BEFORE THE A.P.STATE CONSUMER DISPUTES REDRESSAL COMMISSION AT HYDERABAD.
CC 48 of 2012
Between:
M/s. B. Girjijapathi Reddy & Company
D.No. 24/383-21D, Sujathamma Colony
Dargamitta, Nellore-524 003
Rep. by Managing Director
B. Umapathy Reddy. *** Complainant
And
1) M/s. Bajaj Allianz General Insurance Company Ltd.
Regional Office : Far East Plaza
D.No. 3-6-111/8, Street No. 18
Main Road, Himayathnagar
Hyderabad-500 029.
Rep. by its Regional Manager
2) M/s. Bajaj Allianz General Insurance Company Ltd.
6th Floor, Block-II, White House
Begumpet, Hyderabad-500 016
Rep. by its Branch Manager. *** Opposite Parties
Counsel for the complainant: M/s. V. Gourishankara Rao
Counsel for the Ops: M/s. S. N. Padmini
CORAM:
SMT. M. SHREESHA, PRESIDING MEMBER
&
SRI S. BHUJANGA RAO, MEMBER
FRIDAY, THE TWENTY EIGTH DAY OF JUNE TWO THOUSAND THIRTEEN
ORAL ORDER: (Per Smt. M. Shreesha, Member)
***
1) The brief facts as set out in the complaint are that the complainant insured his Hitachi Hydraulic Excavator with the opposite party insurance company for a sum of Rs. 1,53,04,000/- for a period of one year commencing from 26.6.2010 to 25.6.2011 by paying premium of Rs. 3,58,497/- and a Contractors Plant & Machinery Policy was issued to the complainant. While so, on 31.10.2010 the excavator accidentally slipped and fell in the sump where the rain water was accumulated with mud while working in open cast mine at Medipally of Ramagundam in Karimnagar Dist. The complainant immediately informed the accident to the opposite party which in turn appointed one Mr. Kishore of M/s. Intech Insurance Surveyors & Loss Assessors on 9.11.2010 to inspect and estimate the damage caused to the vehicle. The surveyor inspected the excavator on 10.11.2010 and the complainant’s claim was registered for Rs. 48,89,193/- which was the amount incurred by the complainant towards repair charges. The complainant submitted all the quotations issued by the workshop to the surveyor for an amount of Rs. 56,81,013/-. The surveyor submitted his report only in August, 2011 and that Op1 sent an e-mail on 27.11.2011 asking the complainant to clarify as to why the fencing was not put around the pit. The complainant submitted a representation to Op2 demanding him to furnish a copy of the surveyor’s report but on 29.9.2011 the Op1 repudiated the claim on the ground that “the cause of loss does not fall under the purview of the policy, and that loss or damage due to electrical or mechanical breakdown, failure, breakage or derangement etc., is not covered.
2) The complainant submits that the damage caused to the excavator was neither due to electrical or mechanical breakdown or defective lubrication or lack of oil but only due to accidental fall of the excavator in the sump, and that the excavator was not operated either in rain water or in the mud. A copy of the surveyor’s report was furnished along with the repudiation letter and this showed that the surveyor assessed the gross loss at Rs. 41,45,199/- and a sum of Rs. 12,43,559/- was deducted towards depreciation at 30%, Rs. 70,000/- was deducted towards salvage, Rs. 3,52,539/- was deducted towards under insurance and also deducted 1% policy excess at Rs. 1,53,040/-. The surveyor finally assessed the net loss at Rs. 23,26,060/-. The complainant got issued a legal notice on 22.12.2011 demanding to pay Rs. 48,89,193/- for which Ops gave reply stating that proper care and caution was not taken by the operator while handling the excavator in the loose soil and that he did not stop the engine immediately and negligently tried to take out the excavator while the engine was in a running condition. The complainant denies that the operator was negligent and that the excavator operator in his statement dt. 10.11.2010 stated that while he was loading in the third shift duty, there was a sump at a distance of 5 mtrs and the said sump was almost covered with silt because of the recent rain water, and while he tried to turn the excavator track chains, because of the coal underneath, the excavator bent and sunk into the sump because of the weight of the engine. The operator’s cabin also sank. When he tried to pull the excavator with the support of the bucket by swinging the excavator, it stopped completely. The complainant submits that there is no negligence on behalf of the excavator operator and seeks directions to the opposite parties to pay the claim amount of Rs. 48,89,193/- with interest @ 18% p.a., from 31.10.2010 together with compensation of Rs. 2 lakhs and costs of Rs. 25,000/-.
3) The opposite parties filed their written version admitting the issuance of policy for the period from 26.6.2010 to 25.6.2011. They also admitted that on 31.10.2010 the complainant’s excavator was damaged for which a claim was made for Rs. 48,89,193/-. The opposite parties submit that Mr. Gopal Reddy who is the excavator operator in his statement stated that while loading when he tried to turn the truck chains, due to coal underneath the track chain, the excavator leaned into the sump, since the engine, hydraulic pump became counter weight as they were located in rear side, the excavator went into the sump and stranded in the sump up to silencer level and when he tried to swing the excavator to pull up with the bucket support the excavator self-stopped. The opposite parties submit that this itself shows that the insured was running the excavator in the mud water.
4) The complainant got the excavator repaired with M/s. Telco Construction Equipment Company Ltd. (TELCON) and filed invoices but withheld the actual information furnished by TELCON and also analysis report along with photographs which discloses the manner and parts of damage. In the service report dt. 17.5.2011 issued by the Service Engineer of TELCON discloses that when the excavator was received by them, the engine was not starting.
5) The opposite parties further submit that the inspection report reads as follows :
“It discloses that they inspected the accident spot and found the machine inside the loose mud pit towards boom side and total machine was loaded on bucket, total travel device of both sides were in the mud water and tried to crank the engine, but engine was not able to crank and found the crankshaft endplay has no play, then removed the lube oil filter, and found fine and shiny metal particles in the oil, then removed the oil pan and found heavy mud mixed with oil and copper metal flakes in the oil pan, after inspecting the same gave a specific conclusion confirming that “mud water entered from muffler and further entered inside the engine through exhaust valve and mixed with engine oil. After the incident machine was run quite some time to swing the machine to opposite side, due to mud water contamination with engine oil, engine got seized.”
The opposite party insurance company repudiated the claim on the ground that “the said loss is not falling under the purview of the policy as per the Exception (b) of the policy which reads as follows :
(b) Loss of damage due to electrical or mechanical breakdown, failure, breakage or derangement, freezing of coolant or other fluid, defective lubrication or leak of oil or coolant, but if as a consequence of such breakdown or derangement an accident occurs causing external damage, such consequential damage will be indemnifiable.
It is the opposite parties case that the surveyor in his report specifically stated that there were no external/physical damages to the cabin and also to the external parts except the mud/slush marks over the travel motor assembly and track motor assembly areas and after the dismantling of the engine also no physical damages were found to travel motor, main pump, fan pump and swing motors. The surveyor also observed “ had the operator stopped the engine, when he noticed the excavator is sinking, there would be no loss/damage as there is no possibility of entering the mud water into the engine in stopped condition, and therefore the loss is due to wilful negligence of the insured”. Therefore they submit that their repudiation is justified and seek the dismissal of the complaint with costs.
6) The complainant in proof of his case filed the affidavit evidence of the Managing Director and Exs. A1 to A13 are marked on their behalf. The opposite parties filed the affidavit evidence of Senior Legal Executive and Exs. B1 to B6 are marked on their behalf. The insurance surveyor also filed his affidavit evidence.
7) The counsel for the opposite parties filed her written arguments.
8) The points that arise for consideration are:
i) Whether there is any deficiency of service on behalf of opposite parties?
ii) whether the complainant is entitled to the reliefs sought for in the complaint?
9) The facts not in dispute is the issuance of Contractors Plant & Machinery Policy for a period of one year commencing from 26.6.2010 to 25.6.2011 evidenced under Ex. A1 which is the policy schedule. Ex. A3 is the claim made by the complainant to the opposite parties with respect to the damaged excavator. Ex. A4 is the letter written by the complainant to Ops on 10.11.2010 informing about the damage caused to the excavator. Ex. A5 is the bunch of bills relating to the repair charges of the concerned excavator which are as follows :
S.No. | Description | Rs. |
1. | Z-670MP | |
| 38032333-Spares | 49,122.82 |
| 38032334- Service | 44,120.00 |
2. | Z-670 TM | |
| 38032335 - Spares | 53,386.77 |
| 38032336 - Service | 44,120.00 |
3. | Z-670 SM | |
| 38032337 - Spares | 7,505.49 |
| 38032338 - Service | 44,120.00 |
4. | Z-670 Fan Pump | |
| 38032339 - Spares | 35,591.19 |
| 38032340 - Service | 19,854.00 |
5. | Z-670 ENG | |
| 38032343- Spares | 45,19,677.44 |
| 38032344 - Service | 71,695.00 |
They are issued by TELCON for Rs. 48,89,193/- for which TELCON had issued a receipt vide Ex. A7 dt. 15.7.2011 for an amount of Rs. 48,89,193/-. Ex. A8 is the legal notice got issued by the complainant to Ops on 13.9.2011 calling upon them to settle the claim for which Ops replied vide Ex. A9 dt. 29.9.2011 enclosing the surveyor’s report and stated in this letter that the claim is repudiated as per Exception (b) of the policy which reads as follows :
(b) Loss of damage due to electrical or mechanical breakdown, failure, breakage or derangement, freezing of coolant or other fluid, defective lubrication or leak of oil or coolant, but if as a consequence of such breakdown or derangement an accident occurs causing external damage, such consequential damage will be indemnifiable.
Ex. A10 is the surveyor’s report wherein the assessed loss (as per XL) is Rs. 41,45,199/- and the net assessed loss is Rs. 23,26,060/-. Ex. A12 is the legal notice got issued by the complainant to the opposite parties to settle the claim with interest and costs.
10) It is the main case of the opposite parties that the claim cannot be settled as it falls under Exclusion (b) of the policy and that the loss or damage due to electrical or mechanical breakdown, failure, breakage or derangement, freezing of coolant or other fluid, defective lubrication and also because of the negligent operation of the excavator by the operator are not indemnifiable. The learned counsel for the opposite parties relied on Exs. B3 & B4 which are workshop component failure analysis report dt. 22.11.2010 and the service report dt. 30.10.2010 respectively. The conclusion in Ex. B4 reads as follows :
As per the observations it is confirmed that actually the machine was submerged in the mud water up to tappet cover level of the engine, complete main pump, radiator, counter weight and engine was submerged in the loose mud water and after that mud water entered from muffler and further entered inside the engine through exhaust valve and mixed with engine oil. After the incident, the machine was run for quite some time to swing the machine to opposite side, due to mud water contamination with engine oil, the engine got seized.
Keeping in view this inspection report, the opposite parties contended that if the operator had immediately switched off the engine when the excavator had fallen in the sump, the mud water would not have entered into the excavator and its consequential loss could have been averted. It is only because of the negligent operation of the excavator operator that this occurred and submit that their repudiation is justified.
11) Though the opposite parties relied on Exception (b) of the policy which reads as follows :
Loss of damage due to electrical or mechanical breakdown, failure, breakage or derangement, freezing of coolant or other fluid, defective lubrication or leak of oil or coolant, but if as a consequence of such breakdown or derangement an accident occurs causing external damage, such consequential damage will be indemnifiable.
We observe from the material on record that there is no documentary evidence to establish that the damage was due to mechanical or electrical breakdown, failure or derangement or defective lubrication etc. It is the case of the opposite parties that the operator should have immediately stopped the engine and only because of his negligence the entire engine got damaged. We observe from the statement and also the findings of the surveyor that the operator only tried his best to get the excavator out of the sump and that the engine had stopped by itself.
12) The surveyor in Ex. B5 dt. 25.9.2011 reported the statement of Sri Gopal Reddy, operator of the excavator as follows :
I Gopal Reddy, working as Operator in excavator No. 672-6 with BGR & Co. Medipally, Open Cast mine since 19.8.2009. There is a sump nearby which is about 5 meters depth and due to recent rains, the mud and silt accumulated in the sump while loading, I have checked the sump with the bucket and started loading. Since the sump was in vertical and when I tried to turn the track chains, due to coal underneath the track chain, the excavator leaned into the sump. Since the engine, hydraulic pump, become counter-weight as they are located in rear side. The excavator went into the sump and stranded in the sump up to the silencer level. Since it was sinking, I tried to swing the excavator to pull up with the bucket support, but the engine was stopped.
13) The aforementioned statement only establishes that the excavator did fall into the sump which is about 5 mtrs depth and due to recent rains, the mud and silt accumulated in the sump. This fact has not been disputed by the opposite parties. The fact remains that the excavator fell into the sump and that there was mud and silt accumulated in the sump because of rains. The statement of the operator only establishes that he tried his level best to get the excavator out of the sump as he tried by swinging the excavator to pull up with the bucket support but by then the engine had stopped. This statement in no way evidences that there was negligence or wilful operation by the excavator operator. It only manifests that the operator had tired his level best to pull out the excavator from out of the sump. In his findings the surveyor has stated that the excavator was found with mud and slush at the travel motor assembly and track motor assembly areas. It is also not in dispute that the engine was stopped and was removed which the surveyor had inspected. The service engineer of TELCON informed the surveyor to inspect whether there are damages to the internal parts. Upon dismantling the engine the surveyor found the following damages:
S.No. | Description | Remarks |
1 | Linear set of engine cylinder | Found with scoring marks |
2 | Camshaft | Found with scoring marks |
3. | Crankshaft | Scoring/rubbing marks found, due to insufficient lubrication |
4. | Rod assembly | Scoring/rubbing marks found, due to insufficient lubrication |
5. | Pump assembly - water | Non-functioning |
6 | Turbo charger | Play in shaft and failure of oil seal |
7. | Pump assembly - INJ | Water entered into the fuel supply pump and caused wear out of pump. |
8 | Nozzle assembly - INJ | Water entered into the fuel supply pump and caused wear out of nozzle |
9. | Pump assembly - Oil | Blocked |
10 | Block assembly - Cylinder | Scored and housing damage has occurred |
11 | Engine control module | Malfunctioning when checked on other engine. |
14) The aforementioned table shows that the engine was damaged. It is the case of the opposite parties that it was damaged due to mechanical break- down. The meaning of ‘mechanical break-down reads as follows:
“A Mechanical Breakdown is defined as the inability of a covered part(s) to perform the function(s) for which it was designed, due solely to defects in materials or faulty workmanship. Note: Mechanical breakdown does not include damage due to negligence, damage caused by an accident, or the gradual reduction in operating performance due to wear and tear.
15) In the instant case the excavator accidentally fell into the sump and has nothing to do with the mechanical break-down as we could see that that the mechanical break-down excludes wear and tear and also any defect in the equipment which in the instant case the damage resulted only because of the accidental fall into the sump. The excavator was working without any problem prior to this fall which occurred in the third shift due to operations in open cast mines. Therefore, we are of the considered view that the damage caused to the excavator is not due to mechanical break down and the repudiation by the opposite parties under the Exception (b) of the policy is not justified, and amounts to deficiency in service.
16) Now we address ourselves to the claim made by the complainant and the report of the surveyor. The summary of the loss assessment made by the surveyor is as follows :
Description | Amount (Rs.) |
Claimed amount | 4889193 |
Assessed Loss (as per Ex-cel) | 4145199 |
Less: Depreciation @ 30% | 1243559.70 |
Assessed Loss | 2901639.30 |
Less: Salvage | 70000 |
Assessed Loss | 2831639.30 |
Under insurance factor (Rs. 15304000/Rs. 17480000) | 0.8755 |
Loss after under insurance | 2479100.20 |
Less: Policy excess @ 1% of S.I. | 153040 |
Net assessed loss | 2326060.20 |
The aforementioned table shows that the deprecation at 30% was deducted and the surveyor has not stated anywhere as to how he arrived at depreciation except for stating that it depends on the life of the parts and that the details are reflected in the Excel sheet. When the excavator for which insurance was taken the value was assessed at Rs. 1,53,04,000/- as per Ex. B1 policy and the policy was issued just four months prior to the accident i.e., on 26.6.2010, we are of the considered view that depreciation at 10% would meet the ends of justice and this could be deducted from the claimed amount. At the same time salvage of Rs. 70,000/- and as well as policy excess at 1% as per the terms of the policy are to be deducted.
17) We also rely on the judgement of National Commission in New India Assurance Company Ltd Vs. M/s Dani Mourdhwaj Cold Storage Pvt. Ltd. in R.P. No. 4113 OF 2007 decided on 10. 2. 2012 in which the National observed that:
“The Surveyor has not recorded any reasons on the basis of which he has assessed the total value of the cold storage as Rs.1,20,00,000/-. The contention of the Counsel for Petitioner that this was done after taking into account the quotations obtained from three contractors which form a part of the Surveyor’s report does not inspire much confidence because the quotations were only in respect of the insulation system wherein the contractors assessed its cost to be between Rs.12,11,000/- to 13,11,082/- while the Surveyor has assessed it to be Rs.17,61,534/- without assigning any reasons. In the same way, we are unable to accept the other valuations in the absence of any reason whatsoever for recording these findings.
In view of these facts, we agree with the finding of the State Commission regarding the loss in respect of the cold storage and potatoes on the basis of Surveyor’s report without taking into account the deductions made for under insurance and uphold the same.”
Even in the instant case, we observe that the surveyor has not given any substantial reasons as to how the valuation made by the insurance company at the time of issuance of policy is wrong. There are no detailed reasons recorded by the surveyor the basis on which he has assessed the total value of the excavator at Rs. 1,74,80,000/- whereas the damage excavator as per the policy is Rs. 1,53,04,000/-. In his report he stated that he has arrived this amount “by deducting trade discount of 5% and adding duties, taxes and transportation @ 15% from the quotation of TELCON dt. 4.1.2011. Hence underinsurance is applicable”. There is no rule position which has been filed by the surveyor in support of this calculation of under insurance. Hence the amount which has been deducted by the surveyor against underinsurance is being disallowed.
Description | Amount (Rs.) |
Loss assessed by surveyor | 4145199.00 |
Less: Depreciation @ 10% | 414519.90 |
Assessed loss | 3730679.10 |
Less: Salvage | 70000.00 |
Assessed loss | 3660679.10 |
Less: policy excess @ 1% of SI | 153040.00 |
Net Assessed Loss | 3507639.10 |
Rounded off to Rs. 35,07,639/-
18) To reiterate, we also observe from the record that the complainant paid an amount of Rs. 48,89,193/- by way of cheque to TELCON evidenced under Ex. A6 for which TELCON issued receipt evidenced under Ex. A7. Ex. A5 a bunch of receipts also evidences that the complainant had paid Rs. 48,89,193/- towards repairs.
19) Therefore, we are of the considered opinion that an amount of Rs. 35,07,639/- may be paid against the claim of Rs. 48,89,193/- with interest @ 9% p.a., from the date of repudiation till the date of realization together with costs of Rs. 5,000/-.
20) In the result this complaint is allowed in part directing the opposite parties to pay Rs. 35,07,639/- with interest @ 9% p.a., from the date of repudiation i.e., from 29.9.2011 till the date of realization together with costs of Rs. 5,000/-. Time for compliance four weeks.
1) _______________________________
PRESIDING MEMBER
2) ________________________________
MEMBER
APPENDIX OF EVIDENCE
WITNESSES EXAMINED FOR
COMPLAINANT OPPOSITE PARTIES
None None
DOCUMENTS MARKED FOR COMPLAINANT:
Ex. A1 30.06.2010 Copy of Policy schedule
Ex. A2 30.05.2077 Copy of invoice of TELCON.
Ex. A3 22.07.2011 Notification of physical loss or damage
Ex. A4 10.11.2010 Letter addressed by S. Gopal Reddy to Op company
Ex. A5 --- Bunch of bills issued by TELCON.
Ex. A6 14.07.2011 Copy of cheque issued by complainant to TELCON
For Rs. 48,89,193/-
Ex. A7 15.07.2011 Receipt issued by TELCON to complainant for Rs.
48,89,193/-
Ex. A8 13.09.2011 Legal notice got issued by complainant to Ops.
Ex. A9 20.09.2011 Reply of Ops to Ex. A8 notice.
Ex. A10& 25.09.2011 Copy of survey report of Intech along with covering letter
Ex. A11
Ex. A12 22.12.2011 Another legal notice got issued by the complainant to Ops.
Ex. A13 23.02.2012 Reply of Ops to Ex. A12 notice
DOCUMENTS MARKED FOR O.Ps:
Ex. B1 30.06.2010 Policy schedule
Ex. B2 10.11.2010 Original letter addressed by S. Gopal Reddy to Op
company
Ex. B3 22.11.2010 Copy of Workshop Component Failure Analysis Report.
Ex. B4 30.10.2010 TELCON service report.
Ex. B5 25.09.2011 Original survey report of Intech.
Ex. B6 16.04.2012 Reply notice of Ops addressed to complainant.
1) _______________________________
PRESIDING MEMBER
3) ________________________________
MEMBER
28/06/2013
*pnr
UP LOAD – O.K.