISPUTES REDRESSAL COMMISSION, UP
C-1 Vikrant Khand 1 (Near Shaheed Path), Gomti Nagar Lucknow-226010
 
Complaint Case No. CC/46/2022
( Date of Filing : 20 Apr 2022 )
 
1. Krishna Nandan Singh
R/o flat no. 1701 Tower no. 13 Omaxe R2 Arjunganj Lucknow
...........Complainant(s)
Versus
1. Ansal Properties and Infrastructure Ltd And Another
Office at 115 Ansal Bhawan 16 Kasturba Gandhi Marg New Delhi
............Opp.Party(s)
 
BEFORE: 
 HON'BLE MR. JUSTICE ASHOK KUMAR PRESIDENT
 HON'BLE MR. SUSHIL KUMAR JUDICIAL MEMBER
 
PRESENT:
 
Dated : 26 Jul 2023
Final Order / Judgement

 RESERVED

THE STATE CONSUMER DISPUTES REDRESSAL COMMISSION, LUCKNOW

 

COMPLAINT CASE NO. 46 OF 2022

 

KRISHNA NANDAN SINGH, Resident of Flat No. 1701, Tower No.13, OMAXE R2, Arjunganj, Lucknow, Uttar Pradesh

    …. COMPLAINANT

Versus

 

  1. M/S ANSAL PROPERTIES & INFRASTRUCTURE LTD., having its registered office at 115, Ansal Bhawan, 16 Kasturba Gandhi Marg, New Delhi 110001, through its Director/Managing Director.

 

  1. SUSHANT GOLF CITY., having its site office at Sushant Golf City., 2nd Floor, Shopping Square 2 Sec D Shaheed Path - Sultanpur Road Sushant Golf City, 226002 through its Authorized Officer/Director.

 

 

  1. LIC HOUSING FINANCE LIMITED, having its registered office at Bombay Life Building, 2nd floor, 45/47 Veer Nariman Road, Mumbai, 400001 and having its branch office at 4/291 Vivek Khand, Gomti Nagar, Lucknow - 226010

…. OPPOSITE PARTIES

AND

Miscellaneous Case no 346/2022

Krshna Nandan Singh Vs. Ansal Properties and Infrastructure   

           Limited &Ors

AND

Miscellaneous Case no 137/2023

Krshna Nandan Singh Vs. Ansal Properties and Infrastructure   

Limited & Ors.

Present:-

Hon’ble Justice Ashok Kumar, President

Hon’ble Mr. Sushil Kumar, Member.

 

Mr Piyush Mani Tripathi , Advocate for Complainant.

Mr Asif Anees , Advocate for Opposite Parties no 1 & 2.

 

Date:  08.08.2023

JUDGMENT

Per Mr. Sushil Kumar, Member: The present Complaint Case and         Miscellaneous Cases are being related to one another hence they  are  being  decided by the single judgment.

 

This complaint case has  been filed under section 47 of the Consumer Protection Act, 2019  against the opposite parties for the following reliefs:

 

 

  1. That Hon'ble Commission may graciously be pleased to direct the opposite parties to hand over the possession of fully finished residential unit of the Apartment No. C1 – 201, situated at Sushant Jeevan Enclave, Sushant Golf City, Lucknow.

 

It is further prayed that this Hon'ble Commission may graciously be please to direct the opposite parties to pay interest at the rate of 24% on amount of Rs. 26,00,090/- (Rupee Twenty Six Lakhs and Ninety Only) with effect from the dates of payment till the date of the execution of the lease deed/conveyance deed.

 

It is also prayed that this Hon'ble Commission may be please to award all the reliefs as mentioned in the prayer clause of the complaint.

 

The brief facts of this complaint case are that, That the complainant is resident of District Lucknow Uttar Pradesh, the cause of action to file this case arose within the territorial and pecuniary jurisdiction of this Hon'ble Commission under Section 47 of the Consumer Protection Act, 2019. As such, it is humbly contended that the complainant is aggrieved by the severe deficiency in service and unfair contract on part of the opposite parties.

 

The opposite party nos. 1 and 2 are builders and are engaged in the construction of the residential unit and developing the projects with all the basic civic amenities. Opposite Party No. 3 is a corporate entity which is in the business of financing housing projects and providing loans to buyers of residential units including the complainant.

 

The opposite party nos. 1 and 2 in order to sell their units propagated online brochure available on several web site, by means of which glorious pictures of the proposed residential project is displayed. In this brochure the facilities and amenities which are to be provided like club house, Gym, swimming pool and interiors shown to be luxurious is shown. The specification which is to be provided to the consumer is also provided in this web brochure.

 

In view of the assurance of the agreed quality construction work with all the amenities, one M/s Jai Shree Shyam Associates applied for the allotment of the unit in the project of the developer, accordingly the flat buyer agreement dated 24.10.2011 was executed between the developer and M/s Jai Shree Shyam Associate by means of which Unit No. C1 – 201, ad measuring 1706 square feet on 2ndfloor, was allotted to him on the sale price of Rs. 3690073/- (Thirty Six Lakhs Ninety Thousand and Seventy Three Only).

 

It is pertinent to submit here that this allotment was thereafter transferred to the present complainant who subsequently on payment of Rs.11,40,090/- (Rupees Eleven Lakh Forty Thousand and Ninty Only) agreed to transfer this to the complainant vide Agreement to Transfer of Rights dated 22.09.2012 between the complainant and M/s Jai Shree Shyam Associates.

 

After receiving the amount, M/s Jai Shree Shyam Associates requested the Opposite Party no. 1 and 2 vide letter dated 24.09.2012 to transfer the rights to the residential unit C1-201, Sushant Jeevan Enclave in favour of the complainant. As per the agreement, the advance of Rs. 11,40,090 paid by M/s Jai Shree Shyam Associates was also to be considered by the Opposite Parties towards payment of the sale consideration.

 

The Opposite Parties no. 1 and 2 informed the Complainant and M/s Jai Shree Shyam Associates that the rights to the aforesaid residential unit would not be transferred in the name of the complainant unless an affidavit relinquishing all claims in the event of any penalty/compensation for delay or construction/offer of physical possession of the residential unit. As the complainant was in dire need of the residential accommodation which was due to be delivered by 24.04.2013 as per the original flat buyer agreement, the complainant signed the affidavit in duress and on repeated assurances of all the parties that timely possession of the fully finished residential unit would be delivered in accordance with all the agreed specification.

 

 

After illegally asking the complainant to sign the unfair contract dated 25.09.2012, the Opposite Parties No. 1 and 2 issued an undated transfer letter in favour of the Complainant, informing him that the transfer application/letter dated 24.09.2012 was accepted by the Opposite Parties and the residential united situated at C1-201 measuring 1706 sq. ft. stood transferred in the name of the complainant.

 

To make the payment of the balance cost of the unit, complainant applied for the financial assistance with the LIC Housing Finance Limited/Opposite Party No. 3 and by means of letter dated 30.07.2012 it was communicated by the Opposite Party No. 3 that Home Loan of Rs. 25,00,000 (Rupees Twenty Five Lakhs Only) was approved ‘In Principle’.

 

Thereafter a Tripartite Agreement was entered into between the Complainant, Opposite Parties No. 1 & 2/Builder and Opposite Party No. 3/Financer according to which Opposite Party No. 3 agreed to remit the remaining sum of Rs. 25,00,000 in installments, as per the payment plan and after periodically checking the progress of the project.

 

As per the Tripartite Agreement, the Opposite Party No. 3 made payment of Rs. 16 Lakhs at various stages of construction as per the payment plan. However, the Opposite Party No. 3/financer failed to appreciate that the payment was to be released after taking into account the stage and progress of construction and next installment was not dispersed on account of the non construction of the project and lack of unapproved plan of builders.

 

The complainant was regularly making the payment of the EMI against the financial assistance which is obtained by him from Opposite Party No. 3, to make the payment of the cost of the Unit. However, it is to the utter dismay of the complainant that the Opposite party no. 3 has disbursed the amount to the Builder without checking the progress of the stage of construction which is their statutory obligation as per the National Housing Bank circulars.

 

It is the duty of the Opposite Party No. 3 to maintain a statement of accounts in order to record the transactions made on behalf of the complainant with the Opposite Party No. 1 and 2/Builder. However, it is to the utter dismay of the complainant that the Financer/Opposite Party No. 3 has failed to maintain the statement of accounts and has not furnished the same to the complainant despite repeated requests.

 

The Opposite Parties illegally and without informing or consulting the complainant, decreased the area of the flat from the agreed 1706 Sq. Ft. to 1047.54 Sq. Ft. The Opposite Parties informed the complainant post facto when the complainant asked for a catalogue/brochure of the said project. There were many more discrepancies in the new Brochure/catalogue from the previous one such as the number of washrooms decreased from three to two. Certain specifications were also changed like the kind of tiles, laminated wooden flooring to wooden texture tiles, specification regarding electrical and telecommunication missing, changes in windows. It is worth noting that although the size of the flat was decreased, the price of the unit was not decreased proportionately.

 

The complainant made repeated requests to the Builder to hand over the fully finished flat in accordance with the agreed specifications within the stipulated time. However, it is to the utter dismay of the complainant that the Opposite Parties have failed to honor their commitment with the complainant and have proceeded to levy illegal interest charges on the complainant even though they have caused inordinate delay in completingthe residential project.

 

It is relevant to mention before this Hon’ble Commission that the opposite parties have internal arrangement with each other and prepare and draft standard form of the agreement which are common for all the consumer, no alteration and modification in these unilateral agreements can be made by the consumer, the provisions which are best suited to their convenience are incorporate by the opposite parties in their unilateral agreement.

However even the stipulation which is drafted and prepared by the opposite parties in their unilateral agreement are violated by them, as such the opposite parties are accountable for Unfair Trade Practice before this Hon'ble Commission.     

 

After the Opposite Parties No. 1 and 2/Builder made unilateral alterations to the specifications of the flat which was not in accordance to the flat buyer agreement coupled with the fact that the Opposite Party No. 1/Builder has caused inordinate delay of more than 9 years, the complainant instructed the Opposite Party No. 3/Financer to stop making payments to the Builder.

 

The opposite parties at the time of the deposit of the amount assured the complainant that the possession of the fully finished flat in the Hi-Tech Society shall be delivered with all the civic amenities and with all the specifications till April 2013. It was specifically assured by the opposite parties that the requisite permission from all the concerned authorities to construct and develop the residential apartment is obtained by them after taking the possession of the land.

 

It is pertinent to mention here that had the opposite parties communicated to the complainant that they shall inordinately delay the development of the project and make the flat contrary to the agreed specifications, the complainant ought not have opted for a Flat in the project/scheme of the opposite parties.

 

As per the RERA registration details of the project, the modified start date of the project is shown to be from 01.01.2015. However, a bare perusal of the statement of account maintained with the Opposite Parties No. 1 and 2/Builder would show that the Opposite Parties have charged delay penalty on the complainant from as early as 2013.

 

It is further necessary to mention here that as per the RERA Registration details, the modified completion date of the project is 01.07.2021 which is completely false, frivolous and contrary to the promised date of possession as per the original flat buyers agreement. It is humbly submitted that the inordinate delay caused by the Opposite Parties constitutes unfair trade practice and deficiency in service and as such extraordinary costs be imposed on the Opposite Parties.

 

It is worth to mention here that the complainant is deprived of their legal right to enjoy the possession of the Flat and are also being charged illegal interest even though the flat has not been constructed as per the specifications. Being put to extreme mental and physical harassment at the hands of the builder/opposite parties, thus the opposite parties are liable to pay punitive damages to the complainants.

 

The opposite parties proclaimed the money from the entire allottees of the project without even developing the scheme where the flat of the complainant is situated which constitutes serious deficiency in service.

 

It is humbly submitted that it is the obligation of the opposite parties as a developer/builder/service provider to demarcate and develop the Hi-Tech project and forthwith to demand the money. However, in the instant case the opposite parties in the most illegally and arbitrary manner collected the amount from the allottees of the project which is in complete contravention of the settled principle of Law without completing the construction of the project as per agreed specifications.

 

Further that the complainant is to encounter irreparable loss and injury at the hand of the opposite parties, it is prayed that this Hon’ble Commission may graciously be pleased to impose Punitive Damages on the builder for the severity of deficiency in service as well as Unfair Trade Practice committed by them.

 

A Apart from the aforementioned facts it is amply clear that the opposite parties obtained huge sum of money from the entire allottees of the scheme and instead of putting the same for the development of the scheme, they misappropriated the same, for which the opposite parties are liable to produce the expenditure and account statement of the entire scheme before this Hon’ble Commission.

 

The opposite parties are accountable for Unfair Trade Practice since they have enjoyed and utilize the hard-earned money of the complainant without providing the possession of the fully finished flat in developed Hi-Tech Society. It is submitted here that the opposite parties are also liable to pay the loss of rent to the complainants which is quantified by the complainants to the tune of Rs.20,000/- per month with effect from April 2013 till the date of the physical possession of the allotted unit.

 

This complaint case is maintainable before this Hon'ble Commission under the provisions of the Consumer Protection Act, 2019 and this Hon'ble Commission has both pecuniary as well as territorial jurisdiction to entertain and adjudicate the complaint, named above.

 

If the Opposite Parties would have finished the construction of the flat without committing any default and handed over the possession, the present market value of the fully finished flat would be around Rs. 75,00,000. Therefore, it is expedient in the interest of justice that if the Opposite Parties are unable to provide the possession of fully finished flat within 30 days, they should be directed to pay Rs 75 lacs, equivalent to the present value of his full furnished/ finished flat so that he can purchase a similar flat of similar area in the vicinity of this project.

 

 

The complainants humbly request to this Hon’ble commission to grant the following reliefs in his favour:

 

 

  1. DIRECT the Opposite Parties no. 1 and 2 to hand over the physical possession of flat situated at C1 – 201, Sushant Jeevan Enclave within 30 days

Or

DIRECT the Opposite Parties no. 1 and 2 to pay Rs 75,00,000 (seventy-five lakhs only), equivalent to the present market value of his finished flat so that he can purchase a similar flat of similar area in the vicinity of this project .

 

  1. DIRECT the Opposite Parties no. 1 and 2 to pay interest on the amount of Rs.26,00,090/- at the rate of 24% with effect from the date of the deposit till the date of delivery of physical possession of the said flat with completion certificate / occupancy certificate, NOC of Civil Aviation Department, NOC of Pollution Control Department, NOC of  Fire Control Department and competition of entire project.

 

  1. DIRECT the Opposite Parties no. 1 and 2 to pay loss of rent to the tune of Rs. 20,000 per month from April 2013 till the date of physical possession of the residential unit.

 

  1. DIRECT the Opposite Parties no. 1 and 2 to pay appropriate compensation and damages which this Hon'ble Commission may deem it just and proper in the facts and circumstances of this case.

 

  1. DIRECT the opposite parties 1 & 2 to pay Punitive Damages to the complainant which this Hon'ble Commission may deem it just and proper in the facts and circumstances of this case.

 

  1. ALLOW the complaint and direct the opposite party to pay a sum of Rs.2,00,000/- towards cost of the case.

 

  1. DIRECT the opposite parties 1 & 2 not to charge a single penny more towards any head of this flat and only to charge maintenance that too after the delivery of physical possession of the said fully finished / furnished flat with completion certificate / occupancy certificate, NOC of Civil Aviation Department, NOC of Pollution Control Department , NOC of  Fire Control Department and competition of entire project.

 

  1. DIRECT the opposite parties no 1 & 2 to pay Rs. 30 lakhs towards harassment, mental agony, anxiety with interest at a rate of 24% after 36 months from the date of original allotment order to the date of giving actual possession of fully furnished/finished flat.

 

  1. Any other order which this Hon'ble State Commission may deem fit and proper in the circumstances of the case may also be passed.

 

         

          In this case, from the perusal of the records, it is clear that summons to the opposite parties were delivered upon them on 04.05.2022 ,30.04.2022 and 02.05.2022 which is clear from the track report of the speed post submitted by the complainant and which is on record. The written statement has been filed on 29.08.2022. Now the question is as to whether this written statement can be taken on record or not.

 

A Constitutional Bench ( 5 JJ ) of the Hon’ble Supreme Court  In the Case of New India Assurance Complainant Vs Hilli Multipurpose Cold Storage Private Limited , Civil Appeal no 10941 -10942 of 2013 along with other many related Civil Appeals( judgement 04.03.2020 ) held ;

“The reference made to this Constitution Bench relates to the                        grant of time for filing response to a complaint under the provisions of the Consumer Protection Act, 1986 (for short ‘the Act’).  

The first question referred is as to whether Section 13(2) (a)   of   the   Consumer   Protection   Act,   which   provides   for the respondent/opposite party filing its response to the complaint within 30 days or such extended period, not exceeding 15 days, should   be   read   as   mandatory   or   directory;   i.e.,   whether  the District Forum has power to extend the time for filing the response beyond the period of 15 days, in addition to                30 days.

The second question which is referred is as to what would be the commencing point of limitation of 30 days stipulated under the aforesaid Section.

 

The first question was referred by a two Judges bench of this Court vide an order dated 11.02.2016 passed in Civil Appeal No (s) 10831084 of 2016, M/S Bhasin Infotech and Infrastructure Pvt Ltd Vs  M/S  Grand Venezia Buyers Association ( Reg), the relevant portion of which is as under :

“there is an apparent conflict between the decision of this Court in Topline Shoes Limited  vs  Corporation Bank [(2002)6 SCC 33], Kailash  vs  Nankhu [(2005)4 SCC 480] , Salem advocate Bar Association VS Union of India [(2005) 6 SCC 344] on the one hand and  J J Merchan  &Ors vs Shrinath Chaturvedi [(2002) 6 SCC 635)] and NIA Vs Hilli Multipurpose Cold Storage [ 2014 AIOL 4615] on the other in so far as the power of the courts to extend time for filing of Written Statement/reply to a complaint is concerned. The earlier mentioned line of decision take the view that the relevant provisions including those of Order 8 Rule 1 of the Civil Procedure Code 1908 are directory in nature and the Courts concerned have the power to extend time for filing the written statement. The second line of decisions which are also of coordinate Benches however takes a contrary view and hold that when it comes to power of the Consumer Fora to extend the time for filing a reply there is no such power. Since the question that falls for determination here often arises before the Consumer Fora and Commissions all over the country it will be more appropriate if the conflict is resolved by an authoritative judgement. Further since the conflict is between Benches comprising three Judges we deem it fit to refer these appeals to a five – Judge Bench to resolve the conflict once and for all. While we do so we are mindful of the fact that in the ordinary course a two – Judge Bench ought to make a reference to a three – Judge Bench in the first place but in the facts and circumstances of the case and keeping in view the fact that the conflict is between coordinate benches That comprising three Judges a reference to 3 Judges may not suffice”

 

The Hon’ble Supreme Court in para 41 of the judgement has held

“ To conclude, we hold that our answer to the first question is that The District Forum has no power to extend the time for filing the response to the complainant beyond the period of 15 days in addition to 30 days as envisaged under section 13 of the Consumer Protection Act ; and the answer to the second question is that the commencing point of limitation of 30 days under Section 13 of the Consumer Protection Act would be from the date of receipt of the notice accompanied with the complainant by the opposite party and not mere receipt of the notice of the complainant. ”

 

The Hon’ble Supreme Court in para 40 of the judgment has held

“………….. we may, however, clarified that the objection of not having received a copy of the complaint along with the notice should be raised on the first date itself and not thereafter, otherwise permitted to be raised at any point later on defeat the very purpose of the Act, which is to provide simple and speedy Redressal of consumer disputes.”

[Section 38 of the Consumer Protection Act  2019 has also the same time limit to file written statement. It is quoted hereinbelow ;

38. Procedure on admission of complaint –(1) the District Commission shall , on admission of a complaint, or in respect of cases referred for mediation on failure of the agreement by mediation proceed with such complaint.

(2) were the complainant relates to any goods, the discussion That shall –

(a) referral copy of the admitted complaint, within 21 days from the date of its admission to the opposite party mentioned in the complaint directing him to give his version of the case within a period of 30 days or such extended period not exceeding 15 days as may be granted by it ; ]

According to section 49 of The Consumer Protection Act 2019, the provisions relating to complainants under section 35, 36, 37, 38 and 39 shall, with such modifications as may be necessary, be applicable to the disposal of complaint by the State Commission.

 

So in this case the written statement has been filed beyond the prescribed period as mentioned in section 49 of the Consumer Protection Act 2019 . As per the act and as per the judgement of the only Supreme Court (Constitutional Bench) this written statement is not liable to be taken on record so it will be not the part of the record. Summon served on opposite party no 3 as per speed post track report but he did not turn up so against him the case shall proceed ex parte .

 

We have heard Sri Piyush Mani Tripathi, learned counsel for the complainant and Sri Asif Anees, learned counsel for the opposite party and perused the pleadings, evidences and documents on record.

 

          So in this case it is clear that the complainant is a subsequent purchaser. One M/s Jai Shree Shyam Associates applied for the allotment of the unit and accordingly Flat Buyer Agreement dated 24-10-2011 was executed between the Developer and M/s Jai Shree Shyam Associates. Thereafter the allotment was transferred to the present complainant who on payment of Rs. 11,40,090/-  agreed to transfer it to the complainant vide agreement to transfer of rights dated 22-09-2012. M/s Jai Shree Shyam Associates requested the opposite parties vide letter dated 24-09-2012 to transfer the rights to the residential unit C1-201 in favour of the complainant but the opposite parties informed that the rights to the aforesaid residential unit would not be transferred in the name of the complainant unless and affidavit relinquishing all claims in the event of any penalty/compensation for delay or construction/offer of physical possession of the residential unit. The complainant was in dire need of a flat therefore he signed the affidavit indurous.

 

          After this, the opposite parties issued an undated transfer letter in favour of the complainant informing him that the transfer application dated 24-09-2012 was accepted and the residential unit at C1-201 measuring 1706 Square Feet stood transfer in the name of the complainant.

 

          The complainant for the payment of balance amount, applied for financial assistance with LIC Housing Finance Limited and he was granted a loan of Rs. 25 Lac by opposite party no.3 therefore money was deposited with the opposite parties and even after filing of the complaint some more money has also been deposited by the complainant.

 

          The opposite parties at the time of the deposit of the amount assured the complainant that the possession of fully finished Flat shall be delivered with all the civic amenities and with all the specifications till April 2013. As per RERA registration details of the project, the modified start date of the project is shown to be from 01.01.2015.Now here one question arises as to from which date the period would have been reckoned for delivery of the possession.

 

          There is a Flat Buyer Agreement on the file which was entered into between the opposite parties and Jai Shree Shyam Associates on 20-07-2011 (16-08-2011 is a date on which M/s Jai Shree Shyam applied for allotment of unit). Para-22 of the Flat Buyer Agreement states that “that the developer shall endeavour to offer possession of apartment to the allottee within 36 months from the date of sanction of building plans by the authorities subject to force majeure circumstances and on receipt of complete payment of the basic sale price and other charges due and payable after the date of possession according to the payment plan applicable to allot punctually. The development on completion of the construction shall issue final call notice to the allottee who shall within 30 days thereof, remit all dues and take possession of the apartment. In the event of his failure to take possession, for any reason whatsoever, he shall deemed to have taken possession of the allotted apartment from the date the same has been offered, for purpose of payment of maintenance charges or any other levies on account of the allotted unit, but the actual physical possession shall be given on payment of all up to date outstanding payments as demanded by the developer.”

 

          It is clear that the possession was to be handed over within 36 months . In this condition nothing has been said about the completion certificate and occupancy certificate which are necessary during the process of completion of the building and giving possession to the allottees. But before dealing with the completion and occupancy certificate we have to know the object of the Consumer Protection Act.

 

The main objectives of consumer protection act?

The Consumer Protection Act, came into existence and implemented in 1986, provides Consumer Rights to prevent consumers from fraud or specified unfair practices. It safeguards and encourages and gives an opportunity to consumers to speak against insufficiency and flaws in goods and services. If traders, manufacturers and distributors follow any foul trade, this act protects their rights as a consumer.

On which products are these right applicable?

This Protection Act covers entire goods and services of all sectors that are public, private, or cooperative sectors, except those exempted by the central government. The act provides a floor for a consumer where one can file their complaint against the product and the forum takes an action against the concerned supplier and compensation is granted to the consumer for the inconvenience he/she has encountered.

Objectives of consumer protection act

  • To Provide better and all round protection to consumer.
  • To Provide machinery for the speedy redressal of the grievances.
  • To Create framework for consumers to seek redressal.
  • To Provide rights to consumers.
  • To Safeguarde rights of Consumers.

Let us know more about the rights and responsiblities of consumer

Consumer Rights

Listed below are the Rights of the Consumer

  • Right to Safety- Before buying, a consumer can examine on the quality and guarantee of the goods and opt for ISI or AGMARK products.
  • Right to Choose- Consumer must have the right to choose from a variety and number of goods and in a competitive price
  • Right to be informed- The buyers must be provided with complete information with all the necessary and adequate details of the product, make her/him act wise, and change the buying decision.
  • Right to Consumer Education- The consumer must be aware of his/her rights and avoid exploitation.
  • Right to be heard- The consumer will get due attention to express their grievances at a suitable platform.
  • Right to seek compensation- The consumer has the right to seek or ask for redressal against unfair and inhumane practices or exploitation of the consumer.

Consumer Responsibilities

  • Responsibility to be aware – A consumer has to be careful of the safety and quality of products and services before purchasing.
  • Responsibility to think independently– Consumer should be well bothered about what they want and need and hence make independent choices.
  • Responsibility to speak out- The buyer should be fearless to speak out their problems and tell to traders what they exactly want
  • Responsibility to complain- It becomes the consumer’s responsibility to express and file a complaint about their dissatisfaction with goods or services in a sincere and fair manner.
  • Responsibility to be an Ethical Consumer- Consumer must be fair and not engage themselves with any deceptive practice.

 

 

The Consumer Protection Act 1986 was enacted to provide for better protection of the interests of consumers and for that purpose to make provision for the establishment of Consumers Councils and other authorities for the settlement of consumers’ disputes and for matters connected therewith (Preamble).

The Act Inter alia, seeks to promote and protect the rights of consumers such as —

(1) right to be protected against marketing of goods which are hazardous to life and property;
(2) right to be informed about the quality, quantity, potency, purity, standard and price of goods to protect the consumer against unfair trade practices;
(3) right to be assured, wherever possible, access to variety of goods at competitive prices;
(4) right to be heard and to assured that customers’ interests will receive due consideration at appropriate forums.
(5) Right to seek redressal against unfair practices or unscrupulous exploitation of consumers; and
(6) Right to consumer education

The objects are sought to be promoted and protected by the Consumer Protection Councils to be established at the Central and State levels.

The Act applies to all goods and services, except if otherwise provided by the Central Government by Notification. To provide speedy and simple redressal of consumer disputes, a quasi judicial machinery is set up at the District, State and Central levels. The three tier system of quasi judicial bodies will observe the principle of natural justice and are empowered to give relief of a specific nature and to award, wherever appropriate, compensation to consumers. Penalties for non-compliance of the orders given by the quasi judicial bodies have also been provided.

Thus the Consumer Protection Act is to serve the interests of the consumers. Consumer education and redressal of consumers’ grievances are the two aspects of the Act. It makes good the loss a consumer suffers and increases the feeling of responsibility of the manufacturer, trader, supplier or businessman.

The provisions of the Act have to be construed in favor of the consumer to achieve the purpose of enactment as it is social benefit oriented legislation. The primary duty of the Court while construing the provisions of such an Act is to adopt a constructive approach subject to that it should not do violence to the language of the provisions and not contrary to attempted objective of the enactment.

Extent of Consumer Protection:

While other legislations may be either punitive or preventive, the Consumer Protection Act compensates the consumer. The provisions of the Act are in addition to and not in derogation of the provisions of any law at the time being in force (Sec 3). In Maine Container Services South Pvt Ltd v Go Garments 1998 (3) SCC 247 it has been held that the Contract Act applies to all litigants before the Commissioner under the Consumers Protection Act. Passengers traveling in train suffering injuries and loss of Jewelry as a result of assault by unruly crowd are eligible for filing of complaint before State Commission is maintainable notwithstanding the provisions of sections 100 and 103 of Railways Act, 1889. The Consumer Protection Act therefore gives the consumer an additional remedy besides those which may be available under other existing laws. Existence of an arbitration clause in the agreement is no bar to the entertainment of complaint by the Redressal Agency as the remedy under the Act is in addition to the provisions of any other law. However, the Consumer Forums under the Act have not taken over the jurisdiction of civil Courts. If the dispute between the parties is pending in Civil Court no Consumer Forum will adjudicate the dispute. Similarly if evidence be laid by the parties to the dispute is voluminous or complicated the parties will be referred to the appropriate Civil Court.

Consumers Protection Act, thus enshrines the rights of a consumer to be informed about the quality, quantity, potency, price etc., of the goods to be protected against unfair trade practices, to seek inexpensive and expeditious redressal of grievances before the Consumer Forums. Consumer Protection Act is a benevolent piece of legislation to protect a large body of consumers from exploitation.

With the passage of time, the populace of the country is on hike and so are their opinions. Their opinion forms the basis for their interpretation, it may be a good or a bad interpretation. What would happen in the situation where people starting interpreting the laws? We might be flooded with several interpretations. The interpretations will be in such huge number that the laws will become unclear. This is the reason why lawmakers, while making the law, formulate itin accordance with the aim, set out by them, before penning down the legislations. The aim of any legislation defines the basis of the act. It becomes the ground norm of the act, based upon which the judiciary interprets the disputed texts.

 

The aim of any act forms the indispensable element, because it acts as the cord that delivers the real intention of the legislators behind the act.  Whenever there is clash between two legislations, it is the aim of the legislation which makes the judges to derive at the endpoint in deciding which law has the superseding effect. It is through the doctrine of pith and substance that judges are able to derive at the major inclination towards one act over another act. This inclination is decided on the basis of the aim/goal of the act and the facts of that particular case.

 

Somewhat similar situation aroused in front of Supreme Court in the case of Aftab Singh and Others v. Emaar MGF Land Limited and Another ( Review Petition (C) Nos. 2629-2630 of 2018 in Civil Appeal Nos. 23512-23513 of 2017)

 

CONSUMER PROTECTION ACT (CPA)

The beneficial legislation of Consumer Protection Act aims at reducing the grievances of the all classes of customers by providing them the preferential treatment. According to the Consumer Protection Act, the consumer dispute is the entity where the consumer/ customers have been given the convenient safeguards against ample exploitation like bad customer service, faulty goods or any unfair trade practices. The interest of the customers is protected by setting up, the three tier quasi-judicial consumer Redressal machinery which are at national, state and district levels as per section 9 of Consumer Protection Act. The Consumer Protection Act, 1986 (CPA) has been enacted in light of certain concerns related to public policy and the benefit of consumer.

 

So the main object of the consumer protection act is to safeguard the consumer against deficiency of service, unfair trade practice, inexpensive and expeditious redressal of grievances before the Consumer Forums. It is also clear that this act is not in derogation of any act but it is in addition of other act. Now we come to see about completion and occupancy certificates and also to know what is different in the two and when they are necessary for the builders.

 

COMPLETION  /  OCCUPANCY  CERTIFICATE

When buying a home, it is vital to obtain documents, such as the Occupancy Certificate (OC) and Completion Certificate (CC). These are essential documents that allow you to mortgage or sell your home. Hence, homebuyers are advised to take possession of their flat or property only after these documents have been issued.

According to Vikas Bhasin, CMD, Saya Group, “Completion Certificate and Occupancy Certificate are some of the most important documents for a home buyer. Civic authorities can evict the occupants in case of non-availability of the necessary approvals. Before investing in a property, people must be doubly assured that all the certificates and approvals are in place.”

Let us dive a little deeper into the details of these documents and their importance before you make a move to buy your dream home.

Owning a home is the culmination of years of savings, research, and paperwork. After patiently waiting for the construction to be complete, you finally register the property and take possession of your flat. But what if your dream home is declared unauthorised, and you are evicted by the authorities? This is not as far-fetched as it sounds. This nightmare could turn into reality without a crucial link in the property sale process - the Occupancy Certificate (OC). 

The majority of apartments in different Indian cities have been occupied by owners without any occupancy certificate. This oversight can turn into a costly mistake, jeopardising the legal status of your dream home. The importance of the occupancy certificate cannot be overstated as it seals the legal status of your property and protects your ownership rights. 

Decoding legal documents 

To understand the importance of an occupancy certificate and other legal documents, let’s decode the legal jargon and understand their meaning in simple terms. Here’s a ready reckoner of the most important legal documents related to your property: 

Occupancy Certificate 

An OC certifies that the construction of the building has complied with the approved plans. It is issued by local municipal authorities or the building proposal department once the building has been completed and is ready to be occupied. Simply put, without an OC, your building has not been awarded a ‘pass certificate’. 

Completion Certificate 

A Completion Certificate (CC) is issued only after the construction meets other building standards like distance from the road, the height of the building, and rainwater harvesting system. A CC alone cannot legalise occupation; the OC is a must. 

Commencement Certificate 

If you are buying an under construction property, make sure you check the Commencement Certificate before signing the agreement. Many builders do not wait for a Commencement Certificate. This is illegal and can create serious problems in obtaining an OC at a subsequent stage. 

Why is it unsafe to buy a flat without OC? 

In the absence of a valid OC, the local municipal body can initiate serious action against flat owners. In 2014, residents of a well-known building complex in Mumbai’s upscale Worli area were hit with a bolt from the blue after their complex was declared unauthorised. At the time of possession, buyers overlooked the issuance of an OC from the builder. It was only after that they were forced to evacuate their flats that the writing on the wall became clear to them. 

This is just one instance, and if buyers are not careful about getting the OC, they may face the following repercussions: 

• In the absence of a valid OC, your building can be demolished as it can be classified as an unauthorised structure.

• The OC is crucial while applying for a home loan or loan to purchase a resale flat. If you wish to sell or hypothecate the property after a lapse of time, you will not be able to do so without a valid OC. 

• The water connection, sanitary connection or electricity supply can be disconnected in the absence of an OC. 

 

How to obtain an OC 

The OC is obtained from local municipal bodies by submitting an OC application form along with the following documents: 

• Commencement Certificate 

• Completion Certificate 

• Built and Section plan 

• NOC for fire and pollution 

• Area calculation sheet of floor signed by an authorised architect 

• Photographs of the completed building 

• Tax assessment with tax paid receipt 

• Photographs of rain harvesting and solar panels 

• Copy of the sanctioned plan 

After submitting the form, authorities inspect the complex and confirm if it has conformed to the approved plan before issuing an OC. Legally and ideally, a builder should submit an application with the municipal commissioner for the OC within 30 days of completion of the property. 

How you can apply for an OC 

As a flat owner, you can also apply for an OC by approaching the local corporation or municipality, and if all approvals are in place, an OC is issued within 30 days of application. You will have to submit the same documents as the builder to procure an OC. 

Know your rights 

If the builder refuses to provide an OC, you should consider exercising your legal rights. You can issue a notice against the builder asking him to apply and hand over the copy of the OC within a month. You can also approach consumer forums and file a writ petition demanding the OC. 

Some canny builders simply present the receipt of the OC and dupe gullible customers. But you shouldn’t accept anything less than the actual OC as the receipt may be dated. 

Landmark legislations like the Real Estate Regulatory Act (RERA) have been passed to regulate the sector, promote transparency and protect consumer rights. However, consumers must be vigilant and understand their rights and responsibilities towards owning a property. Documents like OC are essential and ensure the security of your investment. 

Going forward, real estate experts believe that the OC should be made mandatory for the registration of flats and essential services. Until then, buyers must ensure builders get all the necessary approvals before handing over a property.   

 

A Completion Certificate (CC) is an important legal document that certifies that a building is constructed according to the laid down norms and master plan of the city. This document has all the information related to the project, such as the building materials used, building height, and building plan, among other things like provision for green belt.

In a nutshell, this document certifies that the building adheres to all the prevailing rules and has not violated any norms. In fact, this document is to be shown compulsorily to the authorities to obtain electricity and water connection.

Builders are allowed to obtain a provisional Completion Certificate when there are minor works left in the project. Authorities then provide a provisional certificate valid for six months. After the expiry of the six months, the developer is bound to get a final CC.

Who issues a Completion Certificate?

Local authorities issue the Completion Certificate after a thorough inspection of the premises. If the developer violates no rules, authority issues a Completion Certificate.

Why is Completion Certificate important?

Buyers must be aware of the fact that if they are buying or moving into a property that does not have a Completion Certificate, they might be making a risky investment choice. The civic authorities hold the power to slap heavy penalties on the developer, leading to stalling or cancellation of the registered layout of the project. In case the building is already occupied, residents may also have to face eviction in extreme cases.

Difference between Occupancy Certificate and Completion Certificate

Occupancy Certificate examines and certifies a property for adherence to bye-laws, civic amenities, electricity, sanitation and other clearances. On the other hand, a Completion Certificate is a document that certifies that a property is fit for possession by the buyers.

Clarifying the difference, Deepak Kapoor, Director, Gulshan Homz, says, “Completion Certificate is just a reaffirmation that the building has been constructed as per the building byelaws and the layout plan has been approved by various concerned authorities. Occupation Certificate signals that there is no violation of building construction norms, and thus, the structure is safe for occupants. 

Generally, these documents are not required at the time of registry, and hence, buyers tend to overlook or ignore these. But for their own benefit and peace of mind, it is warranted that buyers of both ready-to-move-in as well as under-construction properties check these documents before taking possession. This would help avoid any unnecessary dispute or confrontation in the future.”

In the absence of any such certificate on the record it shall be presumed that the builders did not get the completion certificate or occupancy certificate. Occupancy certificate is necessary at the time of giving possession of the flat to the allottee which can be seen by the following judgement of this Hon’ble Supreme Court.

 

Supreme Court: The bench of Dr. DY Chandrachud* and AS Bopanna, JJ has held that failure on the part of the builder to provide occupancy certificate is a continuing breach under the Maharashtra Ownership Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act 1963 and amounts to a continuing wrong.

Factual Background

The appellant is a co-operative housing society. The respondent constructed Wings ‘A’ and ‘B’ and entered into agreements to sell flats with individual purchasers in accordance with the Maharashtra Ownership Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act 1963 (MOFA). The members of the appellant booked the flats in 1993 and were granted possession in 1997. According to the appellant, the respondent failed to take steps to obtain the occupation certificate from the municipal authorities.

There was an obligation on the respondent to provide the occupancy certificate and pay for the relevant charges till the certificate has been provided, however, the respondent time and again failed to provide the occupancy certificate to the appellant society. For this reason, a complaint was instituted in 1998 by the appellant against the respondent. The NCDRC on 20 August 2014 directed the respondent to obtain the certificate within a period of four months. Further, the NCDRC also imposed a penalty for any the delay in obtaining the occupancy certificate beyond these 4 months. Since 2014 till date, the respondent failed to provide the occupancy certificate.

In the absence of the occupation certificate, individual flat owners were not eligible for electricity and water connections. Due to the efforts of the appellant, temporary water and electricity connections were granted by the authorities. However, the members of the appellant had to pay property tax at a rate 25% higher than the normal rate and water charges at a rate which was 50% higher than the normal charge.

Analysis

Obligations of Promoter under MOFA

Section 3 of the MOFA imposes certain general obligations on a promoter. These obligations inter alia include making disclosures on the nature of title to the land, encumbrances on the land, fixtures, fittings and amenities to be provided, and to not grant possession of a flat until a completion certificate is given by the local authority. The responsibility to obtain the occupancy certificate from the local authority has also been imposed under the agreement to sell between the members of the appellant and the respondent on the latter.

Sections 3 and 6 of the MOFA indicate that the promoter has an obligation to provide the occupancy certificate to the flat owners. Apart from this, the promoter must make payments of outgoings such as ground rent, municipal taxes, water charges and electricity charges till the time the property is transferred to the flat-owners. Where the promoter fails to pay such charges, the promoter is liable even after the transfer of property.

Limitation

In the instant case, the appellant submitted that since the cause of action is founded on a continuing wrong, the complaint is within limitation.

Section 24A of the Consumer Protection Act 1986 provides for the period of limitation period for lodging a complaint. A complaint to a consumer forum has to be filed within two years of the date on which the cause of action has arisen.

Section 22 of the Limitation Act 1963 provides for the computation of limitation in the case of a continuing breach of contract or tort. It provides that in case of a continuing breach of contract, a fresh period of limitation begins to run at every moment of time during which the breach continues

A continuing wrong occurs when a party continuously breaches an obligation imposed by law or agreement. The continuous failure to obtain an occupancy certificate is a breach of the obligations imposed on the respondent under the MOFA and amounts to a continuing wrong.

The appellants, therefore, were entitled to damages arising out of this continuing wrong and their complaint is not barred by limitation.

“Rejecting the complaint as being barred by limitation, when the demand for higher taxes is made repeatedly due to the lack of an occupancy certificate, is a narrow view which is not consonance with the welfare objective of the Consumer Protection Act 1986.”

Consumer

Section 2(1)(d) of the Consumer Protection Act defines a ‘consumer’ as a person that avails of any service for a consideration. A ‘deficiency’ is defined under Section 2(1)(g) as the shortcoming or inadequacy in the quality of service that is required to be maintained by law.

In the present case, the NCDRC had held that the appellant is not a ‘consumer’ under the provisions of the Consumer Protection Act as they have claimed the recovery of higher charges paid to the municipal authorities from the respondent. Extending this further, the NCDRC observed that the respondent is not the service provider for water or electricity and thus, the complaint is not maintainable.

 

The respondent was responsible for transferring the title to the flats to the society along with the occupancy certificate. The failure of the respondent to obtain the occupation certificate is a deficiency in service for which the respondent is liable. Thus, the members of the appellant society are well within their rights as ‘consumers’ to pray for compensation as a recompense for the consequent liability (such as payment of higher taxes and water charges by the owners) arising from the lack of an occupancy certificate.

[Samruddhi Co-operative Housing Society Ltd v. Mumbai Mahalaxmi Construction Pvt. Ltd, , decided on 11.01.2022]

 

During the course of argument, the complainants counsel stated that after filing of this complaint some more money has been deposited by the complainant which is more than 90% of the total cost of the flat but the flat has not been given up till now. The first flat buyer agreement was executed between the first allottee M/S Jai Shree Shyam Associates and the opposite parties on 24 October 2011. According to the flat buyer agreement the possession of the flat was to be given in three years, that is by 23rd October 2014. When this flat was transferred to the complainant, and other unfair contract was executed on 25 September 2012 . This transfer of the flat has been confirmed by the opposite parties on 24 September 2012 and thereafter the agreement was executed. The promise was made to complete the flat within three years from 24 October 2011 but cleverly  when the flat was transferred in the name of complainant, the opposite parties executed another agreement on 24 September 2012 and now they argued that the period shall be reckoned from 24 September 2012 and not from 24 October 2011. It means if there would be more than 2, 3 subsequent purchasers till 2018, the period of construction will automatically enhanced from the last agreement ! The answer is ‘no’. You have promised to complete the flat within three years and the period will start from the flat buyer agreement executed between the first allottee and the opposite parties. So we take 24 October 2011 as the starting point and according to it the delivery of possession of the flat was to be given on or before 23 October 2014. For the purpose of calculation of compensation, interest, rent et cetera we take the cut-off date as 01.11.2014.

 

As the written statement of the opposite parties has not be taken on record so only the argument presented by the opposite parties can be considered. The counsel of the opposite parties argued that the demand of 18% interest is unreasonable and the current price of the unit which is mentioned as Rs 75 lacs is false and unreasonable. He further argued that when there is a specific term in the contract, the parties are bound by the terms in the contract. The property in question is almost prepared and will be ready for possession within 8 to 10 months. But no such offer of possession has been given along with the completion certificate and occupancy certificate showing that the opposite parties are not serious in this matter.

 

In this case it is also to be noted that the opposite parties illegally and without informing or consulting the complainant decreased the area of the flat from the agreed 1706 square ft to 1047.54 square ft. The opposite party has sent a letter to the present complainant on 24 September 2012 stating that

 

 “this is to confirm that unit no  3621-1/C1-201 measuring 1706 sq ft situated in Sushant Golf City , Lucknow which was in the name of m/s Jai Shree Shyam Associates stands transferred in your name and the amount of ₹ 1,140,090/– stand credited to your account.”

 

So it is clear that when the said flat was transferred in the name of the complainant, it is area was 1706 square ft. The counsel of the opposite parties vehemently denied this fact and stated that the area of the flat is still 1706 square ft as was specified in the agreement. So it will be seen later on or at the time of execution.

 

It is argued on behalf of the opposite parties that the complainant has no locus standi against the opposite parties and there is no deficiency of service on the part of the opposite parties and there is no relation of consumer and service provider between the two because the first agreement was entered into by the previous allottee. The only Supreme Court in the following judgement has discussed in length all the aspects of this relation.

 

Whether the relation of service provider and consumer between the parties or not. Now Supreme Court has discussed in length all these aspects in the following judgement.

 

In the case of  Faqir Chand Gulati vs Uppal Agencies Pvt. Ltd. & Anr. on 10 July, 2008,  CIVIL APPEAL NO. 3302 of 2005 ,IN THE SUPREME COURT OF INDIA, Hon’ble Supreme Court has held

3. The appellant (also referred to as `land-owner') alleges that the first respondent (also referred to as the `builder') secured sanction of the plan for construction from the Municipal Corporation of Delhi [for short 'MCD') but made several unauthorized deviations during construction, resulting in several deviation notices from MCD. In fact, MCD passed an order dated 16.1.1991 to seal the premises, but subsequently, the premises was de- sealed to enable the builder to rectify the deviations. The builder delivered possession of the ground floor on 2.4.1992. The builder sold the first and second floors to four persons under sale deeds dated 18.3.1992, 18.3.1992, 2.6.1995 and 2.6.1995.

4. The delivery of the ground floor was made by the builder to appellant's son during appellant's absence from India. On his return, the appellant sent a letter dated 29.10.1992, pointing out several shortcomings in the construction and the violations of sanctioned plan, and called upon the builder to rectify the deviations and defects. The builder did not comply.”

 

“5. The appellant therefore filed complaint No. 1866 of 1994 before the District Consumer Disputes Redressal Forum-IX, Delhi, under the Consumer Protection Act, 1986 (`Act' for short) seeking the following reliefs against the builder :

a)    Return of the title deeds relating to the premises;

 

b)    Supply of completion certificate and C&D Forms from MCD; and

 

c)    Delivery of security deposit receipt for electricity meter and payment

of Rs.4262.64 being the charges for change of electricity meter. The District Forum dismissed the complaint by order dated 10.5.1996 as not maintainable under the Act, holding that the appellant was not a `consumer' as defined in section 2(1)(d)(ii) of the Act. It held that the agreement between the parties created mutual rights and obligations with a provision that in the event of breach of any condition, the affected party shall have the right of specific performance and such an agreement cannot be construed as a contract for hiring/availing a service, for consideration by a consumer.”

 

“ 12. On the contentions raised, two questions arise for consideration :

(i) Whether on the facts and circumstances, a complaint under the Consumer Protection Act, 1986 is maintainable, in regard to the Agreement dated 17.5.1991 between the parties

(ii) Whether a complaint is maintainable under the Act for a prayer seeking delivery of completion certificate and C&D Forms in regard to a building and whether the prayer for completion certificate/C&D Forms involves a prayer for rectification of the deficiencies in the building so as to secure the completion certificate and C&D Forms. Re : First Question :

13. The first question in fact involves examination of the following issue: When the owner of a plot of land enters into an agreement with a builder for development of the property by construction of a building and sharing the constructed area between the owner and the builder, and the developer commits any breach either by failing to deliver owner's share of constructed area or by constructing the building contrary to specifications, or by failing to fulfill the obligations relating to completion certificate or amenities like water, electricity and drainage, whether the owner can maintain a complaint under the Consumer Protection Act and whether in such circumstances, the owner can claim that he is a consumer and the builder is the service- provider.

14. In Lucknow Development Authority vs. M. K. Gupta [1994 (1) SCC 243] referring to the nature and object of the Act, this Court observed:

"To begin with the preamble of the Act, which can afford useful assistance to ascertain the legislative intention, it was enacted, 'to provide for the protection of the interest of consumers'. Use of the word 'protection' furnishes key to the minds of makers of the Act. Various definitions and provisions which elaborately attempt to achieve this objective have to be construed in this light without departing from the settled view that a preamble cannot control otherwise plain meaning of a provision. In fact the law meets long felt necessity of protecting the common man from such wrongs for which the remedy under ordinary law for various reasons has become illusory. Various legislations and regulations permitting the State to intervene and protect interest of the consumers have become a haven for unscrupulous ones and the enforcement machinery either does not move or it moves ineffectively, inefficiently and for reasons which are not necessary to be stated. The importance of the Act lies in promoting welfare of the society by enabling the consumer to participate directly in the market economy. It attempts to remove the helplessness of a consumer which he faces against powerful business, described as, 'a network of rackets' or a society in which, 'producers have secured power' to 'rob the rest' and the might of public bodies which are degenerating into store house of inaction where papers do not move from one desk to another as a matter of duty and responsibility but for extraneous consideration leaving the common man helpless, bewildered and shocked. The malady is becoming so rampant, widespread and deep that the society instead of bothering, complaining and fighting for it, is accepting it as part of life. The enactment in these unbelievable yet harsh realities appears to be a silver lining, which may in course of time succeed in checking the rot. A scrutiny of various definitions such as 'consumer', 'service', 'trader', 'unfair' trade practice indicates that legislature has attempted to widen the reach of the Act. Each of these definitions are in two parts, one, explanatory and the other expandatory. The explanatory or the main part itself uses expressions of wide amplitude indicating clearly its wide sweep then its ambit is widened to such things which otherwise would have been beyond its natural import."

This Court next considered the meaning of the word 'service'. Thereafter, this Court dealt with the question whether `service' included housing construction, even before the inclusion of `housing construction' in the definition of `service' by Act No.50 of 1993 with effect from 18.6.1993. This Court observed:

"What is the meaning of the word 'service'? Does it extend to deficiency in the building of a house or flat? Can a complaint be filed under the Act against the statutory authority or a builder or contractor for any deficiency in respect of given property. The answer to all this shall understanding of the word 'service'. The term has variety of meanings. It may mean any benefit or any act resulting in promoting interest or happiness. It may be contractual, professional, public, domestic, legal, statutory etc. The concept of service thus is very wide. How it should be understood and what it means depends in the context in which it has been used in an enactment.

 

What remains to be examined is if housing construction or building activity carried on by a private or statutory body was service within meaning of Clause (o) of Section 2 of the Act as it stood prior to inclusion of the expression 'housing construction' in the definition of "service" by Ordinance No. 24 of 1993. As pointed out earlier the entire purpose of widening the definition is to include in it not only day to day buying and selling activity undertaken by a common man but even to such activities which are otherwise not commercial in nature yet they partake of a character in which some benefit is conferred on the consumer. Construction of a house or flat is for the benefit of person for whom it is constructed. He may do it himself or hire services of a builder or contractor. The latter being for consideration is service as defined in the Act.... If the service is defective or it is not what was represented then it would be unfair trade practice as defined' in the Act. Any defect in construction activity would be denial of comfort and service to a consumer. When possession of property is not delivered within stipulated period the delay so caused is denial of service. Such disputes or claims are not in respect of immoveable property as argued but deficiency in rendering of service of particular standard, quality or grade. Such deficiencies or omissions are defined in Sub-clause (ii) of Clause (r) of Section 2 as unfair trade practice. If a builder of a house uses sub-standard material in construction of a building or makes false or misleading representation about the condition of the house then it is denial of the facility or benefit of which a consumer is entitled to claim value under the Act. When the contractor or builder undertakes to erect a house or flat then it is inherent in it that he shall perform his obligation as agreed to. A flat with a leaking roof, or cracking wall or sub-standard floor is denial of service. .............A person who applies for allotment of a building site or for a flat constructed by the development authority or enters into an agreement with a builder or a contractor is a potential user and nature of transaction is covered in the expression 'service of any description'. It further indicates that the definition is not exhaustive. The inclusive clause succeeded in widening its scope but not exhausting the services which could be covered in earlier part. So any service except when it is free of charge or under a constraint of personal service is included in it. Since housing activity is a service it was covered in the clause as it stood before 1993."

15. The predicament faced by the persons who deal with builders and promoters, was noticed by this Court in Friends Colony Development Committee vs. State of Orissa [2004 (8) SCC 733] in a different context while dealing with town planning laws :

"Builders violate with impunity the sanctioned building plans and indulge deviations much to the prejudice of the planned development of the city and at the peril of the occupants of the premises constructed or of the inhabitants of the city at large. Serious threat is posed to ecology and environment and, at the same time, the infrastructure consisting of water supply, sewerage and traffic movement facilities suffer unbearable burden and are often thrown out of gear. Unwary purchasers in search of roof over their heads and purchasing flats/apartments from builders, find themselves having fallen prey and become victims to the design of unscrupulous builders. The builder conveniently walks away having pocketed the money leaving behind the unfortunate occupants to face the music in the event of unauthorized constructions being detected or exposed and threatened with demolition. Though the local authorities have the staff consisting of engineers and inspectors whose duty is to keep a watch on building activities and to promptly stop the illegal constructions or deviations coming up, they often fail in discharging their duty. Either they don't act or do not act promptly or do connive at such activities apparently for illegitimate considerations. If such activities are to stop, some stringent actions are required to be taken by ruthlessly demolishing the illegal constructions and non-compoundable deviations. The unwary purchasers who shall be the sufferers must be adequately compensated by the builder. The arms of the law must stretch to catch hold of such unscrupulous builders. At the same time in order to secure vigilant performance of duties, responsibility should be fixed on the officials whose duty was to prevent unauthorized construction, but who failed in doing so either by negligence or connivance."

[Emphasis supplied]

 

16. There is no dispute or doubt that a complaint under the Act will be maintainable in the following circumstances :

(a) Where the owner/holder of a land who has entrusted the construction of a house to a contractor, has a complaint of deficiency of service with reference to the construction.

(b) Where the purchaser or intending purchaser of an apartment/flat/ house has a complaint against the builder/developer with reference to construction or delivery or amenities.

But we are concerned with a third hybrid category which is popularly called as `Joint-Venture Agreements' or `Development Agreements' or `Collaboration Agreements' between a land-holder and a Builder. In such transactions, the land-holder provides the land. The Builder puts up a building. Thereafter, the land owner and builder share the constructed area.

 

The builder delivers the `owner's share' to the land-holder and retains the `Builder's share'. The land-holder sells/transfers undivided share/s in the land corresponding to the Builder's share of the building to the builder or his nominees. As a result each Apartment owner becomes the owner of the Apartment with corresponding undivided share in the land and an undivided share in the common areas of the building. In such a contract, the owner's share may be a single apartment or several apartments. The land-holder who gets some apartments may retain the same or may dispose of his share of apartments with corresponding undivided shares to others. The usual feature of these agreements is that the land-holder will have no say or control in the construction. Nor will he have any say as to whom and at what cost the builder's share of apartments are to be dealt with or disposed of. His only right is to demand delivery of his share of constructed area in accordance with the specifications. The builders contend that such agreements are neither contracts for construction, nor contracts for sale of apartments, but are contracts entered for mutual benefit and profit and in such a contract, they are not `service-providers' to the land-owners, but a co-adventurer with the land-holder in a `joint venture', in developing the land by putting up multiple-housing (Apartments) and sharing the benefits of the project. The question is whether such agreements are truly joint-ventures in the legal sense.

17. This Court had occasion to consider the nature of `joint-venture' in New Horizons Ltd vs. Union of India [1995 (1) SCC 478). This Court held :

"The expression "joint venture" is more frequently used in the United States. It connotes a legal entity in the nature of a partnership engaged in the joint undertaking of a particular transaction for mutual profit or an association of persons or companies jointly undertaking some commercial enterprise wherein all contribute assets and share risks. It requires a community of interest in the performance of the subject matter, a right to direct and govern the policy in connection therewith, and duty, which may be altered by agreement, to share both in profit and losses. [Black's Law Dictionary; Sixth Edition, p. 839]. According to Words and Phrases, Permanent Edition, a joint venture is an association of two or more persons to carry out a single business enterprise for profit [P.117, Vol. 23]. "

[Emphasis supplied] The following definition of 'joint venture' occurring in American Jurisprudence [2nd Edition, Vol.46 pages 19, 22 and 23] is relevant:

 

"A joint venture is frequently defined as an association of two or more persons formed to carry out a single business enterprise for profit. More specifically, it is in association of persons with intent, by way of contract, express or implied, to engage in and carry out a single business venture for joint profit, for which purpose such persons combine their property, money, effects, skill, and knowledge, without creating a partnership, a corporation or other business entity, pursuant to an agreement that there shall be a community of interest among the parties as to the purpose of the undertaking, and that each joint venturer must stand in the relation of principal, as well as agent, as to each of the other coventurers within the general scope of the enterprise.

Joint ventures are, in general, governed by the same rules as partnerships. The relations of the parties to a joint venture and the nature of their association are so similar and closely akin to a partnership that their rights, duties, and liabilities are generally tested by rules which are closely analogous to and substantially the same, if not exactly the same as those which govern partnerships. Since the legal consequences of a joint venture are equivalent to those of a partnership, the courts freely apply partnership law to joint ventures when appropriate. In fact, it has been said that the trend in the law has been to blur the distinctions between a partnership and a joint venture, very little law being found applicable to one that does not apply to the other. Thus, the liability for torts of parties to a joint venture agreement is governed by the law applicable to partnerships."

 

"A joint venture is to be distinguished from a relationship of independent contractor, the latter being one who, exercising an independent employment, contracts to do work according to his own methods and without being subject to the control of his employer except as to the result of the work, while a joint venture is a special combination of two or more persons where, in some specific venture, a profit is jointly sought without any actual partnership or corporate designation."

(emphasis supplied) To the same effect is the definition in Corpus Juris Secundum (Vol. 48A pages 314-315):

 

"Joint venture," a term used interchangeably and synonymous with 'joint adventure', or coventure, has been defined as a special combination of two or more persons wherein some specific venture for profit is jointly sought without any actual partnership or corporate designation, or as an association of two or more persons to carry out a single business enterprise for profit or a special combination of persons undertaking jointly some specific adventure for profit, for which purpose they combine their property, money, effects, skill, and knowledge........ Among the acts or conduct which are indicative of a joint venture, no single one of which is controlling in determining whether a joint venture exists, are: (1) joint ownership and control of property; (2) sharing of expenses, profits and losses, and having and exercising some voice in determining division of net earnings; (3) community of control over, and active participation in, management and direction of business enterprise; (4) intention of parties, express or implied; and (5) fixing of salaries by joint agreement."

(emphasis supplied) Black's Law Dictionary (7th Edition, page 843) defines `joint venture' thus :

 

"Joint Venture : A business undertaking by two or more persons engaged in a single defined project. The necessary elements are : (1) an express or implied agreement; (2) a common purpose that the group intends to carry out; (3) shared profits and losses; and (4) each member's equal voice in controlling the project."

 

An illustration of joint venture may be of some assistance. An agreement between the owner of a land and a builder, for construction of apartments and sale of those of apartments so as to share the profits in a particular ratio may be a joint venture, if the agreement discloses an intent that both parties shall exercise joint control over the construction/development and be accountable to each other for their respective acts with reference to the project.

18. We may now notice the various terms in the agreement between the appellant and first respondent which militate against the same being a `joint venture'. Firstly, there is a categorical statement in clause 24, that the agreement shall not be deemed to constitute a partnership between the owner and the builder. The land-owner is specifically excluded from management and is barred from interfering with the construction in any manner (vide clause 15) and the Builder has the exclusive right to appoint the Architects, contractors and sub-contractors for the construction (vide clause 16). The Builder is entitled to sell its share of the building as it deemed fit, without reference to the land owner. (vide clauses 7 and 13). The builder undertakes to the landowner that it will construct the building within 12 months from the date of sanction of building plan and deliver the owner's share to the land owner (vide clauses 9 & 14). The Builder alone is responsible to pay penalties in respect of deviations (vide clause 12) and for payment of compensation under the Workmen's Compensation Act in case of accident (vide clause 10). Secondly, there is no community of interest or common/joint control in the management, nor sharing of profits and losses. The land owner has no control or participation in the management of the venture. The requirement of each joint venturer being the principal as well as agent of the other party is also significantly absent. We are therefore of the view that such an agreement is not a joint venture, as understood in law.

19. What then is the nature of the agreement between the appellant and the first respondent? Appellant is the owner of the land. He wants a new house, but is not able to construct a new house for himself either on account of paucity of funds or lack of expertise or resources. He, therefore, enters into an agreement with the builder. He asks the builder to construct a house and give it to him. He says that as he does not have the money to pay for the construction and will therefore permit the builder to construct and own additional floor/s as consideration. He also agrees to transfer an undivided share in the land corresponding to the additional floor/s which falls to the share of the builder. As a result, instead of being the full owner of the land with an old building, he becomes a co-owner of the land with a one-third share in the land and absolute owner of the ground floor of the newly constructed building and agrees that the builder will become the owner of the upper floors with corresponding two-third share in the land. As the cost of the undivided two-third share in the land which the land owner agrees to transfer to the builder, is more than the cost of construction of the ground floor by the builder for the landowner, it is also mutually agreed that the builder will pay the landowner an additional cash consideration of Rs.8 lakhs. The basic underlying purpose of the agreement is the construction of a house or an apartment (ground floor) in accordance with the specifications, by the builder for the owner, the consideration for such construction being the transfer of undivided share in land to the builder and grant of permission to the builder to construct two floors. Such agreement whether called as a `collaboration agreement' or a `joint-venture agreement', is not however a `joint-venture'. There is a contract for construction of an apartment or house for the appellant, in accordance with the specifications and in terms of the contract. There is a consideration for such construction, flowing from the landowner to the builder (in the form of sale of an undivided share in the land and permission to construct and own the upper floors). To adjust the value of the extent of land to be transferred, there is also payment of cash consideration by the builder. But the important aspect is the availment of services of the builder by the land-owner for a house construction (construction of owner's share of the building) for a consideration. To that extent, the land-owner is a consumer, the builder is a service-provider and if there is deficiency in service in regard to construction, the dispute raised by the land owner will be a consumer dispute. We may mention that it makes no difference for this purpose whether the collaboration agreement is for construction and delivery of one apartment or one floor to the owner or whether it is for construction and delivery of multiple apartments or more than one floor to the owner. The principle would be the same and the contract will be considered as one for house construction for consideration. The deciding factor is not the number of apartments deliverable to the land owner, but whether the agreement is in the nature of a joint-venture or whether the agreement is basically for construction of certain area for the land-owner.

20. It is however true that where the contract is a true joint venture the scope of which has been pointed out in para 17 above, the position will be different. In a true joint venture agreement between the land-owner and another (whether a recognized builder or fund provider), the land-owner is a true partner or co-adventurer in the venture where the land owner has a say or control in the construction and participates in the business and management of the joint venture, and has a share in the profit/loss of the venture. In such a case, the land owner is not a consumer nor is the other co- adventurer in the joint venture, a service provider. The land owner himself is responsible for the construction as a co-adventurer in the venture. But such true joint ventures are comparatively rare. What is more prevalent are agreements of the nature found in this case, which are a hybrid agreement for construction for consideration and sale and are pseudo joint-ventures. Normally a professional builder who develops properties of others is not interested in sharing the control and management of the business or the control over the construction with the land owners. Except assuring the land owner a certain constructed area and/or certain cash consideration, the builder ensures absolute control in himself, only assuring the quality of construction and compliance with the requirements of local and municipal laws, and undertaking to deliver the owners' constructed area of the building with all certificates, clearances and approvals to the land owner.

21. Learned counsel for the respondent contended that the agreement was titled as "collaboration agreement" which shows an intention to collaborate and therefore it is a joint venture. It is now well settled that the title or caption or the nomenclature of the instrument/document is not determinative of the nature and character of the instrument/document, though the name may usually give some indication of the nature of the document. The nature and true purpose of a document has to be determined with reference to the terms of the document, which express the intention of the parties. Therefore, the use of the words `joint venture' or `collaboration' in the title of an agreement or even in the body of the agreement will not make the transaction a joint venture, if there are no provisions for shared control of interest or enterprise and shared liability for losses.

22. The State Commission and National Commission have proceeded on an assumption, which appears to be clearly baseless, that wherever there is an agreement for development of a property between the property owner and builder under which the constructed area is to be divided, it would automatically amount to a joint venture and there is no question of the landholder availing the service of the builder for consideration. Reliance was placed on two decisions, the first being that of the National Commission in C Narasimha Rao v. K R Neelakandan - I (1994) CPJ 160 and the second being that of the Delhi State Commission in Har Sarup Gupta v. M/s. Kailash Nath & Associates - II (1995) CPJ 275. In C Narasimha Rao, there was an agreement between the landowners and a builder for construction of a building and sharing of the constructed area. The old building was demolished, but the builder failed to complete the construction of a new building and hand over the owner's share of flats. The landowners preferred a complaint claiming Rs.94,000/- as the value of the malba (retrievable valuables from the debris of the old building) that had been removed by the builder. The National Commission held that as the claim was for recovery of the money being value of the malba removed by the builder, it does not amount to a claim based on deficiency of service and therefore such a claim would fall outside the scope of the Consumer Protection Act. The said decision is wholly inapplicable, as it dealt with a different question. In Har Swarup Gupta, the State Commission was concerned with a claim of the landowners for compensation alleging that the builder had not built the flats in terms of the contract under which the landowners were entitled to 36% and the builder was entitled to 64% of the built up area. The State Commission held that the complaint was not maintainable on the ground that on similar facts the National Commission in Narasimha Rao's case (supra) had held that the fora under the Consumer Protection Act did not have jurisdiction. But Narasimha Rao (supra), as noticed above, was not similar on facts, nor did it lay down any such proposition. Har Swarup Gupta is clearly wrongly decided.

23. We may notice here that if there is a breach by the landowner of his obligations, the builder will have to approach a civil court as the landowner is not providing any service to the builder but merely undertakes certain obligations towards the builder, breach of which would furnish a cause of action for specific performance and/or damages. On the other hand, where the builder commits breach of his obligations, the owner has two options. He has the right to enforce specific performance and/or claim damages by approaching the civil court. Or he can approach the Forum under Consumer Protection Act, for relief as consumer, against the builder as a service- provider. Section 3 of the Act makes it clear that the remedy available under the Act is in addition to the normal remedy or other remedy that may be available to the complainant.

24. The District Forum, the State Commission and the National Commission committed a serious error in wrongly assuming that agreements of this nature being in the nature of joint venture are outside the scope of consumer disputes.

Re : Second Question

25. Under the agreement, the builder is required to construct the ground floor in accordance with the sanctioned plan, and specifications and the terms in the agreement and deliver the same to the owner. If the construction is part of a building which in law requires a completion certificate or C&D forms (relating to assessment), the builder is bound to provide the completion certificate or C&D forms. He is also bound to provide amenities and facilities like water, electricity and drainage in terms of the agreement. If the completion certificate and C&D forms are not being issued by the Corporation because the builder has made deviations/violations in construction, it is his duty to rectify those deviations or bring the deviations within permissible limits and secure a completion certificate and C&D forms from MCD. The builder can not say that he has constructed a ground floor and delivered it and therefore fulfilled his obligations. Nor can the builder contend that he is not bound to produce the completion certificate, but only bound to apply for completion certificate. He cannot say that he is not concerned whether the building is in accordance with the sanction plan or not, whether it fulfills the requirements of the municipal bye-laws or not, or whether there are violations or deviations. The builder cannot be permitted to avoid or escape the consequences of his illegal acts. The obligation on the part of the builder to secure a sanctioned plan and construct a building, carries with it an implied obligation to comply with the requirements of municipal and building laws and secure the mandatory permissions/certificates.

 

26. The surviving prayer is no doubt only for a direction to the builder to furnish the completion certificate and C&D forms. It is not disputed that a building of this nature requires a completion certificate and building assessment (C&D forms). The completion certificate and C&D forms will not be issued if the building constructed is contrary to the bye-laws and sanctioned plan or if the deviations are beyond the permissible compoundable limits. The agreement clearly contemplates the builder completing the construction and securing completion certificate. The agreement, in fact, refers to the possibility of deviations and provides that if there are deviations, the builder will have to pay the penalties, that is do whatever is necessary to get the same regularized. Even if such a provision for providing completion certificate or payment of penalties is not found in the agreement, the builder cannot escape the liability for securing the completion certificate and providing a copy thereof to the owner if the law requires the builder to obtain completion certificate for such a building.

 

27. A prayer for completion certificate and C&D Forms cannot be brushed aside by stating that the builder has already applied for the completion certificate or C&D Forms. If it is not issued, the builder owes a duty to make necessary application and obtain it. If it is wrongly withheld, he may have to approach the appropriate court or other forum to secure it. If it is justifiably withheld or refused, necessarily the builder will have to do whatever that is required to be done to bring the building in consonance with the sanctioned plan so that the municipal authorities can inspect and issue the completion certificate and also assess the property to tax. If the builder fails to do so, he will be liable to compensate the complainant for all loss/damage. Therefore, the assumption of the State Commission and National Commission that the obligation of the builder was discharged when he merely applied for a completion certificate is incorrect. Conclusion

28. The District Forum and National Commission did not examine the matter with reference to facts. The State Commission held that the complaint was not maintainable but purported to consider the factual question in a half-hearted and casual manner. The matter will now have to go back to District Forum for deciding the matter on merits. We, accordingly, allow this appeal as follows :

a) The orders of the National Commission, State Commission and District Forum are set aside.

b) The appellant's complaint is held to be maintainable.

c) The District Forum is directed to consider the matter on merits and dispose of the matter in accordance with law, within six months from the date of receipt of this order.

d) The respondents shall pay costs of Rs.25,000/- to the appellant.

...............................J [R. V. Raveendran] ..............................J A[Lokeshwar Singh Panta] New Delhi.  July 10, 2008 .”

 

Now in this case it has become clear that the opposite parties failed to deliver the possession of the said flat within the stipulated time.

Further regarding delay and regarding completion certificate Hon’ble Supreme Court has very well discussed in the following case law. Hon’ble Supreme Court has also discussed the one-sided agreement which is often entered into by the builder and the allottee.

In the case of Kolkata West International City Pvt. Ltd. Vs. DevasisRudra ,[Civil Appeal No. 3182 of 2019 @ SLP (C) No(S). 1795 of 2017] ;2019 Latest Case law 299 SC

Dr. Dhananjaya Y. Chandrachud, J.

“ This appeal arises from the judgment dated 21 November 2016 of the National Consumer Disputes Redressal Commission1. A Buyer's Agreement dated 2 July 2007 was entered into between the appellant and the respondent. The respondent paid an amount of Rs 39,29,280 in 2006 in terms of a letter of allotment dated 20 September 2006. The agreement between the parties envisaged that the appellant would hand over possession of a Row House to the respondent by 31 December 2008 with a grace period of a further six months ending on 30 June 2009.

 

The respondent filed a consumer complaint before the West Bengal State Consumer Disputes Redressal Commission2 in 2011 1 "NCDRC" "SCDRC" 2 praying for possession of the Row House and in the alternative for the refund of the amount paid to the developer together with interest at 12% per annum. Compensation of Rs 20 lakhs was also claimed. The SCDRC allowed the complaint by directing the appellant to refund the moneys paid by the respondent together with interest at 12% per annum and compensation of Rs 5 lakhs. The NCDRC has modified this order by reducing the compensation from Rs 5 lakhs to Rs 2 lakhs. Mr. Ravinder Narain, learned counsel appearing on behalf of the appellant submits that the primary relief which was sought in the consumer complaint was for delivery of possession. According to the appellant, the completion certificate was received on 29 March 2016, which was intimated to the respondent on 11 April 2016.

Moreover, before the SCDRC, in its written submissions, the appellant had offered possession of the Row House to the respondent. It has also been stated that in a complaint which was filed by an association representing the allottees of 161 Row houses, a settlement was arrived on 11 September 2018 before the NCDRC specifying the date on which possession would be handed over together with interest at 6% per annum instead of 4% as mentioned in the Buyers' Agreement. It was urged that the developer having made a substantial investment in terms of the agreement, a direction for refund is not warranted. It has also been urged that the SCDRC in the course of its decision erroneously observed that the developer was unable to fulfill its obligation to complete the construction within the agreed period and it was not certain when the Row house would be handed over. It was urged that this observation by the SCDRC is contrary to the record since before it, a specific offer of possession was made.”

Interestingly, where the buyer is in default, the agreement stipulates that interest at the rate of 18 per cent from the date of default until the date of payment would be charged for a period of two months, failing which the allotment would be cancelled by deducting 5% of the entire value of the property. The agreement was evidently one sided. For a default on the part of the buyer, interest at the rate of 18% was liable to be charged. However, a default on the part of the developer in handing over possession would make him liable to pay interest only at the savings bank rate prescribed by the SBI. There is merit in the submission which has been urged by the buyer that the agreement was one sided.

 

The clause which has been extracted in the earlier part of this order will not preclude the right and remedy available to the buyer to claim reasonable interest or, as the case may be, compensation. The essential aspect of the case which is required to be analysed is whether the buyer was entitled to seek a refund or was estopped from doing so, having claimed compensation as the primary relief in the consumer complaint.

 

The Buyer's Agreement is dated 2 July 2007. In terms of the agreement, the date for handing over possession was 31 December 2008, with a grace period of six months. Even in 2011, when the buyer filed a consumer complaint, he was ready and willing to accept possession. It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the developer, the completion certificate was received on 29 March 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period.

 

A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund. In the circumstances, we are of the view that the orders passed by the SCDRC and by the NCDRC for refund of moneys were justified. Having regard to all the facts and circumstances of the case, we modify the order of the NCDRC by directing that the appellant shall pay interest at the rate of 9% per annum to the respondent instead and in place of 12% as directed by the NCDRC. Save and except for the above modification, we affirm the directions of the NCDRC. ”

 

So it is clear that such type of agreement which is one sided cannot be binding on the consumer. When the consumer is in default you will charge exorbitant rate of interest and when you, the builder, is in default you provide a meagre amount of damage to the consumer. Therefore such an agreement cannot be considered as a true agreement or contract in the parties. Now we come to the present case. It is clear that the opposite party failed to provide the possession of the flat within stipulated time that is on or before 24.04.2010. For the convenience of calculation of the damages and interest we take the cut-off date as 01.05.2010. Now we have to see the compensation, loss of rent due to non-delivery of possession and rate of interest on the deposited amount by way of judgement delivered by Hon’ble Supreme Court and Hon’ble NCDRC.

 

Ghaziabad Development Authority v. Balbir Singh

In the Supreme Court of India

 

Name of the Case  

Ghaziabad Development Authority v.

Balbir Singh

Citation  

(2004) 4 SCC 65

Year of the Case  

2004

Petitioner  

Ghaziabad Development Authority   

Respondent  

Balbir Singh

Bench/Judges  

Justice H. K. Sema Justice S.N. Variava

Acts Involved  

  Consumer Protection Act, 1986  

Important Sections    

Section 14 of the Consumer Protection

 Act, 1986 Section 22 of the

Consumer Protection Act, 1986  

The case of Ghaziabad Development Authority v Balbir Singh is a landmark decision that laid down certain judicial standards regarding the grounds on which compensation may be awarded, particularly, in matters of allotment of flats/plots by land development authorities. Compensation under consumer protection laws is required to recompense for loss or injury suffered by consumers, and therefore, the quantum of compensation to be awarded would necessarily have to be determined based on the facts and circumstances of each case. This decision set an established precedent on the issue of compensation to be awarded in consumer disputes, and its principles have been relied upon in numerous subsequent cases.

Introduction

The consumer protection laws establish a redressal mechanism whereby consumers can claim monetary reliefs for defective goods, deficiency in service, and unfair trade practices. Sections 14 and 22 of the Consumer Protection Act, 1986 empower the District, State, and National Consumer Disputes Redressal Commission to “to pay such amount as may be awarded by it as compensation to the consumer for any loss or injury suffered by the consumer due to the negligence of the opposite party”. Such monetary reliefs i.e., compensation awarded would have to be based on the facts and circumstances of each case, since the loss and injury suffered would vary. Given the absence of a straight-jacket formula for the determination of the amount of compensation to be awarded in each case, it follows that there can be no uniformity in the award of compensation.

It is for the Consumer Forum to grant compensation to the extent it finds it reasonable, fair, and proper in the facts and circumstances of a given case according to the established judicial standards where the claimant can establish his charge.Ghaziabad Development Authority v Balbir Singh

Background and Facts of the Case

The present case of Ghaziabad Development Authority v Balbir Singh arose out of an appeal directed against the judgment and award passed by the National Consumer Disputes Redressal Commission (NCDRC) awarding an interest @ 18% per annum. The Commission was considering a bunch of matters, the lead being the case of Haryana Urban Development Authority vs. Darsh Kumar, where it held that in cases of deficiency of service by development authorities, the rate of interest awarded must be 18% per annum. Following this, the Commission disposed of subsequent matters by its preceding award. Numerous appeals were filed before the Supreme Court against the decision of the Commission in various cases, primarily against its award of 18% interest.

Since the Supreme Court was considering a wide number of matters relating to allotment of land by development authorities, the facts of each case vary. In some cases, the scheme had gotten canceled after the payment of monies and allotment of flats/plots. Delivery of possession of the flats was therefore refused to the allottees. In some cases, either possession was offered at an increased rate at a much later date possession or was offered but not taken by the party. Possession was not delivered in some cases despite payment of monies and no refusal to deliver possession. In some cases, the construction was of sub-standard quality or it was incomplete, or the authority demanded extra amounts from the party which was paid only by some. In some cases, allotments were made and possession offered of flats/land which was encumbered or occupied by some other party

The appeal in the Supreme Court was filed due to the Commission granting interest at the rate of 18% per annum irrespective of the type of case or amount of delay and without even going into the facts of the case. Complainants had asked for the refund of amounts wrongly collected and in other cases, asked for a refund of the amounts paid.

Issues Involved

  1. Whether the grant of interest at the rate of 18% per annum by the National Consumer Disputes Redressal Commission in all cases is justifiable?

Related Provisions

Section 14 of the Consumer Protection Act, 1986

Section 22 of the Consumer Protection Act, 1986

Related Cases

The Supreme Court relied upon the case of Lucknow Development Authority v. M. K. Gupta

The Court relied upon the English case Geddis v. Proprietors of Bann ReservoirCompensation has not been defined in the Act. According to the dictionary, it means, ‘compensating or being compensated; thing given as recompense;’. In a legal sense, it may constitute actual loss or expected loss and may extend to physical mental or even emotional suffering, insult or injury or loss.”

 

 

Judgment

The Supreme Court, at the outset, reiterated the position taken in the case of Lucknow Development Authority v. M.K. Gupta, and held that “the Consumer Protection Act has a wide reach and the Commission has jurisdiction even in cases of service rendered by statutory and public authorities”. It further held that the power of the NCDRC extends to awarding compensation to consumers for misfeasance in the public office i.e. an act which is oppressive or capricious or arbitrary or negligent provided loss or injury is suffered by a citizen. Therefore, it upheld the appeals filed before it to the extent that it confirmed the jurisdiction of the NCDRC to award compensation in cases of service rendered by statutory & public authorities (the land development authorities in the present case).

As to the issue of whether the grant of interest at the rate of 18% per annum by the NCDRC in all cases is justifiable, the Supreme Court held in the negative. It stated that “the power to and duty to award compensation does not mean that irrespective of facts of the case compensation can be awarded in all matters at a uniform rate of 18% per annum.” It held it to be unsustainable. The Court further stated that the “Award of compensation must be under different separate heads and must vary from case to case depending on the facts of each case.” The purpose of awarding compensation is to recompense for a loss or injury suffered and such compensation would therefore be proportional to the amount of loss and injury.

While considering the compensation to be awarded to the consumers in cases of deficiency of service by Development Authorities, the Court laid down a range of principles for the determination of the amount of compensation, summarised below:

 

The Court held that “such compensation has to be worked out after looking into the facts of each case and after determining what is the amount of harassment/loss which has been caused to the consumer.”

Awarding of Compensation in the Event of Deficiency in Service Rendered

The consumer protection laws have a wide reach and the consumers are entitled to receive compensation for deficiency in services rendered by statutory and public authorities. The Consumer Commissions have been vested with the jurisdiction to award the value of goods or services and compensation. On being satisfied that a complainant is entitled to compensation for loss or injury or harassment or mental agony or oppression, it must direct the authority to pay compensation. A wide discretion has been given to determine the quantum of compensation for any loss or damage suffered by a consumer, to redress any injustice. However, it is a well-established principle that the computation of compensation has to be fair, reasonable, and must reconcile with the loss or injury suffered. The Consumer Forum is cast with the duty to take into account all relevant factors for arriving at the compensation to be paid.

This landmark decision has set a precedent on the matter of compensation to be awarded in matters relating to allotment of land by development authorities and has been relied upon in many subsequent cases of the Supreme Court. In the case of H. P. Housing Board v Varinder Kumar GargGhaziabad Development Authority vs. Balbir Singh in future cases.

Conclusion

This landmark decision laid down rudimentary principles and set judicial standards concerning the awarding of compensation and the determination of the quantum of compensation to be awarded. It struck down the mechanical application of a fixed rate of interest at 18% per annum by the National Commission in numerous cases, asserting that there can be no hard and fast rule.

The principles enunciated go a long way in ensuring that consumers are compensated appropriately and proportionally for the loss and injury suffered. This decision has further strengthened the consumer protection laws by bringing clarity to how the consumer is required to award compensation. 

References


In a latest case, on Supreme Court in Petition(s) for Special Leave to Appeal (C) No(s). 24059/2022 (Arising out of impugned final judgment and order dated 19-09-2022 in RP No. 1187/2022 passed by the National Consumers Disputes Redressal Commission, New Delhi) MEERUT DEVELOPMENT AUTHORITY  VERSUS SURESH CHAND GARG (s) (FOR ADMISSION and IA No.202401/2022-EXEMPTION FROM FILING O.T. ) Date: 05-01-2023 This petition was called on for hearing today.

Held

“We have heard learned counsel for the petitioner and find that the order passed by the Consumer Commission was reasonable and there was no reason of filing appeal/revision against the substantive order passed on the consumer complaint by the District Consumer Commission dated 06.09.2019. Consequently, the present petition is disposed of with a direction, to sum up the litigation which is pending for a long time, that let the order of the District Consumer Commission dated 06.09.2019 shall be complied with and the respondent be refunded the entire deposit with simple interest at the rate of 12% per annum within a further period of 60 days from today, failing which it shall carry interest at the rate of 15% per annum until actual payment.”

 

So the Hon’ble Supreme Court has specifically said that the rate of interest shall be 12% if paid within 60 days from the date of judgment otherwise the rate of interest will be 15% per annum until actual payment. In the present case we have taken the cut of date as 01.05.2010. No we perused the different judgment as mentioned here in above regarding the payment of rent, compensation et cetera, it is clear that the possession has been given to the complainant but in absence of the CC and OC it is not a possession in the of law. Therefore the compensation, damages, interest and other reliefs shall be given to the complainant from cut of date till the date when the copy of Completion Certificate/Occupation Certificate and NOCs from different department be provided to the complainant.

 

Now it has become clear that the opposite parties failed to provide the possession in the promised period. Now we have to see how much compensation and what will be the rate of interest which the opposite parties are liable to pay to the complainant. 

 

 

In  the  case  of   PRIYANKA MITTAL & ANR. V. PARSVNATH DEVELOPERS LTD. & ANR. (NCDRC).These appeals arise out of single order of State Commission, hence, decided by common order. These appeals have been filed against the order dated 25.2.2015 in Complaint Nos. 18 of 2013- Nalin Bhargava &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 34 of 2013- Jasleen Viswanathan &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 58 of 2011- Janmejai Mani Tiwari Vs. Parsvnath Developers Ltd. &Anr.; 68 of 2013- Indu Singh Vs. Parsvnath Developers Ltd. &Anr.; 69 of 2013- Poonam Sagar Vs. Parsvnath Developers Ltd. &Anr.; 86 of 2010- Priyanka Mittal &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 101 of 2011- Mohd. Aslam Khan &Anr. Vs. ParsvnathDevelopersLtd. &Anr.; 130 of 2012- Dr. Sunil Kr. Singh &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 49 of 2012- Neera Mittal &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 74 of 2011- Deepak Bhalla Vs. Parsvnath Developers Ltd. &Anr.; 87 of 2010- Syed Gufran Ali Alvi&Anr. Vs. Parsvnath Developers Ltd. &Anr.; 96 of 2011- Uppasana Malik Vs. Parsvnath Developers Ltd. &Anr.; 175 of 20130- Umesh Chandra Dixit &Anr. Vs. Parsvnath Developers Ltd. &Anr.; 97 of 2011- Pravin Kumar Goel &Anr. Vs. Parsvnath Developers Ltd. &Anr. which complaints were partly allowed.

          The  Hon’ble  NCDRC  held that:

“Brief facts of the cases are that opposite parties/respondents are engaged in the activity of housing construction and accordingly they have launched a project named as Parsvnath Planet situated in Gomti Nagar, Lucknow. The project was demonstrated to be very lucrative and made attractive to the vendees, in order to procure/collect money from the needy persons demonstrating themselves to be excellence in the field of construction activity as compared to other builders and assured the buyers/complainants that it has been duly approved by the Lucknow Development Authority and necessary permission has also been obtained from them. The emphasis was made by the opposite parties that the possession of the Unit shall be given within a scheduled period of 36+6=42 months stipulated in agreements executed in between the parties for the project launched in the year 2006. The complainants/appellants attracted by the promise and assurance of the opposite parties, somehow managed and arranged the money from their personal sources as well as on loan at attractive rate of interest and the hard earned money was paid by them to the opposite parties in a hope that the possession of the units shall be provided to them in the year 2009 and they can leave peacefully in their own houses, since the complainants are living in rented houses. 

The complainants visited the construction site of the opposite parties after depositing the entire amount, where it was revealed that the construction activities were on halt and the persons available on the site told the complainants that the apartments are likely to be completed till 2015. Even the partial construction done by the opposite parties was defective and did not match the specifications provided in the agreement. The complainants were shocked on hearing it and observing the site. The complainants immediately contacted the Area Manager, who told the complainants that there is some delay in the construction of the apartment and the apartments shall be ready till June, 2010. The complainants have to repay the amount taken on loan alongwith interest without getting the possession of the allotted units causing irreparable loss and injury to them. The complainants have come to know that the opposite parties have invested the funds earmarked for this project into their other projects in other city due to which they have not been able to complete the project in time. Besides this, it has also come to the light that although the opposite parties had collected huge funds from the buyers but in spite of that the opposite parties have miserably failed to pay the dues of Lucknow Development Authority which forced the Lucknow Development Authority to issue coercive measures against the opposite parties for therecovery of their dues. Alleging deficiency on the part of opposite parties/ respondents, complainants filed separate complaints before State Commission. Aggrieved  by  the  order  of  Hon’ble  State  Commission, these  appeals preferred  before Hon’ble National  Consumer  Disputes  Redressal  Commission.

 

Hon’ble  NCDRC discussed various  case  laws  and  after  hearing  the  parties held,

 

“Learned Counsel for appellants submitted that as complainants have been deprived of possession for a long period beyond agreed period, it amounts to restrictive trade practice under  and complainants are entitled to get compensation. Section 2 (nnn) runs as under:- means a trade practice which tends to bring about restrictive trade practice manipulation of price or its conditions of delivery or to affect flow of supplies in the market relating to goods or services in such a manner as to impose on the consumers unjustified costs or restrictions and shall include- Delay beyond the period agreed to by a trader in supply of such goods or in providing the services which has led or is likely to lead to rise in the price; Any trade practice which requires a consumer to buy, hire or avail of any goods, or, as the case may be, services as condition precedent to buying, hiring or availing of other goods or services; Perusal of aforesaid provision reveals that when opposite party delays in delivery of goods which leads to rise in the price of goods meaning thereby, more price is charged from complainant, it amounts to restrictive trade practice. In the case in hand, opposite party on account of delayed delivery of possession is not charging higher rate than the agreed rate for delivery of possession of flat, so, it does not fall within the purview of restrictive trade practice under 

 

“Admittedly, agreements were executed in 2006 and as per agreements, possession of flats was to be delivered within 42 months, meaning thereby, possession was to be given in the year 2009-2010 and possession has not been handed over so far though year 2016 has started. No doubt, complainants are entitled to get penalty amount for delayed delivery of possession as per clause 10(c) of the agreement but opposite party cannot be permitted to avail benefit of aforesaid clause for indefinite period. This penalty clause should be allowed for the benefit of parties for a limited period and in the cases in hand, I deem it appropriate to extend applicability of aforesaid clause for a period of one year beyond 42 months and after that, complainants are certainly entitled to compensation. Opposite party cannot be allowed to avail huge funds of complainants by paying merely Rs. 5/- per sq. ft. for example, complainants who have purchased flat measuring 164.901 sq. mtr., they have made payment of about Rs. 31.00 to 32 lakhs and in the garb of clause 10 (c), opposite party is paying penalty @ approximately Rs. 9,000/- per month against enjoying funds more than Rs. 30.00 lakhs. As complainants have been deprived to shift to their flats for a long period which would not only have given them satisfaction of living in their own house but also have raised their social status and opposite party has enjoyed funds of complainants for a long period, I deem it appropriate to allow compensation @ Rs. 15,000/- p.m. to the complainants who have applied for flats upto 175 sq. mtr and Rs. 20,000/- per month to complainants who have applied for flats above 175 sq. after 54 months of execution of agreement till delivery of possession.”

 

Against this judgment, parties went to Hon’ble  Supreme  Court. The judgment of Hon’ble  Supreme  Court is:- 

 

In  Nalin Bhargava  vs.  Parsvnath Developers Ltd. CA 6662/2018 @ SLP(C) 7596/2016 etc and other related civil appeals on 13 July, 2018, Hon’ble Supreme Court held:-

 

  “Leave granted in all the special leave petitions.CA 6662/2018 @ SLP(C) 7596/2016 etc.

 

It is submitted by Mr. M.L. Lahoty, learned counsel appearing for the appellants in all the appeals that the possession has been handed over and the deficiencies have been removed and, therefore, he has no grievance. However,

 

Mr. Lahoty would insist that there should be imposition  of  costs as compensation.

Mr. Sachin Datta, learned senior counsel appearing for the developer has raised   objections    with regard to imposition of costs.

 

Having heard learned counsel for the parties, we are of the considered opinion that the cause of justice would be best subserved if each of the appellants in the present appeals are given Rs.1,50,000/- (Rupees one lakh fifty thousand only) per flat, towards costs. When we say “cost”, we mean costs alone and nothing else.”

 

We have seen that the opposite parties have stated that this Hon’ble commission has disposed of so many cases pertaining to this project therefore they also want that this case we also disposed of in the same manner and they stated,

 

“It is stated that since the captioned complaint also pertains to the same project and apart from the basic facts of the case which differs from allottees, the broad stand of the opposite parties remains the same as was averred in the complaints already disposed by the common order/judgment, the captioned complaint be also disposed off by this Hon’ble Commission.”

 

On the one side they have requested this Hon’ble commission disposed of this petition in the light of the previous judgements and on the other way they vehemently denied all the averments of the complainant and stated that complainant should be dismissed. What the opposite parties want? They are serving two masters ! From the date of judgement passed in similar matters by this commission, many case laws have come into existence and now the scenario has changed and that judgement cannot be applied here.

 

These builders are just earning money from the consumers to whom they issued allotment letters and got a huge amount. They keep this amount for a long time and earn interest on it. Property dealing is that part of business where they never pay a penny to the consumers on their amounts deposited for a long-term or if they pay, they pay a meagre interest of about 5% or so but they charge 18 to 24% or more if the consumers default in depositing any instalment. It reminds us the story of “The Merchant of Venice” The Merchant of Venice is the story of a Jewish money lender Shylock who demands that an antisemitic Christian offer “a pound of flesh” as collateral against a loan. These acts of builders also remind us the age of  Sahukari during ancient India and also during British Raj. Whether these builders have power to frame their own law? They put their terms and conditions in such a way that the sufferer will always be the consumer. The Consumer Protection Act 1986 and 2019 have been enacted for the benefits of consumers,  so the courts dealing with Consumer Protection Act 1986 and 2019 should come forward for their rescue. The courts are not governed by the dictate of the builders as such they are governed by the law, Custom and Usages.

 

We know that the builders usually exploit the consumers in many ways. The following article shows the ways by which these multimillionaire builders exploit the innocent consumers/buyers.

 

Exploitation – A person who has been deceived in any way (like fraud, misrepresentation, coercion, fake information)or by any person, is said to be exploited.

Forms of Consumer Exploitation

1. Fake Advertisement

Whatever is shown and disclosed through advertisements about the product and service, is not completely true. The quality of the product and its durability is not always perfect and long-lasting. The way it is shown only attracts the customers and compels the people to buy it. Non-disclosure of reality is a disadvantage.

2. Substandard Products

Every business aims to earn profit and in order to gain profit, they tend to sell inferior quality products which may cause harm. This practice is also unethical.

3. High Price

Sellers those who have a monopoly of the products and have the control to change the price, take unfair advantage of charging the high prices of the products, and people are left with no choice.

4. Adulteration

This is the worst forms of consumer exploitation. It not only causes monetary loss but also affects the health of a person. The unwanted materials are mixed in the food items which harms the body and may result in different types of diseases.

5. Under Measurement

The quantity printed in the packet is not always accurate. Also, the material which is measured while purchasing is not correct. Sometimes, sellers sell under measured goods and ask for the original quantity price.

6. Black Marketing

When there is a high demand for a certain product, sellers start stocking the product and they will pretend that there is a scarcity of the product due to which the price will be increased and people will buy it because they need it. This happens especially for essential commodities.

For instance, the increase in the price of tomatoes in the market but in reality, they were stored in the warehouse. This is an essential commodity and people have to buy it. Earlier, tomatoes were sold at Rs. 20/- per kg but later on the price was increased to Rs. 80/-. This is hoarding and black marketing.

7. Duplicate Goods

Many sellers sell the goods in the name of branded goods. They change the quality and material and puts the name and logo of different brands. This is misrepresentation and unethical to practice in business.

8. Lack of after Sale Service

A seller has the duty and responsibility towards customer providing after-sale service. Manufacturing and selling are not the only activity to be performed, if any customer faces any kind of problem after using the product, then the problems must be heard and shall be solved.

9. Lack of Information

The ingredients used, manufacturing date, harm, and consequence of the product, etc. are the information that should be disclosed to the customers otherwise they might face problems that will leave a negative impact on the market.

 

 

Now we come to the conclusion that the complainant is entitled for the following reliefs.

 

As far as the building construction is concerned, the builders first promised to construct a beautiful well furnished flat within the promised period of about three years and they allured the consumer to invest their money to get a flat allotted  in the said project. So many projects are launched simultaneously by the same builder and thereafter the builder work only one project and the rest projects are left in the dustbin. These projects serve the buildersto earn huge interest on the money deposited by the allottees. They never deliver the possession of the flat as stipulated in the flat buyer agreement. This results in withdrawal of many consumers from the project and on their withdrawal, the builders deduct a huge amount deposited fund by the allottees ,for themselves in the name of voluntary withdrawal. Some allottees wait for their turn which comes after many years. They invested their savings and also sometimes take a loan from the various banking agencies or insurance companies to fulfil their dream project but in vain.

 

In the present case the complainant purchased the said flat from the previous owner with a hope to get it in the promised period of three years which has already been expired before 01.11.2014 and still today he did not get the possession of his allotted flat. From the cut of date about nine years have passed and the flat is still not fully completed/finished/furnished. The opposite parties did not tell a word about the different No Objection Certificates of fire department, civil aviation department, pollution control Department et cetera. Nothing has been said about the completion certificate and occupancy certificate which are necessary before giving possession of the flat to the allottee. After going through all the evidences and documents on record, it is clear that the opposite parties failed to provide the said flat in the stipulated time. So opposite parties are liable to deliver the possession of the flat alongwith completion certificate, occupancy certificate, NOC’s of fire department, civil aviation department, pollution control Department et cetera, liable to pay compensation, damages, cost of the suit, loss of rent, et cetera et cetera.

 

So in this case we are of the opinion that the complainant is entitled for the following reliefs:

 

The complainant is entitled to get the possession of his fully furnished/finished flat/residential unit no.C1-201 ,Sushant Jeevan Enclave measuring 1706 square ft from the opposite parties within a period of 60 days from the date of judgement of this complaint case along with the completion certificate, occupancy certificate, NOC’s of fire department, civil aviation department, pollution control Department/Board etc. and the opposite parties shall not charge a single penny under whatsoever head it may be from the complainant and if the area of the said unit is found less than whatever is agreed, the proportionate cost shall be decreased and the excess amount charged be refunded.

 

                                      IN ALTERNATE

 

The complainant is entitled to get Rs.70 lakhs from the opposite parties in addition to the amount deposited by the complainant with the opposite parties, within 60 days from the date of judgement of this complaint case otherwise after 60 days the opposite parties will pay Rs.1 lakh per month till the final payment.

 

 

The complainant is entitled to the interest at a rate of 12% per annum from the respective date of their deposits if paid within 60 days from the date of judgment of this complaint case otherwise the rate of interest shall be 15% per month after 60 days from their respective date of deposits  till the date of actual payment.

 

The complainant is entitled to Rs.15,000 per month from 01.01.2014 towards loss of rent with interest at a rate of 12% per annum from 01.01.2014 which will be paid within 60 days from the date of judgment of this complaint case otherwise the rate of interest shall be 15% per annum from 01.01.2014 till the date of actual payment in the light of Priyanka Mittal case (Hon’ble NCDRC) and Meerut Development Authority case (Hon’ble Supreme Court judgment regarding rate of interest).

 

The complainant is entitled to get Rs.2 lakhs from the opposite parties towards cost of the case, if paid within 60 days from the date of judgment of this complaint case otherwise the rate of interest shall be paid @15% per annum on the said amount which shall be paid from 01.11.2014 till the date of actual payment.

 

The complainant is entitled to get the damages of Rs.1.5 lakhs in view of the decision of the Hon’ble Supreme Court.

 

The complainant is entitled to get Rs.30 lakhs from the opposite parties towards delay, harassment, mental agony, anxiety with interest at a rate of per person per annum from 01.11.2014 if paid within 60 days from the date of judgment of this complaint case otherwise the rate of interest shall be 15% per annum which shall be paid from 01.11.2014 till the date of actual payment.

 

Except this complaint case, there are two miscellaneous cases, Miscellaneous case  no.346/2022 and Miscellaneous case no.137/ 2023 against the opposite parties. As the judgement is being delivered in this complaint case, both the Miscellaneous cases shall stand disposed of / dismissed.The present complaint case is decided accordingly.

 

 

 

ORDER

 

  1. The opposite parties no.1 & 2 are directed jointly and severally to hand over the possession of the fully furnished and finished flat, as per the specification of the brochure on record, flat/residential unit to C1-201 ,Sushant Jeevan Enclave measuring 1706 square ft to the complainant and toexecute the sale deed within a period of 30 days from the date of judgement of this complaint case along with the completion certificate, occupancy certificate, NOC’s of fire department, civil aviation department, pollution control Department et cetera, and the opposite parties shall not charge a single penny whatsoever head it may be from the complainant and if the area of the said plot is found less than the agreed area, the proportionate cost shall be decreased.

 

IN ALTERNATE

 

The opposite parties no.1 & 2 are directed jointly and severally to pay Rs.70 lakhs to the complainant in addition to the amount deposited by the complainant with the opposite parties, within 60 days from the date of judgment of this complaint case otherwise after 60 days the opposite parties shall pay Rs.1 lakh per month till the date of actualpayment.

 

  1. The opposite parties no.1 & 2 are directed jointly and severally to pay interest to the complainant at a rate of 12% per annum from the respective date of deposits made by the complainant, if paid within 60 days from the date of judgment of this complaint case otherwise the rate of interest shall be 15% per month after 60 days from the date of judgement of this complaint case from the respective dates of deposits, till the date of actual payment.

 

  1. The opposite parties no.1 & 2 are directed jointly and severally to pay to the complainant Rs.15,000 per month from 01.01.2014 towards loss of rent with interest at a rate of 12% per annum from 01.01.2014 if paid within 60 days from the date of judgment of this complaint case otherwise the rate of interest shall be 15% per annum from 01.01.2014 till the date of actual payment in the light of Priyanka Mittal case (Hon’ble NCDRC) and Meerut Development Authority case (Hon’ble Supreme Court judgment regarding rate of interest).

 

  1. The opposite parties no.1 & 2 are directed jointly and severally to pay to the complainant  Rs.2 lakhs towards cost of the case with interest at a rate of 12% from 01.11.2014 if paid within 60 days from the date of judgment of this complaint case otherwise the rate of interest shall be 15% per annum which shall be paid from 01.11.2014 till the date of actual payment.

 

  1. The opposite parties no.1 & 2 are directed jointly and severally to pay to the complainant Rs.1.5 lakhs towards damages  inview of the Hon’ble Supreme Court.

 

  1. The opposite parties no 1 & 2 are directed jointly and severally to pay to the complainant Rs.30 lakhs towards delay, harassment, mental agony, anxiety with interest at a rate 12% per annum from 01.11.2014, if paid within 60 days from the date of judgment of this complaint case otherwise the rate of interest shall be 15% per annum which shall be paid from 01.11.2014 till the date of actual payment.

 

  1. The opposite party no.3 shall be first charge on this amount up to the extent of unpaid balance of the loan, payable by the complainant, if not paid by the complainant after submitting the calculation sheet jointly with complainant within 60 days from the date of judgment of this complaint case.

 

  1.  If the order is not complied with, within 60 days from the date of judgment of this complaint case, the complainant shall be free to file execution against the opposite parties no.1 & 2 at the cost of opposite parties no.1 & 2 .

 

  1. Both the Miscellaneous cases, Miscellaneous case  no. 346/2022 and Miscellaneous case no.137/2023 against the opposite parties are dismissed.

 

  1. The stenographer is requested to upload this order on the Website of this Commission today itself.

11.      Certified copy of this judgment be provided to the parties as per rules. 

 

 

(Justice Ashok Kumar)(Sushil Kumar)

  •  

 

Judgment dated/typed signed by us and pronounced in the open court. Consign to the Record Room.

 

 

(Justice Ashok Kumar)(Sushil Kumar)

  •  
  •  

Jafri, PA I

Court 1

 

 

  •  

 

 

 
 
[HON'BLE MR. JUSTICE ASHOK KUMAR]
PRESIDENT
 
 
[HON'BLE MR. SUSHIL KUMAR]
JUDICIAL MEMBER
 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.