Circuit Bench Nagpur

StateCommission

A/18/148

PUNJAB NATIONAL BANK - Complainant(s)

Versus

ABDUL RASHID S/O SHEIKH ABDULLA - Opp.Party(s)

ADV.F.I.KHAN

12 Oct 2018

ORDER

STATE CONSUMER DISPUTES REDRESSAL COMMISSION
MAHARASHTRA NAGPUR CIRCUIT BENCH
NAGPUR
 
First Appeal No. A/18/148
( Date of Filing : 05 Apr 2018 )
(Arisen out of Order Dated 30/11/2017 in Case No. RBT/CC/11/804 of District Additional DCF, Nagpur)
 
1. PUNJAB NATIONAL BANK
THROUGH ITS MANAGER GANDHIBAG BRANCH C A ROAD NAGPUR
NAGPUR
MAHARASHTRA
...........Appellant(s)
Versus
1. ABDUL RASHID S/O SHEIKH ABDULLA
R/O SATRANJIPURA MAL DHAKKA NO 1 ITWARI NAGPUR
NAGPUR
MAHARASHTRA
...........Respondent(s)
 
BEFORE: 
 HON'BLE MR. B.A.SHAIKH PRESIDING MEMBER
 HON'BLE MR. S B SAWARKAR MEMBER
 
For the Appellant:
For the Respondent:
Dated : 12 Oct 2018
Final Order / Judgement

(Delivered on 12/10/2018)

PER SHRI B.A. SHAIKH, HON’BLE PRESIDING MEMBER.

1.      Advocate Mr. F.I. Khan is present for the appellant. Adv. Mr. Mushahid Ali is present for the respondent.  The appeal is listed today  for hearing on delay condonation  application filed by the appellant along with appeal memo.  The delay shown in the application  is of  75 days  that occurred in filing of appeal.  We have heard  aforesaid advocates  on the  said  application and perused the entire record and proceedings of  appeal.

2.      The learned advocate of the appellant initially made a submission that the appellant  has got a very good case on merit and he tried to show certain evidence  adduced before the Forum in support of his submission. He further submitted that  otherwise also the appellant is a Nationalized  bank and public money is  involved in the mater and  no prejudice will be caused to the respondent  if delay  of 75 is condoned by this Commission.

3.      He explained  the delay  in brief  is an under.

          The copy of the impugned order  was received on 12/12/2017 by the appellant’s Counsel. The counsel  was preoccupied in other  matter  & hence, he could not scrutinize the judgment.  Latter  on he supplied the  copy of  judgment  to the appellant bank in  the first  week of January-2018. The bank then forwarded the same  to the  Circle Office. The Circle Officer asked for entire record for scrutiny. The same was  provided by the counsel to the bank. Since,  several issues were involved in the  matter  the bank took some time to verify the genuineness of the complaint  once again.  However,  later on  it came to the conclusion that the judgment  needs to be  challenged by filling appeal before this Commission.  Thereafter, in the second week of March 2018 the counsel was informed to prepare the appeal memo.  The counsel for the appellant  prepared the appeal memo and  sent it to the bank.  The same  was sent by the bank to the legal department  who suggested certain changes in it.  After incorporating the necessary changes  the  appeal memo was ready on 23/03/2018. There was holiday on 24/03/2018 and 25/03/2018 and on 26/03/2018 the demand draft  required for filing of appeal was prepared and  the appeal was filed on 27/03/2018 and  thus in that process the delay of 75 days  has been occurred.

4.      The learned advocate of the appellant  therefore submitted that  as the  delay is satisfactorily explained  as above and as  public money is involved  in the matter, the said delay may be condoned. He relied  on the  decision  of the Hon’ble Supreme Court in the case of Collector, Land Acquisition, Anantnag and another  Vs.  Mst. Katiji and others, reported in AIR 1987 Supreme Court 1353.  The learned advocate of the appellant  referred to the observations made in para No. 3 of the  said judgment, which is to the following effect:

i.       Ordinarily a litigant does not stand to benefit by lodging an appeal late.

ii.       Refusing to condone delay can result in a meritorious matter being  thrown  out at the very threshold and cause of justice being  defeated. As  against  this when delay is condoned  the highest that can happen is that a cause would be decided on merits after hearing the parties.

iii.      “Every day’s delay must be explained”  does not mean that a pedantic approach  should be made. Why not every  hour’s delay, every second delay? The doctrine must be applied in a rational common sense pragmatic manner.

iv.      When  substantial justice and technical considerations are pitted against each other, cause of substantial justice deserves to be preferred for the other side cannot claim to have vested right  in injustice being done  because of a non-deliberate delay.

v.       There is no presumption that delay is occasioned deliberately, or on account of culpable  negligence, or on account of mala fides. A litigant does not stand to benefit by resorting to delay. In  fact he runs a serious risk.

vi.      It must be grasped that judiciary is respected not on account of  its power  to legalize injustice on technical grounds but because it is capable of removing  injustice  and is expected to do so.”   

5.      The learned advocate of the appellant therefore requested that the application made for condonation of delay may be granted.  He also to brought to  our notice the entire awarded amount.

6.      On the other hand, the learned advocate of the respondent opposed the application by filing reply.  His submission in brief is as under,

          The appellant has got no good case on merit. The circumstances and the facts brought on record which support case of the respondent.  The  indecisiveness for long time either to file or not file the appeal is no ground for condonation of delay.  The delay of 75 days is not satisfactorily explained by the appellant and hence, it cannot be condoned.  The appellant had obtained  the expert report before the Forum in support of his case and thus the Forum passed well reasoned order in favour  of the respondent.  Hence, application may be rejected.

7.      So far as the question of merit is concerned at this stage while considering the application made for condonation of delay  it is suffice to say that  the appellant  has got no good case on merit  since the Forum below  has  properly  considered the evidence  of both  parties  and passed the correct  impugned order.  Therefore, we find that  as the appellant  has  got  no  good case on merit, the delay  of 75 days  on that ground  cannot be condoned.

8.      Thus delay is of 75 days  that occurred  in filing of appeal.  We find that  no such  delay of 75 days  can occur  simply  for  taking approval from  higher  authority  for the purpose of filing of appeal during  those days of working  on modern technology.  It is not stated in  the application  as to on  which  date the copy of impugned order was sent  by advocate of the appellant to the appellant  and on which  date  same was forwarded to the Circle Office and on which  date  the appellant–bank came to the decision  for filing of appeal.  The first date is mentioned as 12/12/2017 on which the copy of impugned order was received and last date is mentioned as the second week of March 2018 only to prepare the appeal memo. Thus no specific explanation is given for the delay from 12/12/2017 till the second week of March-2018.

9.      The aforesaid  decision  relied on by the learned advocate of the appellant  also shows that  the  treatment  similar  to any other  litigant ought to be accorded  to State Government  &  step motherly treatment  to State Government  in such matter  is not warranted.

10.    In the instant case it is seen that  the specific period  is provided under the Consumer Protection Act,1986 for disposal of appeal  filed under the said Act. The Hon’ble Supreme Court in the case of case of Anshul Aggarawal Vs. New Okhla Industrial Development Authority, (2011) 14 SCC 578, has  very specifically observed that as Consumer Protection Act specifies the period of limitation, object of expeditious adjudication of consumer disputes would be defeated if belated petitions are entertained.  Therefore, the Hon’ble Supreme Court refused to condone the delay  in that case.

11.    We find that the aforesaid decision in the case of Anshul Agrawal, is squarely applicable to the facts and circumstances of the present case.  We also find that the delay of 75 days is not properly explained by the appellant.  We are of the considered view that the appellant could have avoided  the said delay of 75 days, had   the appellant diligent and active in taking the prompt  steps for filing of appeal.  We also find that the delay of 75 days has been occurred because of  gross negligence and inaction on   the part of the appellant. Hence, the aforesaid decision in the case of  Collector  Land Acquisition, Anantnag relied on by the learned advocate of the appellant is not applicable to the facts and circumstances of the present case. Thus, for the foregoing  reasons the application made for condonation of delay deserves to be rejected. 

ORDER

i.        The application  made for condonation of delay is rejected.

ii.       The appeal is dismissed as time barred.

iii.      No order as to cost in appeal.

iv.      Copy of order be furnished to both the parties, free of cost. 

 
 
[HON'BLE MR. B.A.SHAIKH]
PRESIDING MEMBER
 
[HON'BLE MR. S B SAWARKAR]
MEMBER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.