THE DIST.CONSUMER DISPUTES REDRESSAL COMMISSION, KHURDA, BHUBANESWAR:
-ooOoo-
C.D.CASE NO.144/ 2021
Bichitrananda Tripathy, aged about 65 years,
S/o Late – Basudev Tripathy, At – Sital Vihar, Village/ PO- Turanga,
Ps/ Dist – Angul, Pin - 759123
…. Complainant
-Vrs.-
Orissa Construction & Techno Engineering
Co-Operative Society Ltd., At present:
Behind HDFC Bank, Patia Branch,
Sampark Vihar, 1st Lane, Nandankanan Road,
PO- KIIT, Patia, Bhubaneswar – 751024,
Dist – Khurda, Email – octecsociety @ gmail.com,
Represented by
- Niranjan Routray - President,
- Kulamani Parida – Secretary
- Jayanta Kumar Mohanty – Administrative Officer
…. Opp. Parties
For the complainant : M/s B.K.Routray & Associates (Adv.)
For the O.Ps. : Exparte
DATE OF FILING : 23/06/2021
DATE OF ORDER : 06/06/2023
ORDER
K.C.RATH, PRESIDENT
1. This is an application U/s 35of the C.P.Act, 2019.
2. The complainant’s case in brief is that, the OPs floated an advertisement in Odiya Daily “Sambad” for sale of housing plots at six numbers of places in Bhubaneswar. As per the said advertisement, the complainant submitted application for allotment of a residential plot. The OPs asked him to deposit a sum of Rs.1,72,500/- in installments towards cost of the land extending over 2500 sqft. Accordingly, the complainant deposited Rs.86,250/- on 28/10/1998 vide bank draft No.251198 and Rs.84,000/- in cash on 23/06/1999. At the first instance, the OPs allotted a plot to the complainant at Chandrasekharpur complex (BDA), Bhubaneswar. Subsequently, the OPs asked the complainant to change his choice of location of plot. Finally, the OPs allotted a plot measuring an area of 1800 sqft at Chandrasekharpur residential zone, BDA, Phase-II scheme of O.C. & T.E.C.S Ltd., Bhubaneswar. But that plot could not be demarcated due to law & order problem and finally the complainant came to know that, a civil suit is pending on the said plot of land. When the OPs could not allot any plot of land to the complainant, they returned the advance money with interest @ 6% per annum to the complainant in the year 2021. As the complainant could not get a plot of land from the OPs, he files this complaint.
3. On the other hand, the OPs did not appear in the case, as such they were set exparte and exparte hearing is taken up.
4 Perused the materials on record. Admittedly, the complainant in response to the advertisement made by the OPs, applied for allotment of a residential plot and for that, he had paid advance money of Rs.1,72,500/-. The OPs time & again asked the complainant to change his choice of location of the plot. Finally the plot which was allotted to the complainant could not be demarcated due to civil litigation in respect of the land and for law & order problem. Finally, the OPs returned the advance amount with interest @ 6% per annum to the complainant who admits receipt of the said amount. The complainant paid the advance money in the year 1998 & 1999. But he got back his money in the year 2021. The complainant suffered for about 23 years in order to get a plot of land from the OPs. Considering the totality of the fact & circumstances of the case, it appear that the OPs were at fault for which the complainant suffered a lot. The reliefs claimed for by the complainant are not tenable in the facts & circumstances of the case. More so, the Consumer Commission cannot order for specific performance of contract in respect of immovable property. Be that as it may, the complaint bears some merit. Hence it is ordered.
ORDER
The complaint is allowed in part exparte against the OPs. The OPs are directed to pay compensation of Rs.50,000/- (Rupees fifty thousand) only to the complainant towards mental agony suffered by him and a further sum of Rs.5000 /- (Rupees five thousand) only towards litigation expenses. The order be complied with by the OPs within a period of thirty days from the date of communication of this order, failing which the complainant will be at liberty to execute the order against the OPs in accordance with law.
The order is pronounced on this day the 6th June, 2023 under the seal & signature of the President and Member of this Commission.
(K.C.RATH)
PRESIDENT
Dictated & corrected by me
President
I agree
(S.Tripathy)
Member (W)
Transcribed by Smt. M.Kanungo, Sr.Steno